AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

OAKLAND INNER AND OUTER HARBOR CHANNEL MAINTENANCE DREDGING PROJECT, ALAMEDA COUNTY, CALIFORNIA

ENCL): This Amendment: (1) revises CLINs 0002 and 0003 to increase the estimated dredging quantities for the Fiscal Year 2018 dredging cycle; (2) deletes optional CLINs 0004, 0005, 0006, 0007, and 0008 to remove the Fiscal Year 2019 dredging cycle from the solicitation; and

(3) updates the Wage Determination to replace it with the most recently issued version of General Decision Number CA29.

1. CONTRACT ID CODE PAGE OF PAGES

1 93

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P718B0003

X 9B. DATED (SEE ITEM 11)

13-Jun-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

3-Jul-2018

CODE

US ARMY ENGINEER DISTRICT, SAN FRANCISCO

CONTRACTING DIVISION

1455 MARKET ST., 17TH FLOOR SUITE 1741

SAN FRANCISCO CA 94103-1398

W912P7 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

SOLICITATION, OFFER,

AND AWARD

(Construction, Alteration, or Repair)

1. SOLICITATION NO.

W912P718B0003

2. TYPE OF SOLICITATION 3. DATE ISSUED

12-Jun-2018

PAGE OF PAGES

X SEALED BID (IFB)

NEGOTIATED (RFP)

IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.

4. CONTRACT NO. 5. REQUISITION/PURCHASE REQUEST NO. 6. PROJECT NO.

7. ISSUED BY CODE W912P7 8. ADDRESS OFFER TO (If Other Than Item 7) CODE

US ARMY ENGINEER DISTRICT, SAN FRANCISCO

CONTRACTING DIVISION

1455 MARKET ST., 17TH FLOOR SUITE 1741

SAN FRANCISCO CA 94103-1398

TEL: FAX:

See Item 7

TEL: FAX:

9. FOR INFORMATION

CALL:

A. NAME

JAMES E GARROR

B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)

415-503-6988

SOLICITATION

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):

OAKLAND INNER AND OUTER HARBOR MAINTENANCE DREDGING PROJECT, ALAMEDA COUNTY, CALIFORNIA

PROJECT DESCRIPTION: The work includes annual maintenance dredging for the Oakland Inner and Outer Harbor federal navigation channel in Contra Costa County. This project has a Base for the FY18 Dredge Cycle to dredge the Inner and Outer Harbor to -50-f t (MLLW) plus 1-ft of paid over-depth to be transported and placed at a Contractor-furnished permitted beneficial use upland site and a portion of Reach 10 in the Outer harbor to be transported and disposed at the Government-furnished deep ocean disposal site SF-DODS. This project includes two Alternative Options; Alternative 1 Options is for the FY19 Dredge Cycle dredging the Inner and Outer Harbor to -50-f t (MLLW) plus 1-ft of paid over-depth to be transported to the Government- furnished site SF-DODS. Alternative 2 is for the FY19 Dredging Cycle dredging the Inner and Outer harbor to -50-f t (MLLW) plus 1-ft of paid over-depth with transportation and placement at a Contractor-furnished beneficial reuse upland site.

This requirement is for an Unrestricted Competition. It will be issued as an Invitation for Bids (IFB) which will result in the award of a single Firm Fixed price (FFP) contract.

The North American Industry Classification System (NAICS) Code applicable to this acquisition is: 237990

ESTIMATED COST RANGE IS BETWEEN: $10,000,000 - $25,000,000 - $100,000,000

11. The Contractor shall begin performance within 5 calendar days and complete it within 113140 calendar days after receiving award, X notice to proceed. This performance period is X mandatory, negotiable. (See 52.211-10 .)

12 A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?

(If "YES," indicate within how many calendar days after award in Item 12B.)

12B. CALENDAR DAYS

X YES NO

13. ADDITIONAL SOLICITATION REQUIREMENTS:

A. Sealed of fers in original and 1 copies to perf orm the work required are due at the place specified in Item 8 by 10:00 AM (hour) local time 13 Jul 2019 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing of fers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.

B. An of fer guarantee X is, is not required.

C. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.

D. Off ers providing less than 60 calendar days f or Government acceptance af ter the date off ers are due will not be considered and will be rejected.

NSN 7540-01-155-3212 1442-101 STANDARD FORM 1442 (REV. 4-85)

Prescribed by GSA FAR (48 CFR) 53.236-1(e)

20B. SIGNATURE

(REV. 4-85)STANDARD FORM 1442 BACK

TO SIGN

NSN 7540-01-155-3212

SOLICITATION, OFFER, AND AWARD (Continued) (Construction, Alteration, or Repair)

CODE FACILITY CODE

17. The offeror agrees to perform the w ork required at the prices specif ied below in strict accordance w ith the terms of this solicitation, if this offer is accepted by the Government in w riting w ithin ________ calendar days after the date offers are due.

the minimum requirements stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.)

AMOUNTS SEE SCHEDULE OF PRICES

18. The offeror agrees to furnish any required performance and payment bonds.

19. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)

AMENDMENT NO.

