QUESTIONS_AND_ANSWERS.pdf

PDF 291 KB Posted

Attached to
Water Quality Monitoring Surveys
Solicitation number
W912P718T0004
Issued by

View the file

Other files

File Type Posted
A.01.38_SOW_WQMP_for_FY18_OM_Dredging.pdf PDF
FAR_Provisions.pdf PDF
BLANK_B.03.3_PPQ-_Past_Performance_Questionnaire.pdf PDF
Line_Item_Template_WQ_Monitoring.xlsx XLSX spreadsheet
Contractor's_Experience_Form.docx DOCX document
WAGE_DETERMINATION.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS

Q: Who the Incumbent?

A: There is not a current contract in place.

Q: What is the Overall project Pricing of Water Quality Monitoring Surveys?

A: All acquisition more than 25 thousand dollars are posted on FBO. https://www.fbo.gov

Q: When did the dredging projects begin & finish in the past 3 years?

Q: What is the estimated duration for Redwood City Dredging?

A: Day 0 - Take turbidity reading for background measurement Day 1 - Start dredging (Digging) - Take measurements, dredger will not be decanting this day Day 2 - 6 - Take measurements through the day when dredge is decanting the scows.

If there are no exceedances between Day 2 - 6, monitoring will no longer be required.

Day 7 - 11 - If there are exceedances between Day 2 and/on Day 6 then an additional 5 days of measurements are required.

Therefore, period of performance may be 7 days (Day 0 - 6 of dredging) minimum up to 12 days (Day 0 - 11 of dredging).

Q: Please explain the Unit of Issue on the Line Item Template?

A: “Jobs” are the encompassing requirements to complete the task Water Quality Monitoring Survey which include all days anticipated to accomplish the task. Based on the PWS – Jobs would consist of 12 days total.

Q: What are the Duration of the Options?

A: The same as the Task – exercised at the discretion of the Government.