Questions Responses 9-3-2008.doc

DOC document 179 KB Posted

Attached to
Redwood City Dredging Project Federal contract opportunity
Solicitation number
W912P7-08-B-0005
Issued by
Department of the Army Corps of Engineers Engineering District San Francisco

About this file

Questions and answers as of 3 September 2008

View the file

Other files for this federal contract opportunity

Other files attached to Redwood City Dredging Project, newest first.
File Type Posted
Bid Abstract for RWC Dredge.xls XLS spreadsheet
Redwood_2of6.cal —
Readme_Redwood.txt TXT text file
Redwood_4of6.cal —
Redwood_3of6.cal —
Redwood_5of6.cal —
Redwood_City_FY08_05Aug08.pdf PDF
Redwood_1of6.cal —
Redwood_6of6.cal —

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Redwood City Harbor, CA (O&M)

CALIFORNIA

AS OF: 2 September 2008 Page 1 of 5

QUESTIONS & RESPONSES

SOLICITATION NUMBER W912P7-08-B-0005

The intent of this section is to provide questions & comments received from interested parties on the above solicitation, and our responses to those questions and comments. It is possible that the information below does not reflect 100% of the questions and responses. The questions and comments do not necessarily represent questions received from any particular contractor.

Questions and responses are provided for information only and are not made part of the solicitation. Only a formal amendment (SF30) to the solicitation changes the solicitation.

Changes to any previous responses in this document will be struck-through and new, updated responses will be provided as appropriate.

No.

RFP Section

Question

Response

1
Section 35 20 23, Paragraph 5.8
Regarding Section 35 20 23, Paragraph 5.8 Overflow, Spillage, and Leakage. If the contractor elects to use a Hopper Dredge, will they be allowed to overflow for an amount of time specified by the contracting officer in order to optimize production?

5.8 Overflow, Spillage and Leakage

5.8.1 Misplaced Material. Any dredged material that escapes, sloughs, or is lost at any time while dredging, loading, transporting, or which is deposited in an area other than that designated on the Plans shall be redredged or retrieved, and material shall be deposited where directed by the Contracting Officer, at the Contractor's expense.

5.8.2 The Contractor’s Spill Response Plan shall include monitoring of overflow, spillage and leakage.

5.8.3 The Contractor shall remove all material spilled outside the project limits at no cost to the Government.

Both the Consistency Determination (CD) and the Waste Discharge Requirements (WDR) allow 15 minutes of overflow for hopper dredge operations. The allowance is action specific and not project specific, meaning that it would apply on any project where a hopper dredge is used. The documents do not specify which projects may or may not use a hopper dredge. Both documents are worded such that the overflow is per excavation cut. We have clarified this with the agencies and their intention and interpretation is that after 15 minutes of overflow the dredge will transit to the disposal/placement site and unload.