DATE

20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN

OFFER (Type or print)

AWARD (To be completed by Government)

21. ITEMS ACCEPTED:

22. AMOUNT 23. ACCOUNTING AND APPROPRIATION DATA

24. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

(4 copies unless otherwise specified)

CODE

(Insert any number equal to or greater than

20C. OFFER DATE

25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO

10 U.S.C. 2304(c) 41 U.S.C. 253(c)

CODE27. PAYMENT WILL BE MADE BY:26. ADMINISTERED BY

(Include ZIP Code)14. NAME AND ADDRESS OF OFFEROR 15. TELEPHONE NO. (Include area code)

See Item 14

(Include only if different than Item 14)16. REMITTANCE ADDRESS

30B. SIGNATURE

29. AWARD (Contractor is not required to sign this document.)

document and return _______ copies to issuing office.) Contractor agrees Your of f er on this solicitation, is hereby accepted as to the items listed. This award con-to f urnish and deliv er all items or perf orm all work, requisitions identif ied summates the contract, which consists of (a) the Gov ernment solicitation and on this f orm and any continuation sheets f or the consideration stated in this y our of f er, and (b) this contract award. No f urther contractual document is contract. The rights and obligations of the parties to this contract shall be necessary .

gov erned by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certif ications, and specif ications or incorporated by ref er-ence in or attached to this contract.

30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED 31A. NAME OF CONTRACTING OFFICER (Type or print)

30C. DATE

(Type or print)

TEL: EMAIL:

31B. UNITED STATES OF AMERICA 31C. AWARD DATE

BY

CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE

(Contractor is required to sign this28. NEGOTIATED AGREEMENT

(M ust be fully completed by offeror)OFFER

W912P7-18-B-0003

SECTION 00 10 00

PRICING SCHEDULE

OPTIONS WILL BE EVALUATED IN ACCORDANCE WITH FAR 52.217-5

THE CONTRACTOR SHALL FURNISH ALL PLANT, LABOR, MATERIAL,

EQUIPMENT, NECESSARY TO PERFORM ALL WORK IN STRICT ACCORDANCE

WITH THE TERMS AND CONDITIONS SET FORTH IN THE CONTRACT TO

INCLUDE ALL ATTACHMENTS THERETO.

Item Description Quantity Unit Unit Price Amount

BASE BID ITEMS – OAKLAND INNER AND OUTER HARBOR FY18 DREDGING CYCLE WITH

DISPOSAL AT A CONTRACTOR-FURNISHED PERMITTED BENEFICIAL REUSE UPLAND SITE

AND AT THE GOVERNMENT-FURNISHED DEEP OCEAN DISPOSAL SITE (SF-DODS)

0001 Mobilization and Demobilization, FY18 Dredging Cycle 1 Job $_______ $________

0002 Dredging, FY18 Dredging Cycle, Reaches 1-10A (cover) to -50-ft (MLLW) including 1-foot of Paid Overdepth with disposal at Beneficial Reuse Upland site.

0002AA Required Dredging to -50-ft MLLW at Oakland Harbor 158405,000 CY $______ $_______

0002AB Overdepth Dredging to -51-ft MLLW at Oakland Harbor 210200,000 CY $______ $_______

0003 Dredging, FY18 Dredging Cycle, Reaches 1-10B (cover & non-cover) to -50-ft (MLLW) including 1-foot of Paid Overdepth with disposal at SF-DODS.

0003AA Required Dredging to -50-ft MLLW at Oakland Harbor 2040,000 CY $______ $_______

0003AB Overdepth Dredging to -51-ft MLLW at Oakland Harbor 2030,000 CY $______ $_______

BASETOTAL BID PRICE (Item 0001 + Item 0002 + Item 0003) $______________

ALTERNATIVE 1 OPTION: BASE BID ITEMS PLUS OPTION BID ITEMS FOR FY19

DREDGING CYCLE WITH DISPOSAL AT SF-DODS

0004 Mobilization and Demobilization, (Option) FY19 Dredging Cycle 1 Job $______ $______

0005 Dredging, FY19 Dredging Cycle, (Option) to -50-ft (MLLW) including

1-foot of Paid Overdepth.

0005AA Required Dredging to -50-ft (Option) MLLW at Oakland Harbor 260,000 CY $______ $______

0005AB Overdepth Dredging to -51-ft (Option) MLLW at Oakland Harbor 270,000 CY $______ $______

ALTERNATIVE 1 OPTION BID PRICE (Option Item 0004 + Option Item 0005) $_______________

ADJUSTMENT TO ALTERNATIVE 1 OPTION BID PRICE -

Estimated Additional Foreseeable Costs to Government For Disposal at SF-DODS $_____810,620.00

EVALUATED ALTERNATIVE 1 OPTION BID PRICE

(Option Item 0004 + Option Item 0005 + $810,620.00) $_________________

ALTERNATIVE 1 EVALUATED BID:

