Pre-Bid_Meeting_Minutes_20Aug15.pdf

PDF 64 KB Posted

Attached to
RICHMOND INNER AND OUTER HARBOR CHANNEL MAINTENANCE DREDGING PROJECT, CONTRA COSTA COUNTY, CALIFORNIA
Solicitation number
W912P7-15-B-0004
Issued by

About this file

Pre-Bid Meeting Minutes 20 August 2015.pdf

View the file

Other files

File Type Posted
B01_-_1_Abstract_of_Bids_Richmond_Inner_and_Outer_Harobr_Dredging_Project.pdf PDF
Questions_and_Answers__Richmond_Inner_and_Outer_Harbor_Dredging_8-26-15.pdf PDF
W912P7-15-B-0004_Amendment_0002.pdf PDF
Richmond_O M_Sheet 3 of 10.cal —
Richmond_O M_Sheet 5 of 10.cal —
Richmond_O M_Sheet 7 of 10.cal —
W912P7-15-B-0004_Amendment_0001_August_21_2015.pdf PDF
_Readme.txt TXT text file
Richmond_Cover Sheet 1 of 10.cal —
Richmond_O M_Sheet 2 of 10.cal —
Richmond_O M_Sheet 6 of 10.cal —
SF_07_RIH_20150723-24_CON_SORTED15.xyz XYZ file
Richmond_O M_Sheet 8 of 10.cal —
ROH_LW_20150727_CON_100_Sorted 15.xyz XYZ file
Richmond_O M_Sheet 4 of 10.cal —
Richmond_O M_Sheet 9 of 10.cal —
ROH_SHS_20150728_CON_100'_Sorted 15.xyz XYZ file
maxview513.exe EXE file
Richmond_O M_Sheet 10 of 10.cal —
Richmond_Pre_Bid_Meeting.pdf PDF
Richmond_Pre_Bid_Meeting.pdf PDF
Richmond_Inner_O M_Sheet 4 of 10.cal —
Richmond_Outer_O M_Sheet 9 of 10.cal —
(R9)SF_07_RIH_20150114_BD_R8 9_3x3Avg_MLLW.xyz XYZ file
W912P7-15-B-0004_Richmond_Final_Solicitation_and_Technical_Specifications_28Jul15.pdf PDF
(R8)SF_07_RIH_20150114_BD_R8 9_3x3Avg_MLLW.xyz XYZ file
Richmond_Outer_O M_Sheet 10 of 10.cal —
maxview513.exe EXE file
(R7)SF_07_RIH_R7BD_20141230_3x3Avg_MLLW.xyz XYZ file
_Readme.txt TXT text file
SF_07_ROH_20150220-23_CON_3x3Avg_MLLW_filled.XYZ XYZ file
(R6)20141125 Etrac RI R6 BD.xyz XYZ file
Richmond_Inner_O M_Sheet 5 of 10.cal —
Richmond_Outer_O M_Sheet 8 of 10.cal —
Richmond_Inner_O M_Sheet 6 of 10.cal —
Richmond_LongWharf Sheet 7 of 10.cal —
(R10)SF_07_RIH_20150126_R10_BD_3x3.xyz XYZ file
Richmond_Inner_O M_Sheet 3 of 10.cal —
Richmond_Reference_Sheet 2 of 10.cal —
(R2)SF_07_RIH_20150107_BD_R1-3_3x3Avg_MLLW.xyz XYZ file
(R4)RES_141125_Richmond_R4_3x3.xyz XYZ file
Richmond_Cover2015-Sheet 1 of 10.cal —
(R1)SF_07_RIH_20150107_BD_R1-3_3x3Avg_MLLW.xyz XYZ file
(R5)SF_07_RIH_20150114_BD_R5_3x3Avg_MLLW.xyz XYZ file
(R3)SF_07_RIH_20150107_BD_R1-3_3x3Avg_MLLW.xyz XYZ file
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Richmond Inner and Outer Harbor FY15 O&M Dredging Project

Pre-Bid Meeting

20 August 2015

Attendees Company E-Mail

Jeff Casey R.E. Staite Engineering JeffC@restaite.net

Eric McMann Manson Construction Co. EMcMann@mansonconstruction.com

Ross McDonnel R.E. Staite Engineering RossM@restaite.net

Rick Olejniczak GBA Engineering RAOlejniczak@gba-inc.com

Kristen Odroniec Manson Construction Co. KOdroniec@mansonconstruction.com

Jere Harper USACE – San Francisco Jere.B.Harper@usace.army.mil

David Doak USACE – San Francisco David.V.Doak@usace.army.mil

Summary of Work:

The Base work includes dredging Reaches 1 thru 10 of the Inner Harbor to -38-ft MLLW plus 1-ft of allowable paid over-depth, and an Option for Reaches 1 thru 3 of the Outer Harbor and the specified polygon areas in the Long Wharf maneuvering area to -45-ft MLLW plus 1-ft of allowable paid over-depth. Scow decant/overflow is allowed if the Contractor provides independent water quality monitoring in accordance with the Regional Water Quality Control

Board-approved WQ Monitoring Plan in Appendix 18 of the solicitation. All disposal of dredged material at the Government–furnished aquatic disposal sites (SF-DODS, SF-10, and SF-11) must cease after 30 November. Dredging may continue past 30 November with placement at a permitted beneficial use upland site of the Contractor’s choosing at no additional cost to the

Government. Contractor must provide California Department of Fish and Wildlife-approved herring observers for all dredging operations after 30 November.

Questions

1. Does the work in the Option for the Richmond Outer Harbor include the Long Wharf and

South Hampton Shoal Channel?

mailto:JeffC@restaite.net mailto:EMcMann@mansonconstruction.com mailto:RossM@restaite.net mailto:RAOlejniczak@gba-inc.com mailto:KOdroniec@mansonconstruction.com mailto:Jere.B.Harper@usace.army.mil mailto:David.V.Doak@usace.army.mil

Answer: Yes, the Option includes Polygons A and B in the Long Wharf maneuvering area and all of the South Hampton Shoal Channel. The advertised Option volumes in the

Pricing Schedule reflect the material in Polygons A and B and the South Hampton Shoal

Channel.

2. Will there be an amendment with updated volumes?

Answer: Yes, Amendment 001 will be issued shortly with revised volumes for a project depth of -38-ft instead of -37-ft. There will also be other minor changes in the specifications, and an updated Wage Determination and Water Quality Monitoring Plan.

3. Will the work window be extended for the Outer Harbor?

Answer: Yes, the work window will be extended without consultation beyond 30

November for the Outer Harbor if all of the dredged material is placed at a permitted beneficial use upland site, and at no additional cost to the Government.

File details come from the government source that posted it. Updated .