Questions_and_Answers__Richmond__Inner_Harbor_August_8-21-2017.pdf

PDF 88 KB Posted

Attached to
RICHMOND INNER HARBOR CHANNEL MAINTENANCE DREDGING PROJECT, CONTRA COSTA COUNTY, CALIFORNIA
Solicitation number
W912P7-18-B-0001
Issued by

About this file

Questions and Answers Richmond Inner Harbor August 8-21-2018.pdf

View the file

Other files

File Type Posted
Bid_Results_Richmond_Inner_Harbor.pdf PDF
SF_07_RIH_20170609_BD_SORTED15.xyz XYZ file
DWF6 ePlot.pc3 —
RI-1b.jpg JPG image
DWG To PDF.pc3 —
Richmond_O&M_2018_Plans_Amendment.pdf PDF
W912P718B0001_AMENDMENT_0002_8-22-2018.pdf PDF
Richmond O&M 2018 TXT text file
Richmond O&M 2018 —
Arial.ttf TTF file
Richmond_Inner_O&M_2018 —
SF_07_RIH_20170609_BD_S&C.dxf DXF file
monochrome 2.ctb —
SF_07_RIH_20180803_CS_R4&11_SORTED15.XYZ XYZ file
Richmond_Inner_O&M_2018-LK REVISED.dwg DWG drawing
RI-2b.jpg JPG image
acad.fmp —
ariali.ttf TTF file
DWG To PDF 600 dpi image.pc3 —
arialbd.ttf TTF file
RI-3b.jpg JPG image
calibri.ttf TTF file
arialbi.ttf TTF file
ltypeshp.shx —
SF_07_RIH_20170609_BD_SORTED15.xyz XYZ file
romans.shx —
SF_07_RIH_20180803_CS_R4&11_SOUNDINGS.dxf DXF file
txt.shx —
ariblk.ttf TTF file
architectural imperial.dwt —
Richmond_O&M_2018_(Amendment)_-_Standard.zip ZIP file
W912P718B0001_AMENDMENT_0001.pdf PDF
SF_07_RIH_20170609_BD_S&C.dxf DXF file
Solicitation Drawings.pdf PDF
Richmond_Inner_O&M_2018 —
Richmond_Inner_O&M_2018.dwg DWG drawing
W912P7-18-B-0001_JULY_18_2018.pdf PDF
SF_07_RIH_20170609_BD_SORTED15.xyz XYZ file
Richmond_Inner_O&M_2018_(G01_-_G03).dwg DWG drawing
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RICHMOND INNER HARBOR CHANNEL MAINTENANCE

DREDGING PROJECT, CONTRA COSTA COUNTY, CALIFORNIA

AS OF: 21 August 2018 Page 1 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-18-B-0001

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.

No. RFP Section Question Response

Please confirm that it is at the contractor’s discretion to dispose of all project yardage at a contractor furnished upland site.

Confirm SF-DODS disposal is not a contract requirement.

The Contractor may dispose of all material at an upland site provided the site is permitted to receive both cover quality (Reach 4) and non-cover quality (Reach 11) material.

2 If all options are awarded, what is the total cumulative yardage available as it is displayed per the clins? The pricing schedule as it is written is unclear.

An amendment will inform bidders of revised quantities.

File details come from the government source that posted it.