BASE BID PRICE PLUS EVALUATED ALTERNATIVE 1 OPTION

BID PRICE (Item 0001 + Item 0002 + Item 0003 + Option Item 0004 + Option Item 0005 + $810,620.00) $_________________

ALTERNATIVE 2 OPTION: BASE BID ITEMS PLUS OPTION BID ITEMS FOR FY19

DREDGING CYCLE WITH DISPOSAL AT A CONTRACTOR-FURNISHED PERMITTED

BENEFICIAL REUSE UPLAND SITE AND AT THE GOVERNMENT-FURNISHED SF-DODS

0006 Mobilization and Demobilization, (Option) FY19 Dredging Cycle 1 Job $______ $______

0007 Dredging, FY19 Dredging Cycle, (Option) Reaches 1-10A (cover) to -50-ft

(MLLW) including 1-foot of Paid Overdepth with disposal at Beneficial Reuse Upland Site.

0007AA Required Dredging to -50-ft

(Option) MLLW at Oakland Harbor 250,000 CY

0007AB Overdepth Dredging to -51-ft (Option) MLLW at Oakland Harbor 260,000 CY $______ $______

0008 Dredging, FY19 Dredging Cycle, (Option) Reaches 10B (non-cover) to -50-ft

(MLLW) including 1-foot of Paid Overdepth with disposal at SF-DODS.

0008AA Required Dredging to -50-ft (Option) MLLW at Oakland Harbor 10,000 CY $______ $_______

0008AB Overdepth Dredging to -51-ft (Option) MLLW at Oakland Harbor 10,000 CY $______ $_______

ALTERNATIVE 2 OPTION BID PRICE (Option Item 0006 + Option Item 0007 + Option Item 0008) $_______________

ALTERNATIVE 2 EVALUATED BID:

BASE BID PRICE PLUS EVALUATED ALTERNATIVE 2 OPTION BID

PRICE (Item 0001 + Item 0002 + Item 0003 + Option Item 0006 + Option Item 0007 + Option Item 0008) $_________________

Notes:

*QUANTITY IS AN ESTIMATED AMOUNT, SEE SECTION 00700, FAR 52.211-18.

1. To be considered responsive, prices must be submitted on all individual items within the Bid Schedule. Failure to do so may be cause for rejection of bids.

2. Bidders must complete and submit attached “Dredging Plant and Equipment Schedule”, forms Page 1 and Page 2 as part of their solicitation package for bid evaluation. Failure to do so may cause the bid to be considered nonresponsive. The Contractor shall demonstrate that all necessary equipment will be available and committed to this contract.

3. The term "Job", which appears on the Pricing Schedule (Section 00 10

00) under “Unit” for BASE BID ITEM 0001 shall not apply to BID ITEM 0001, ALTERNATIVE 1 OPTION BID ITEM 0004, and ALTERNATIVE 2 OPTION BID ITEM 0006 shall be considered as a Lump Sum. The Variation in Quantity contract clause, FAR 52.211-18, shall not apply to BASE BID ITEM 0001, ALTERNATIVE 1 OPTION BID ITEM 0004, or ALTERNATIVE 2 OPTION BID ITEM 0006.

4. BASIS of AWARD: The contract will be awarded in accordance with FAR 52.214-19 Contract Award – Sealed Bidding – Construction. The estimate of additional foreseeable costs to the Government resulting from dredging with disposal at SF-DODS will be included in evaluating the bid amount provided for Alternative 1. For evaluation of bids, each offeror will be considered to have submitted two alternative bids: (1) Alternative 1 – Base Bid Price plus Evaluated Alternative 1 Option Bid Price; and (2) Alternative 2 – Base Bid Price plus Evaluated Alternative 2 Option Bid Price. The alternative bid with the lowest evaluated price, whether Alternative 1 or Alternative 2, will be considered for award as the most advantageous to the Government; however, if an Alternative 1 bid is selected for award, the awarded contract price will not include the price adjustment that reflects the Government’s additional foreseeable costs for disposal at SF-DODS.

5. Options will be evaluated for award purposes in accordance with FAR 52.217-5. Exercise of the options will be in accordance with FAR 17.207.

If the Option is exercised, the Government will provide notice of the exercise of the Option no later than 1 July 2019. Notice to Proceed for awarded Alternative Option will be issued so "in water" work may begin on 1 August of 2019.

65. The Government reserves the right to direct the Contractor to place dredged material at an environmentally acceptable alternate disposal site in accordance with the Change Clause FAR 52.243-4.

- End of Document –

W912P718B0003

CLAUSES INCORPORATED BY REFERENCE

52.214-3 Amendments To Invitations For Bids DEC 2016 52.214-4 False Statements In Bids APR 1984 52.214-5 Submission Of Bids DEC 2016 52.214-6 Explanation To Prospective Bidders APR 1984 52.214-7 Late Submissions, Modifications, and Withdrawals of Bids NOV 1999 52.214-18 Preparation of Bids-Construction APR 1984 52.214-19 Contract Award-Sealed Bidding-Construction AUG 1996 52.214-34 Submission Of Offers In The English Language APR 1991 52.214-35 Submission Of Offers In U.S. Currency APR 1991 52.225-12 Alt l Notice of Buy American Requirement--Construction MAY 2014

Materials Under Trade Agreements 52.236-28 Preparation of Proposals--Construction OCT 1997

CLAUSES INCORPORATED BY FULL TEXT

52.216-1 TYPE OF CONTRACT (APR 1984)

The Government contemplates award of a firm fixed price contract resulting from this solicitation.

