This is a Scope of Work (SOW) document for Intermediate Bulk Container (IBC) Removal services issued by the U.S. Army Corps of Engineers (USACE), Chicago District, dated November 4, 2025.

The USACE requires removal, reuse, recycling, and/or disposal services for IBCs and metal drums containing or previously containing concrete admixtures and used oil from two locations: Indiana Harbor & Canal Confined Disposal Facility (IHC-CDF) in East Chicago, Indiana, and Calumet Harbor Stone Dock in Chicago, Illinois. The contract is divided into four Contract Line Items (CLINs): CLIN 001 covers removal of 14 IBCs (275-gallon capacity each) containing expired concrete admixtures from IHC-CDF; CLIN 002 covers 19 IBCs from Calumet Harbor Stone Dock containing expired concrete admixtures; CLIN 003 covers 2 empty IBCs and 2 empty metal drums (55-gallon capacity) previously containing used oil; and CLIN 004 covers 1 IBC containing used oil. The contractor is responsible for determining proper means and methods for handling, transportation, and disposal in accordance with all federal, state, and local regulations. The period of performance is 120 calendar days after contract award, with payment made as a single lump sum via ACH within 10 business days of final acceptance. The contractor must comply with extensive safety requirements per EM 385-1-1, including submission of an Accident Prevention Plan (ENG Form 6293), Site Safety & Health Officer designation (ENG Form 6282), and Activity Hazard Analyses. A Waste Management and Transportation Disposal Plan must be prepared and approved by both the TPOC and Environmental POC prior to work commencement. The contractor must also meet security requirements including AT Level I training, E-Verify enrollment, antiterrorism training, and iWATCH suspicious activity reporting compliance. Contractor operating hours are Monday-Friday, 7:00 a.m. to 3:30 p.m. local time, with site access controlled by the Government.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SCOPE OF WORK

for Intermediate Bulk Container Removal at Indiana Harbor & Canal Confined Disposal Facility and

Calumet Harbor Stone Dock

4 November 2025

PART 1: GENERAL INFORMATION AND SCOPE

1.1 Scope of Work (SOW):

The U.S. Army Corps of Engineers (USACE), Chicago District, requires services for the proper removal and reuse, recycling, and/or disposal of Intermediate Bulk Containers (IBCs) and metal drums, and their contents, from two different USACE Chicago District site locations. The Contractor shall provide all necessary labor, material, and equipment to complete the work. The Contractor shall be responsible for determining the means and methods for proper removal and reuse, recycling, and/or disposal of the IBCs and drums, and their contents, in accordance with all applicable Federal, State, and Local laws and regulations. All but three of the IBCs contain, or previously contained, concrete admixtures. Two IBCs are empty and previously contained used oil. One IBC contains used oil. The metal drums are empty and previously contained used oil. Services for this project can be divided into the following Contract Line Items (CLINS).

CLIN 001: Remove and reuse, recycle, and/or dispose of 14 IBCs and their contents, stored at the Indiana Harbor & Canal Confined Disposal Facility (IHC-CDF). There are 14 IBCs, 275-gal capacity each, stored at the IHC-CDF. These IBCs contain expired concrete admixtures and are mostly full of unused concrete admixtures (13 full, 1 half-full). See Pictures 1 & 2.

CLIN002: Remove and reuse, recycle, and/or dispose of 19 IBCs and their contents, stored at the Calumet Harbor Stone Dock. There are 19 IBCs, 275-gal capacity each, stored at the Calumet Harbor Stone Dock. These IBCs contain expired concrete admixtures and are empty or partially empty, as some of the concrete admixture was used. Some consolidation of the concrete admixtures has occurred within these IBCs (15 partially empty, 4 empty). See Picture 3.

CLIN003: Remove and reuse, recycle, and/or dispose of 2 empty IBCs and 2 empty metal drums stored at the Calumet Harbor Stone Dock. There are 2 IBCs, 275-gal capacity each, stored at the Calumet Harbor Stone Dock. These IBCs previously contained used oil and are now empty. See Picture 4. There are 2 metal drums, 55-gal capacity each, stored at the Calumet Harbor Stone Dock. These drums previously contained used oil and are now empty.

See Picture 5.

CLIN004: Remove and reuse, recycle, and/or dispose of the 1 IBC containing used oil stored at the Calumet Harbor Stone Dock. There is 1 IBC, 275-gal capacity each, stored at the Calumet Harbor Stone Dock. This IBC contains used oil. See Picture 4.

