Questions_and_Answers_Oakland_Inner_and_Outer_30_April_2019.pdf

PDF 204 KB Posted

Attached to
Oakland Inner and Outer Harbor Channels Maintenance Dredging Project, Alameda County, California
Solicitation number
W912P719B0001
Issued by

About this file

Questions and Answers - Oakland Inner and Outer.pdf

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

OAKLAND INNER AND OUTER HARBOR CHANNEL MAINTENANCE

DREDGING PROJECT, ALAMEDA COUNTY, CALIFORNIA

AS OF: 30 April 2019 Page 1 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P719B0001

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.

No. RFP Section Question Response

Section 01 11 00 1.1.1 states:

The Contractor shall place the first 456,000 cubic yards of dredged material from Reaches 1-9 and 10B, (including paid and non-paid overdepth) at the Contractor-furnished permitted beneficial use upland site as cover before 15 November.

After the Government and the Contractor agree in writing that 456,000 cubic yards of dredged material have been placed at the Contractor-furnished permitted beneficial use upland site as cover, the remainder of the dredged material may be disposed at the Government-furnished deep ocean disposal site SF-DODS, or at the Contractor-furnished beneficial use upland site except Reach 10A.

Dredged material from Reach 10A shall be disposed at SF-DODS only before 15 November 2019.

Can you confirm that Reach 10A may be disposed at a Contractor furnished beneficial use upland site?

No, material from reach 10A shall be placed at SF-DODS.

2 3.5.1 Preconstruction Air Permits in Section 01 57

19 states “Notify the Air Program Manager, through the Contracting Officer, at least 6 months prior to bringing equipment… onto the Installation, so that air permits can be secured.

Necessary permitting time must be considered in regard to construction activities. Clean Air Act (CAA) permits must be obtained prior to bringing equipment, assembled or unassembled, onto the Installation.” Is this paragraph applicable to this work?

No, this paragraph is not applicable and will be removed.

Amendment forthcoming.

AS OF: 30 April 2019 Page 2 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P719B0001

3 3.1.4 Water Quality Monitoring in Section 01 57

19 indicates that no decanting from scows will be allowed on the first day of dredging and that, starting on the second day of dredging, decanting will be required for 5 to 10 consecutive dredging days so that the Government can perform water quality monitoring. When water quality monitoring has completed, may the Contractor continue to decant for the remainder of dredging operations?

Yes, decanting will be allowed after completion of the Water Quality Monitoring if no exceedances are recorded during monitoring phase. USACE will inform the Contractor at the end of the monitoring period.

4 3.4.5 San Francisco Deep Ocean Disposal Site

(SF-DODS) in Section 35 20 24 states "Disposal quantity limits for SF-DODS are established on a project-specific basis. The Contractor shall limit disposal quantities to those amounts specified in the Government-provided regulatory guidance."

What is the referenced Government-provided regulatory guidance, and may the Contractor assume that the quantities anticipated for disposal at SF-DODS in the Bid Schedule will not exceed the limits?

Refer to the documents in Section 1.1 (References).

5 Sheet G-03 of the Contract Drawings calls out

“!Caution! Sub-marine BART Tube Area of Special Handling". Above this call out, a note indicates "See Section 35 20 23 Dredging, Paragraph 3.2.9". However, Paragraph 3.2.9 of Section 35 20 23 discusses how the Contractor should handle salvaged material but does not mention the BART Tube. Should there be language in the Specifications that addresses the BART Tube or special handling near it?

Reference to Section 35 20 23 on the drawing will be removed. Amendment forthcoming.

The information that is provided on the drawing is sufficient to inform the Contractor regarding the location and depth of the tube.

AS OF: 30 April 2019 Page 3 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P719B0001

Clause 52.211-10 Commencement, Prosecution, and Completion of Work (Apr 1984) of Section 00 72 00 states “The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 190 calendar days after receipt of notice to proceed.” However, Paragraph 1.1 Project Description and 1.1.1 Requirements of Section 01 11 00 indicate that work may not begin before June 1st and must be completed by November 15th. If NTP were received in order to start work on June 1st this would only allow 172 calendar days to complete by the November 15th deadline. Can the Owner please clarify the schedule and number of days the Contractor has to complete the work?

In water work window is between 1-June and 30-Nov.

Amendment with the November 30 end date is forthcoming.