(End of provision)

52.217-5 EVALUATION OF OPTIONS (JUL 1990)

Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

(End of provision)

52.233-2 SERVICE OF PROTEST (SEP 2006)

(a) Protests, as defined in section 33.101 of the Federal Acquisition Regulation, that are filed directly with an agency, and copies of any protests that are filed with the Government Accountability Office (GAO), shall be served on the Contracting Officer (addressed as follows) by obtaining written and dated acknowledgment of receipt from

U.S. Army Corps of Engineers, San Francisco District Attn: Contracting Officer, Room 1741 San Francisco, CA 94103-1398

(b) The copy of any protest shall be received in the office designated above within one day of filing a protest with the GAO.

(End of provision)

52.236-27 SITE VISIT (CONSTRUCTION) (FEB 1995)

(a) The clauses at 52.236-2, Differing Site Conditions, and 52.236-3, Site Investigations and Conditions Affecting the Work, will be included in any contract awarded as a result of this solicitation. Accordingly, offerors or quoters are urged and expected to inspect the site where the work will be performed.

52.236-21 Alt I Specifications and Drawings for Construction (Feb 1997) - APR 1984

Alternate I 52.236-26 Preconstruction Conference FEB 1995 52.242-13 Bankruptcy JUL 1995 52.242-14 Suspension of Work APR 1984 52.243-4 Changes JUN 2007 52.244-6 Subcontracts for Commercial Items NOV 2017 52.246-12 Inspection of Construction AUG 1996 52.248-3 Value Engineering-Construction OCT 2015 52.249-2 Alt I Termination for Convenience of the Government (Fixed- SEP 1996

Price) (Apr 2012) - Alternate I 52.249-10 Default (Fixed-Price Construction) APR 1984 52.253-1 Computer Generated Forms JAN 1991 252.201-7000 Contracting Officer's Representative DEC 1991 252.203-7002 Requirement to Inform Employees of Whistleblower Rights SEP 2013 252.203-7003 Agency Office of the Inspector General DEC 2012 252.204-7005 Oral Attestation of Security Responsibilities NOV 2001 252.205-7000 Provision Of Information To Cooperative Agreement Holders DEC 1991 252.209-7004 Subcontracting With Firms That Are Owned or Controlled By OCT 2015

The Government of a Country that is a State Sponsor of Terrorism

252.219-7003 Small Business Subcontracting Plan (DOD Contracts)--Basic MAR 2016 252.223-7004 Drug Free Work Force SEP 1988 252.225-7012 Preference For Certain Domestic Commodities DEC 2017 252.226-7001 Utilization of Indian Organizations and Indian-Owned SEP 2004

Economic Enterprises, and Native Hawaiian Small Business Concerns

252.227-7025 Limitations on the Use or Disclosure of Government- MAY 2013 Furnished Information Marked with Restrictive Legends

252.227-7033 Rights in Shop Drawings APR 1966 252.231-7000 Supplemental Cost Principles DEC 1991 252.232-7003 Electronic Submission of Payment Requests and Receiving JUN 2012

Reports 252.236-7000 Modification Proposals-Price Breakdown DEC 1991 252.236-7002 Obstruction of Navigable Waterways DEC 1991 252.243-7001 Pricing Of Contract Modifications DEC 1991 252.243-7002 Requests for Equitable Adjustment DEC 2012 252.244-7000 Subcontracts for Commercial Items JUN 2013 252.247-7023 Transportation of Supplies by Sea APR 2014 252.247-7024 Notification Of Transportation Of Supplies By Sea MAR 2000

CLAUSES INCORPORATED BY FULL TEXT

52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)

The Contractor shall be required to (a) commence work under this contract within 5 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 113140 calendar days after receipt of notice to proceed. The time stated for completion shall include final cleanup of the premises.

(End of clause)

52.211-12 LIQUIDATED DAMAGES--CONSTRUCTION (SEP 2000)

(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $3,400 for each calendar day of delay until the work is completed or accepted.

(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.

(End of clause)

UAI 5152.211-9000 Evaluation of Subdivided Items.

EVALUATION OF SUBDIVIDED ITEMS (MAR 1995)

Item Nos. 0002, 0003, 0005, 0007, 0008 are subdivided into two or more estimated quantities and are to be separately priced. The Government will evaluate each of these items on the basis of total price of its sub items. (End of clause)

UAI 5152.211-9001 Variations in Estimated Quantities – Subdivided Items.