For CLINS 001 and 002, the USACE Chicago District has provided Safety Data Sheets (SDS) corresponding to the various concrete admixtures present within the IBCs stored at the IHC- CDF and Calumet Harbor Stone Dock. Due to length of storage, environmental conditions, and consolidation efforts, not all of the IBCs are labeled with a label specifically corresponding to one of the SDSs. However, the SDSs provided reflect all of the concrete admixtures present in the IBCs. The SDSs should be consulted to ensure proper handling, transportation, and disposal of the materials.

1.2 Site Locations: The work will take place at two U.S. Army Corps of

Engineers (USACE) project sites; IHC-CDF at 3500 Indianapolis Blvd, East Chicago, IN 46312 and at the Calumet Harbor Stone Dock. See Figures 1 & 2 for site location and totes storage. The Stone Dock does not have a mailing address, but the entrance gate for access is located at the intersection of E. 89th Street & Lake Shore Drive in Chicago, IL 60617. See Figures 3 & 4 for site location and totes storage.

1.3 Period of Performance: The period of performance for this Contract will be 120 calendar days after contract award.

1.4 Payment: Payment will be made for costs associated with this job. The payment made constitutes full compensation for furnishing all labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, and reports, and for performing all work required for which separate payment is not otherwise provided.

Upon completion Work, the Technical Point of Contact (TPOC or designated representative) will confirm satisfactory completion of Work. Contractor will then provide the TPOC with an electronic invoice to request payment. Remittance will be via one, lump sum, ACH payment, within 10 business days of final acceptance of Work. Partial and/or progress payments are not authorized for this service.

1.5 Government Facility Operating Hours: The Government Facility hours do not include U.S. federally recognized holidays or when the Government Facility is closed due to local or national emergencies, administrative closings, or similar Government directed facility closings. The Government Administrative Building hours are Monday-Friday, 7:00 a.m. to 3:30 p.m. local time.

1.6 Recognized Holidays: When a U.S. holiday occurs on a Saturday or a Sunday, the holiday is observed on the preceding Friday or following Monday, respectively. If submittal of any documentation (e.g. deliverables, submittals, etc.) deadlines fall on a holiday, the closest workday prior to the holiday will apply as the deadline for submittal.

New Year’s Day January 1st M. L. King Memorial Day 3rd Monday in January Presidents’ Day 3rd Monday in February Memorial Day last Monday in May Juneteenth June 19th Independence Day July 4th

Labor Day 1st Monday in September Columbus Day 2nd Monday in October Veteran’s Day November 11th Thanksgiving Day 4th Thursday in November Christmas Day December 25th

1.7 Contractor Operating Hours: In any circumstance, the Government shall not be liable if the Contractor cannot access the site outside the facility operating hours.

The Contractor must perform their work Monday-Friday between 7:00 a.m. to 3:30 p.m., except on holidays. The Contractor may request access to the site outside the Government Building Operating Hours. Contractor must give the Facility Manager (FM) at least 24 hours advance notice for approval.

1.8 Site Access: It will be the responsibility of the Government to unlock/lock the Lake Shore Drive entrance gate, 2 Stone Dock access gates, and Indianapolis Blvd entrance gates to allow access during the Contractor’s 7:00 a.m. to 3:30 p.m.

workday shift. No access cards or gate keys will be provided to the Contractor. Call the TPOC to coordinate site access.

1.9 Security Requirements: The IHC-CDF and Stone Dock are secured government locations. Contractor personnel shall adhere to facility security policies and restrictions. The Contractor shall ensure that all employees, of both the Contractor and any subcontractor, know these requirements and that the Government only grants permission for use of the premise for the purpose of the contract. The Contractor and any subcontractors shall comply with the following security requirements.

1.9.1 General Security Requirements and Guidance (Clause 1): The security requirements described below apply to all contract personnel (including employees of the prime Contractor (“Contractor”) and all subcontractor employees) supporting the performance requirements of this contract. The Contractor is responsible for compliance with these security requirements.

Questions regarding security matters shall be addressed to the designated Government representative (e.g., Contracting Officer Representative (COR), Requiring Activity (RA) representative, or Contracting Officer (if a COR or other RA representative is not appointed)). Contract personnel are critical to the overall security and safety of US Army Corps of Engineers (USACE) installations, facilities and activities, and security awareness training contributes to those efforts. The Department of Defense (DoD) and Army security training requirements specified below, if applicable, are performance requirements; all applicable contract personnel shall complete initial training within 30 days of contract award or the date new contract personnel begin performance on the contract. Within five business days from the completion of training, the Contractor shall provide written documentation (e.g., email or memorandum) to the Government representative. The documentation shall include the names of contract personnel trained and which training they completed; the Contractor shall maintain training records as part of their contract files and be prepared to provide copies of training certificates to the Government representative.

