Questions_and_Answers_Pinol_Shoal_Dredging_7-15-2015_(2).pdf

PDF 94 KB Posted

Attached to
PINOLE SHOAL CHANNEL MAINTENANCE DREDGING PROJECT, CONTRA COSTA COUNTY, CALIFORNIA
Solicitation number
W912P7-15-B-0001
Issued by

About this file

Questions and Answers Pinole Shoal Dredging.pdf

View the file

Other files

File Type Posted
B01_-_1_Abstract_of_Bid_for_Pinole_Shoal_Channel_Maintenance_Dredging_Project.pdf PDF
SF_27_PSC_20150701-07_CON_10x10Avg_MLLW_Combined.xyz XYZ file
Pinole2015_5of7.cal —
plot.log LOG file
Pinole2015_6of7.cal —
maxview513.exe EXE file
Pinole2015_7of7.cal —
Pinole2015_2of7.cal —
W912P7-15-B-0001_Amendment_0001_July_16_2015.pdf PDF
Pinole2015_1of7.cal —
Pinole2015_3of7.cal —
_Readme.txt TXT text file
Pinole2015_4of7.cal —
Pre-Bid_Meeting_-_Pinole_Shoal_Channel_Maintenance_Dredging_Project.pdf PDF
aaa03784 —
W912P7-15-B-0001_June_17_2015.pdf PDF
Pinole Shoal O M 2015Sheet5of7 .cal —
maxview513.exe EXE file
Pinole Shoal O M 2015Sheet6of7 .cal —
Pinole Shoal O M 2015Sheet2of7 .cal —
_Readme.txt TXT text file
Pinole Shoal O M 2015Sheet7of7 .cal —
plot.log LOG file
Pinole Shoal Coversheet 2015 —
Pinole Shoal O M 2015Sheet4of7 .cal —
Pinole Shoal O M 2015Sheet3of7 .cal —
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PINOL SHOAL CHANNEL MAINTENANCE DREDGING PROJECT,

CONTRA COSTA COUNTY, CALIFORNIA

AS OF: 15 July 2015 Page 1 of 7

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-15-B-0001

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.

No. RFP Section Question Response

Section 52.246-21, WARRANTY OF CONSTRUCTION (MAR 1994), indicates the following:

(a) In addition to any other warranties in this contract, the Contractor warrants, except as provided in paragraph (i) of this clause, that work performed under this contract conforms to the contract requirements and is free of any defect in equipment, material, or design furnished, or workmanship performed by the Contractor or any subcontractor or supplier at any tier.

(b) This warranty shall continue for a period of 1 year from the date of final acceptance of the work. If the

Government takes possession of any part of the work before final acceptance, this warranty shall continue for a period of 1 year from the date the Government takes possession.

Please clarify if a guarantee is required for dredging work after an area has been accepted by the USACE as complete.

A bid guarantee is required for the whole project, and not parts of the project.

The warranty is for the contractor’s performance of work during the execution of the contract and does not apply to shoaling material after acceptance.

AS OF: 15 July 2015 Page 2 of 7

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-15-B-0001

2 Section 35 20 23, DREDGING, 3.2.2.1

Dredging Plant state the following:

Dredging shall be performed by mechanical dredging plant only, equipped with a closed, environmental style bucket to reduce turbidity. The use of a hydraulic dredge is prohibited for this project to avoid impacts to the federally listed species.

It is requested that a clamshell bucket also be allowed for use.

See Amendment coming soon.

AS OF: 15 July 2015 Page 3 of 7

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-15-B-0001

3 SECTION 35 20 23, DREDGING 3.2.6.1

Overflow, Spillage and Leakage, state the following:

Scow overflow is allowed only during dredging operations while scow is being filled to its allowable capacity. Spillage and leakage of any and all dredge material or water is prohibited outside of areas specifically authorized for dredging in accordance with the project plans, specifications and permits. Any material that is spilled, escapes, leaks, sloughs, or is lost or misplaced outside of Dredged Material Management site(s) at any time during operations, to include but not limited to dredging, loading or transporting, shall be retrieved and deposited in accordance with the project plans, specifications and permits.

Based on the permits provided, it appears that decanting is only allowed if there is an approved monitoring plan that has been approved by the RWQCB. It is our understanding that a decanting monitoring plan may have prepared by the USACE and submitted to the RWQCB for review. It is requested that the monitoring plan be provided to the Contractor to be sure that all costs associated with the monitoring can be estimated prior to bid time, unless the USACE is providing all services associated with monitoring.

See Amendment coming soon.

4 Please provide the reference to the

FAR section that covers the Required insurance for the project.

FAR 28.307-2 Liability

AS OF: 15 July 2015 Page 4 of 7

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-15-B-0001

5 It does not appear that Section 35

20 23 DREDGING, 3.2.5.6 - Weather Delays was included in Section 35

20 23 DREDGING.

Please clarify the number of weather days allowed for this project.

All Weather delays will be in accordance with FAR 52.236-4.

AS OF: 15 July 2015 Page 5 of 7

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-15-B-0001

AS OF: 15 July 2015 Page 6 of 7

AS OF: 15 July 2015 Page 7 of 7

File details come from the government source that posted it. Updated .