VARIATIONS IN ESTIMATED QUANTITIES — SUBDIVIDED ITEMS (MAR 1995)

This variation in estimated quantities clause is applicable only to item Nos. 0002, 0003, 0005, 0007, 0008.

(a) Variation from the estimated quantity in the actual work performed under any second or subsequent sub-item or elimination of all work under such a second or subsequent sub-item will not be the basis for an adjustment in contract unit price.

(b) Where the actual quantity of work performed for item Nos. 0002AA, 0002AB, 0003AA, 0003AB, 0005AA, 0005AB, 0007AA, 0007AB, 0008AA, 0008AB is less than 85% of the quantity of the first sub-item listed under such item, the contractor will be paid at the contract unit price for that sub-item for the actual quantity of work performed and, in addition, an equitable adjustment shall be made in accordance with the clause Federal Acquisition Regulation (FAR) 52.211-18, Variation in Estimated Quantities.

(c) If the actual quantity of work performed under item Nos. 0002AA, 0002AB, 0003AA, 0003AB, 0005AA, 0005AB, 0007AA, 0007AB, 0008AA, 0008AB exceeds 115% or is less than 85% of the total estimated quantity of the sub-item under that item and/or if the quantity of the work performed under the second sub-item or any subsequent sub-item under item Nos. 0002AA, 0002AB, 0003AA, 0003AB, 0005AA, 0005AB, 0007AA, 0007AB, 0008AA, 0008AB exceeds 115% or is less than 85% of the estimated quantity of any such sub-item, and if such variation causes an increase or a decrease in the time required for performance of this contract the contract completion time will be adjusted in accordance with the clause FAR 52.211-18, Variation in Estimated Quantities.

(End of clause)

52.217-7 -- Option for Increased Quantity -- Separately Priced Line Item. (Mar 1989)

The Government may require the delivery of the numbered line item, identified in the Schedule as an option item, in the quantity and at the price stated in the Schedule. The Contracting Officer may exercise the option by written

General Decision Number: CA180029 06/29/2018 CA29

Superseded General Decision Number: CA20170029

State: California

Construction Types: Building, Heavy (Heavy and Dredging) and Highway

Counties: Alameda, Calaveras, Contra Costa, Fresno, Kings, Madera, Mariposa, Merced, Monterey, San Benito, San Francisco, San Joaquin, San Mateo, Santa Clara, Santa Cruz, Stanislaus and Tuolumne Counties in California.

BUILDING CONSTRUCTION PROJECTS; DREDGING PROJECTS (does not include hopper dredge work); HEAVY CONSTRUCTION PROJECTS (does not include water well drilling); HIGHWAY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.35 for calendar year 2018 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.35 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2018. The EO minimum wage rate will be adjusted annually.

Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date 0 01/05/2018 1 01/12/2018 2 01/19/2018 3 01/26/2018 4 02/09/2018 5 03/02/2018 6 04/06/2018 7 04/13/2018 8 05/04/2018 9 06/01/2018 10 06/15/2018 11 06/29/2018

* ASBE0016-004 06/25/2018

AREA 1: CALAVERAS, FRESNO, KINGS, MADERA, MARIPOSA, MERCED,

MONTEREY, SAN BENITO, SAN JOAQUIN, SANTA CRUZ, STANISLAUS &

TOULMNE COUNTIES

AREA 2: ALAMEDA, CONTRA COSTA, SAN FRANSICO, SAN MATEO & SANTA

CLARA COUNTIES

Rates Fringes

Asbestos Removal worker/hazardous material handler (Includes preparation, wetting, stripping, removal, scrapping, vacuuming, bagging and disposing of all insulation materials from mechanical systems, whether they contain asbestos or not) Area 1......................$ 30.81 22.71 Area 2......................$ 31.81 22.71

ASBE0016-008 01/01/2018

AREA 1: ALAMEDA, CONTRA COSTA, MONTEREY, SAN BENITO, SAN

FRANSICO, SAN MATEO, SANTA CLARA, & SANTA CRUZ

AREA 2: CALAVERAS, COLUSA, FRESNO, KINGS, MADERA, MARIPOSA,

MERCED, SAN JOAQUIN, STANISLAU, & TUOLUMNE

Asbestos Workers/Insulator (Includes the application of all insulating materials, Protective Coverings, Coatings, and Finishes to all types of mechanical systems) Area 1......................$ 35.36 22.98 Area 2......................$ 49.46 22.98

BOIL0549-001 10/01/2016

AREA 1: ALAMEDA, CONTRA COSTA, SAN FRANCISCO, SAN MATEO & SANTA

CLARA COUNTIES

AREA 2: REMAINING COUNTIES

BOILERMAKER

Area 1......................$ 43.28 37.91 Area 2......................$ 39.68 35.71

