PINOL SHOAL CHANNEL MAINTENANCE DREDGING PROJECT,
CONTRA COSTA COUNTY, CALIFORNIA
AS OF: 15 July 2015 Page 1 of 7
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P7-15-B-0001
The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.
Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.
Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.
No. RFP Section Question Response
Section 52.246-21, WARRANTY OF CONSTRUCTION (MAR 1994), indicates the following:
(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.
(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the
Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.
Please clarify if a guarantee is required for dredging work after an area has been accepted by the USACE as complete.
A bid guarantee is required for the whole project, and not parts of the project.
The warranty is for the contractor’s performance of work during the execution of the contract and does not apply to shoaling material after acceptance.
AS OF: 15 July 2015 Page 2 of 7
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P7-15-B-0001
2 Section 35 20 23, DREDGING, 3.2.2.1
Dredging Plant state the following:
Dredging shall be performed by mechanical dredging plant only, equipped with a closed, environmental style bucket to reduce turbidity. The use of a hydraulic dredge is prohibited for this project to avoid impacts to the federally listed species.
It is requested that a clamshell bucket also be allowed for use.
See Amendment coming soon.
AS OF: 15 July 2015 Page 3 of 7
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P7-15-B-0001
3 SECTION 35 20 23, DREDGING 3.2.6.1
Overflow, Spillage and Leakage, state the following:
Scow overflow is allowed only during dredging operations while scow is being filled to its allowable capacity. Spillage and leakage of any and all dredge material or water is prohibited outside of areas specifically authorized for dredging in accordance with the project plans, specifications and permits. Any material that is spilled, escapes, leaks, sloughs, or is lost or misplaced outside of Dredged Material Management site(s) at any time during operations, to include but not limited to dredging, loading or transporting, shall be retrieved and deposited in accordance with the project plans, specifications and permits.
Based on the permits provided, it appears that decanting is only allowed if there is an approved monitoring plan that has been approved by the RWQCB. It is our understanding that a decanting monitoring plan may have prepared by the USACE and submitted to the RWQCB for review. It is requested that the monitoring plan be provided to the Contractor to be sure that all costs associated with the monitoring can be estimated prior to bid time, unless the USACE is providing all services associated with monitoring.
See Amendment coming soon.
4 Please provide the reference to the
FAR section that covers the Required insurance for the project.
FAR 28.307-2 Liability
AS OF: 15 July 2015 Page 4 of 7
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P7-15-B-0001
5 It does not appear that Section 35
20 23 DREDGING, 3.2.5.6 - Weather Delays was included in Section 35
20 23 DREDGING.
Please clarify the number of weather days allowed for this project.
All Weather delays will be in accordance with FAR 52.236-4.
AS OF: 15 July 2015 Page 5 of 7
QUESTIONS & RESPONSES
SOLICITATION NUMBER W912P7-15-B-0001
AS OF: 15 July 2015 Page 6 of 7
AS OF: 15 July 2015 Page 7 of 7