Line Item 0001 in the Bid Schedule refers to Mobilization and Demobilization for the FY18 Dredging Cycle. Please modify this line item to reflect the cost of Mobilization and Demobilization for the FY19 Dredging Cycle.

Corrected. Amendment forthcoming.

3.2.5 Municipal Separate Storm Sewer Systems

(MS4) Management in Section 01 57 19 states “Comply with the Installation’s MS4 permit requirements.” If applicable to this work, what are Installation MS4 permit requirements?

This paragraph is not applicable. Amendment

The SF1449 states that the remaining estimated 300,000cy of material may be dredged and disposed at SF-DODS or at the Contractor furnished beneficial use upland site but Line Items 0004-0012 (which contain the 300,000cy of material) on the Pricing Schedule only specify disposal at SF-

DODS.

a. Can the remaining 300,000cy of materials be disposed of at a Contractor furnished beneficial use upland site?

No, the 300,000CY shall go to SF-DODs.

AS OF: 30 April 2019 Page 4 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P719B0001

1.1.1 Requirements in Section 01 11 00 states

“The Contractor shall place the first 456,000 cubic yards of dredged material from Reaches 1-9 and 10B, (including paid and non-paid overdepth) at the Contractor-furnished permitted beneficial use upland site as cover before 15 November. After the Government and the Contractor agree in writing that 456,000 cubic yards of dredged material have been placed at the Contractor-furnished permitted beneficial use upland site as cover, the remainder of the dredged material may be disposed at the Government-furnished deep ocean disposal site SF-DODS, or at the Contractor-furnished beneficial use upland site except Reach 10A.” Will the Government allow disposal of dredged material at SF-DODS prior to, or concurrent with, upland disposal?

Section 01 11 00, paragraph 1.1.1 has been modified.

Amendment forthcoming.

Section 35 20 23, paragraph 3.2.1 (Order of Work) has been removed. Amendment forthcoming.

Yes, upon direction from the Contracting Officer, the sequence of work can be altered. The required amount for both the upland placement and the disposal at SF-DOD shall be accomplished within the November 30 end date (environmental window).

1.1.1 Requirements in Section 01 11 00 states

“The Contractor shall place the first 456,000 cubic yards of dredged material from Reaches 1-9 and 10B, (including paid and non-paid overdepth) at the Contractor-furnished permitted beneficial use upland site as cover before 15 November.”

However, the Pricing Schedule indicates that material from Reaches 1 and 2 will be placed upland and all other material will be placed at SF- DODS. Will an equitable adjustment be allowed if material beyond Reaches 1 and 2 is required to be placed upland to satisfy the 456,000 CY requirement?

Section 01 11 00, paragraph 1.1.1 (Requirements) has been modified. Amendment forthcoming.

Yes, this is only if the Contractor is directed to place material obtained from reaches 1-9 and 10B to satisfy the 456, 000 CY upland placement amount.

1.1.1 Requirements in Section 01 11 00 states

“The Contractor shall place the first 456,000 cubic yards of dredged material from Reaches 1-9 and 10B, (including paid and non-paid overdepth) at the Contractor-furnished permitted beneficial use upland site as cover before 15 November.” Can the Contractor assume that all material, except that from Reach 10A, may be classified as cover material?

Yes.

1.1.1 Requirements in Section 01 11 00 states “All

dredging operations shall be completed by 15 November. Will the Government please consider modifying this requirement to allow dredging operations to continue through November 30th?

Yes, amendment with the November 30 end date is forthcoming

AS OF: 30 April 2019 Page 5 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P719B0001

Paragraph G in Section 3.1.3 Depth Measurement Procedures and Calibrations refers to the use of a 3rd party survey company. However, Section 35 20 23 Paragraph 1.5.6 Final Payment Quantities states, “The final payment quantities for each reach will be 100% of the payable quantity calculated from the Contractor’s Before-Dredge and After-Dredge surveys using the TIN to TIN method in EM 1110- 2-1003. The Government reserves the right to use contractor multi-beam survey data. The Contractor’s surveys shall be used unless there is evidence of collusion, fraud, or obvious error, documented.” Will the Government please confirm that there is no requirement for third party surveys on this contract, including conditional and progress payment surveys?

An amendment to Section 35 20 23, paragraph 3.3 (Measurement) requiring a third party survey is