BRCA0003-001 08/01/2017

Rates Fringes

MARBLE FINISHER..................$ 32.60 15.31

BRCA0003-003 08/01/2017

Rates Fringes

MARBLE MASON.....................$ 44.60 26.83

BRCA0003-005 05/01/2017

Rates Fringes

BRICKLAYER

( 1) Fresno, Kings, Madera, Mariposa, Merced....$ 38.45 21.22 ( 7) San Francisco, San Mateo.......................$ 42.34 25.83 ( 8) Alameda, Contra Costa, San Benito, Santa Clara.......................$ 44.16 21.71 ( 9) Calaveras, San Joaquin, Stanislaus, Toulumne....................$ 39.66 20.76

(16) Monterey, Santa Cruz...$ 39.51 23.49

BRCA0003-008 09/01/2017

Rates Fringes

TERRAZZO FINISHER................$ 35.14 16.87

TERRAZZO WORKER/SETTER...........$ 44.11 26.36

BRCA0003-011 04/01/2018

AREA 1: Alameda, Contra Costa, Monterey, San Benito, San Francisco, San Mateo, Santa Clara, Santa Cruz

AREA 2: Calaveras, San Joaquin, Stanislaus, Tuolumne

AREA 3: Fresno, Kings, Madera, Mariposa, Merced

TILE FINISHER

Area 1......................$ 28.56 15.87 Area 2......................$ 25.60 14.30 Area 3......................$ 25.88 15.17 Tile Layer Area 1......................$ 47.77 18.29 Area 2......................$ 42.67 16.81 Area 3......................$ 38.15 17.70

CARP0022-001 07/01/2017

San Francisco County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 46.55 28.71 Journeyman Carpenter........$ 46.40 28.71 Millwright..................$ 46.50 30.30

CARP0034-001 07/01/2017

Rates Fringes

Diver Assistant Tender, ROV Tender/Technician...........$ 45.65 31.91 Diver standby...............$ 50.61 31.91 Diver Tender................$ 49.82 31.91 Diver wet...................$ 95.17 31.91 Manifold Operator (mixed gas)........................$ 54.82 31.91 Manifold Operator (Standby).$ 49.82 31.91

DEPTH PAY (Surface Diving):

050 to 100 ft $2.00 per foot 101 to 150 ft $3.00 per foot 151 to 220 ft $4.00 per foot

SATURATION DIVING:

The standby rate shall apply until saturation starts. The saturation diving rate applies when divers are under pressure continuously until work task and decompression are complete. The diver rate shall be paid for all saturation hours.

DIVING IN ENCLOSURES:

Where it is necessary for Divers to enter pipes or tunnels, or other enclosures where there is no vertical ascent, the following premium shall be paid: Distance traveled from entrance 26 feet to 300 feet: $1.00 per foot. When it is necessary for a diver to enter any pipe, tunnel or other enclosure less than 48" in height, the premium will be $1.00 per foot.

WORK IN COMBINATION OF CLASSIFICATIONS:

Employees working in any combination of classifications within the diving crew (except dive supervisor) in a shift are paid in the classification with the highest rate for that shift.

CARP0034-003 07/01/2017

Rates Fringes

Piledriver.......................$ 46.65 31.91

CARP0035-007 07/01/2017

AREA 1: Alameda, Contra Costa, San Francisco, San Mateo, Santa Clara counties

AREA 2: Monterey, San Benito, Santa Cruz Counties

AREA 3: Calaveras, Fresno, Kings, Madera, Mariposa, Merced, San Joaquin, Stanislaus, Tuolumne Counties

Modular Furniture Installer Area 1 Installer I................$ 25.61 20.42 Installer II...............$ 22.18 20.42 Lead Installer.............$ 29.06 20.92 Master Installer...........$ 33.28 20.92 Area 2 Installer I................$ 22.96 20.42 Installer II...............$ 20.01 20.42 Lead Installer.............$ 25.93 20.92 Master Installer...........$ 29.56 20.92 Area 3 Installer I................$ 22.01 20.42 Installer II...............$ 19.24 20.42 Lead Installer.............$ 24.81 20.92 Master Installer...........$ 31.83 20.92

CARP0035-008 08/01/2017

AREA 1: Alameda, Contra Costa, San Francisco, San Mateo, Santa Clara counties

AREA 2: Monterey, San Benito, Santa Cruz Counties

AREA 3: San Joaquin

AREA 4: Calaveras, Fresno, Kings, Madera, Mariposa, Merced, Stanislaus, Tuolumne Counties

Drywall Installers/Lathers:

Area 1......................$ 46.40 29.15 Area 2......................$ 40.52 29.15 Area 3......................$ 41.02 29.15 Area 4......................$ 39.67 29.15 Drywall Stocker/Scrapper Area 1......................$ 23.20 16.88 Area 2......................$ 20.26 16.88 Area 3......................$ 20.51 16.88 Area 4......................$ 19.84 16.88

CARP0152-001 07/01/2017

Contra Costa County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 46.55 28.71 Journeyman Carpenter........$ 46.40 28.71 Millwright..................$ 46.50 28.71

CARP0152-002 07/01/2017

San Joaquin County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.67 28.71 Journeyman Carpenter........$ 40.52 28.71 Millwright..................$ 43.02 30.30

CARP0152-004 07/01/2017

Calaveras, Mariposa, Merced, Stanislaus and Tuolumne Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold &

Steel Shoring Erector, Saw Filer.......................$ 39.32 28.71 Journeyman Carpenter........$ 39.17 28.71 Millwright..................$ 41.67 30.30

CARP0217-001 07/01/2017

San Mateo County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 46.55 28.71 Journeyman Carpenter........$ 46.40 28.71 Millwright..................$ 46.50 30.30

CARP0405-001 07/01/2017

Santa Clara County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 46.55 28.71 Journeyman Carpenter........$ 46.40 28.71 Millwright..................$ 46.50 30.30

CARP0405-002 07/01/2017

San Benito County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.58 28.71 Journeyman Carpenter........$ 40.52 28.71 Millwright..................$ 43.02 30.30

CARP0505-001 07/01/2017

Santa Cruz County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.67 28.71 Journeyman Carpenter........$ 40.52 28.71 Millwright..................$ 43.02 30.30

CARP0605-001 07/01/2017

Monterey County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 40.67 28.71 Journeyman Carpenter........$ 40.52 28.71 Millwright..................$ 43.02 30.30

CARP0701-001 07/01/2017

Fresno and Madera Counties

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 39.32 28.71 Journeyman Carpenter........$ 39.17 28.71 Millwright..................$ 41.67 30.30

CARP0713-001 07/01/2017

Alameda County

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 46.55 28.71 Journeyman Carpenter........$ 46.40 28.71 Millwright..................$ 46.50 30.30

CARP1109-001 07/01/2017

Kings County

Rates Fringes

Carpenters Bridge Builder/Highway Carpenter...................$ 46.40 28.71 Hardwood Floorlayer, Shingler, Power Saw Operator, Steel Scaffold & Steel Shoring Erector, Saw Filer.......................$ 39.32 28.71 Journeyman Carpenter........$ 39.17 28.71 Millwright..................$ 41.67 30.30

ELEC0006-004 12/01/2017

SAN FRANCISCO COUNTY

Rates Fringes

Sound & Communications Installer...................$ 38.52 3%+18.05 Technician..................$ 44.30 3%+18.05

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0006-007 06/01/2017

SAN FRANCISCO COUNTY

Rates Fringes

ELECTRICIAN......................$ 66.00 3%+43.40

ELEC0100-002 03/01/2018

FRESNO, KINGS, AND MADERA COUNTIES

Rates Fringes

ELECTRICIAN......................$ 37.50 22.18

ELEC0100-005 12/01/2016

FRESNO, KINGS, MADERA

Rates Fringes

Communications System Installer...................$ 30.64 3%+17.86 Technician..................$ 34.89 3%+17.86

SCOPE OF WORK

Includes the installation testing, service and maintenance, of the following systems which utilize the transmission and/or transference of voice, sound, vision and digital for commercial, education, security and entertainment purposes for the following: TV monitoring and surveillance, background-foreground music, intercom and telephone interconnect, inventory control systems, microwave transmission, multi-media, multiplex, nurse call system, radio page, school intercom and sound, burglar alarms, and low voltage master clock systems.

A. SOUND AND VOICE TRANSMISSION/TRANSFERENCE SYSTEMS

Background foreground music, Intercom and telephone interconnect systems, Telephone systems Nurse call systems, Radio page systems, School intercom and sound systems, Burglar alarm systems, Low voltage, master clock systems, Multi-media/multiplex systems, Sound and musical entertainment systems, RF systems, Antennas and Wave Guide, B. FIRE ALARM SYSTEMS Installation, wire pulling and testing

C. TELEVISION AND VIDEO SYSTEMS Television monitoring and surveillance systems Video security systems, Video entertainment systems, Video educational systems, Microwave transmission systems, CATV and CCTV

D. SECURITY SYSTEMS Perimeter security systems Vibration sensor systems Card access systems Access control systems, Sonar/infrared monitoring equipment

E. COMMUNICATIONS SYSTEMS THAT TRANSMIT OR RECEIVE

INFORMATION AND/OR CONTROL SYSTEMS THAT ARE INTRINSIC TO

THE ABOVE LISTED SYSTEMS SCADA (Supervisory Control and Data Acquisition) PCM (Pulse Code Modulation) Inventory Control Systems, Digital Data Systems Broadband and Baseband and Carriers Point of Sale Systems, VSAT Data Systems Data Communication Systems RF and Remote Control Systems, Fiber Optic Data Systems

WORK EXCLUDED Raceway systems are not covered (excluding Ladder-Rack for the purpose of the above listed systems).

Chases and/or nipples (not to exceed 10 feet) may be installed on open wiring systems. Energy management systems. SCADA (Supervisory Control and Data Acquisition) when not intrinsic to the above listed systems (in the scope). Fire alarm systems when installed in raceways (including wire and cable pulling) shall be performed at the electrician wage rate, when either of the following two

(2) conditions apply:

1. The project involves new or major remodel building trades construction.

2. The conductors for the fire alarm system are installed in conduit.

ELEC0234-001 05/28/2018

MONTEREY, SAN BENITO AND SANTA CRUZ COUNTIES

Rates Fringes

ELECTRICIAN

Zone A......................$ 44.65 24.44 Zone B......................$ 50.77 25.62

Zone A: All of Santa Cruz, Monterey, and San Benito Counties within 25 air miles of Highway 1 and Dolan Road in Moss Landing, and an area extending 5 miles east and west of Highway 101 South to the San Luis Obispo County Line

Zone B: Any area outside of Zone A

ELEC0234-003 12/01/2017

MONTEREY, SAN BENITO, AND SANTA CRUZ COUNTIES

Sound & Communications Installer...................$ 38.02 18.69 Technician..................$ 43.72 18.86

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0302-001 01/01/2018

CONTRA COSTA COUNTY

Rates Fringes

CABLE SPLICER....................$ 56.17 26.59

ELECTRICIAN......................$ 49.76 26.59

ELEC0302-003 12/01/2017

CONTRA COSTA COUNTY

Rates Fringes

Sound & Communications Installer...................$ 37.22 18.66 Technician..................$ 42.80 18.83

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0332-001 05/29/2017

SANTA CLARA COUNTY

Rates Fringes

CABLE SPLICER....................$ 69.60 34.318

ELECTRICIAN......................$ 60.52 34.046

FOOTNOTES: Work under compressed air or where gas masks are required, orwork on ladders, scaffolds, stacks, "Bosun's chairs," or other structures and where the workers are not protected by permanent guard rails at a distance of 40 to 60 ft. from the ground or supporting structures: to be paid one and one-half times the straight-time rate of pay.

Work on structures of 60 ft. or over (as described above):

to be paid twice the straight-time rate of pay.

ELEC0332-003 12/01/2017

SANTA CLARA COUNTY

Rates Fringes

Sound & Communications Installer...................$ 38.02 18.69 Technician..................$ 43.72 18.86

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0595-001 06/01/2018

ALAMEDA COUNTY

Rates Fringes

CABLE SPLICER....................$ 61.03 3%+35.72

ELECTRICIAN......................$ 54.25 3%+35.72

ELEC0595-002 06/01/2017

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

CABLE SPLICER....................$ 41.40 3%+28.83

ELECTRICIAN

(1) Tunnel work.............$ 38.86 3%+28.83

(2) All other work.........$ 36.00 3%+28.83

ELEC0595-006 12/01/2017

ALAMEDA COUNTY

Rates Fringes

Sound & Communications Installer...................$ 38.02 3%+17.96 Technician..................$ 43.72 3%+17.96

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0595-008 12/01/2017

CALAVERAS AND SAN JOAQUIN COUNTIES

Rates Fringes

Communications System Installer...................$ 38.02 3%+17.96 Technician..................$ 43.72 3%+17.96

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0617-001 06/01/2017

SAN MATEO COUNTY

Rates Fringes

ELECTRICIAN......................$ 57.00 33.59

ELEC0617-003 12/01/2017

SAN MATEO COUNTY

Rates Fringes

Sound & Communications Installer...................$ 38.02 19.27 Technician..................$ 43.72 19.27

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

ELEC0684-001 06/01/2018

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES

Rates Fringes

ELECTRICIAN......................$ 38.00 3%+21.33

CABLE SPLICER = 110% of Journeyman Electrician

ELEC0684-004 12/01/2016

MARIPOSA, MERCED, STANISLAUS AND TUOLUMNE COUNTIES

Rates Fringes

Communications System Installer...................$ 30.64 3%+17.86 Technician..................$ 34.89 3%+17.86

SCOPE OF WORK: Including any data system whose only function is to transmit or receive information; excluding all other data systems or multiple systems which include control function or power supply; inclusion or exclusion of terminations and testings of conductors determined by their function; excluding fire alarm work when installed in raceways (including wire and cable pulling) and when performed on new or major remodel building projects or jobs for which the conductors for the fire alarm system are installed in conduit; excluding installation of raceway systems, line voltage work, industrial work, life-safety systems (all buildings having floors located more than 75' above the lowest floor level having building access);

excluding energy management systems.

FOOTNOTE: Fire alarm work when installed in raceways (including wire and cable pulling), on projects which involve new or major remodel building construction, for which the conductors for the fire alarm system are installed in the conduit, shall be performed by the inside electrician.

* ELEC1245-001 06/01/2018

Rates Fringes

LINE CONSTRUCTION

(1) Lineman; Cable splicer..$ 56.79 17.91

(2) Equipment specialist (operates crawler tractors, commercial motor vehicles, backhoes, trenchers, cranes (50 tons and below), overhead & underground distribution line equipment)...........$ 45.36 16.74

(3) Groundman...............$ 34.68 16.36

(4) Powderman...............$ 49.55 3%+17.65

HOLIDAYS: New Year's Day, M.L. King Day, Memorial Day, Independence Day, Labor Day, Veterans Day, Thanksgiving Day and day after Thanksgiving, Christmas Day

ELEV0008-001…