Contractor personnel and vehicles are subject to search when entering federal installations. Additionally, all contract personnel shall comply with Force Protection Condition (FPCON) measures, Random Antiterrorism Measures (commonly referred to as “RAMs”), and Health Protection Condition (HPCON) measures. The Contractor is responsible for meeting performance requirements during elevated FPCON and/or HPCON levels in accordance with applicable RA plans and procedures—this includes identifying mission essential and non-mission essential personnel. In addition to the changes otherwise authorized by the changes clause of this contract, should the FPCON or HPCON levels at any individual facility or installation change, the Government may implement security changes that affect contract personnel. The Contractor shall ensure all contract personnel are aware of their security responsibilities, including any site-specific requirements identified in local policies or procedures. Accessing the site, shall not be permitted to roam about the site unescorted and must be accommodated by a sufficient number of escorts to ensure that everyone can be communicated with and observed at all times.

1.9.2 Antiterrorism (AT) Level I Training: All contract personnel requiring routine access to Army installations, facilities, and controlled access areas, or requiring network access shall complete initial and annual refresher AT Level I awareness training. Online AT Level I awareness training is available at (https://jko.jten.mil/) (website subject to change).

1.9.3 Physical Security and Access Control Requirements. The IHC-CDF is a secured government location with an 8-ft high chain-linked fence with barbed wire on the north and west sides of the property. An 8-ft high concrete wall secures the east side. The south side of the site is an open dock face along the Indiana Harbor Ship Canal. The site has an intercom access system at the north and south cantilever slide gates along Indianapolis Boulevard with video surveillance cameras installed around its facilities. Both gates delay 15 seconds before closing upon entering/exiting the site. The Contractor is responsible for preventing “tailgating” access to the site. The totes are stored in an area at the south end encompassed by an 8-ft high chain-linked fence with barbed wire and padlocked double-swing gate.

The entrance gate to the Stone Dock is a chain-linked swing gate with padlock on the east side of Lake Shore Drive at the intersection with E. 89th Street. The gate acts as a barrier to vehicles but can be bypassed by pedestrians. A secondary 6-ft high double-swing gate just to the north of the Stone Dock is owned by Chicago Park District and is also controlled by a padlock. The totes are stored at the Stone Dock encompassed by an 8-ft high chain-linked fence with barbed wire. A double-swing gate on the dock’s north side is controlled by a third padlock.

All contract personnel requiring physical access to a federal installation or facility shall comply with the access control procedures of that location. Contract personnel requiring unescorted access to meet contract performance requirements on a DoD installation in the US shall be vetted by the installation/facility Provost Marshal/Directorate of Emergency Services/Security Office using the National Crime Information Center-Interstate Identification Index (commonly referred to as “NCIC-III”) and Terrorist Screening Database (commonly referred to as “TSDB”). Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures. Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the Requiring Activity (RA) representative.

1.9.4 Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something): All contract personnel shall receive initial and annual refresher training from the RA representative on the local suspicious activity reporting program. This locally developed training provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity.

1.9.5 Pre-screening of Contractor Candidates via E-verify Program:

Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart 22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An initial list of verified/eligible candidates shall be provided to the COR no later than 3 business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, and submit it to the Contracting Officer to become part of the official contract file.

1.9.6 Security Requirement Clauses:

a) Clause 1/3: Physical security and access control requirements for UNESCORTED ACCESS: In the event the contractors require access to any federal facility within the gated area not just the buildings.

i. Contract personnel shall comply with all personal identity verification requirements specified in installation/facility policies and procedures.

Contract personnel who do not meet requirements for unescorted access to USACE facilities shall coordinate escorted access with the Government representative, as needed. Contract personnel who receive keys, access cards, or lock combinations that provide access to government-owned property shall comply with key and lock control procedures of the RA.

Anyone accessing the site, shall not be permitted to roam about the site unescorted and must be accommodated by a sufficient number of escorts to ensure that everyone can be communicated with and observed at all times.

b) CLAUSE 1/2/6: General Security Requirements and Guidance/ Suspicious Activity Reporting Training (e.g. iWATCH, CorpsWatch, or See Something, Say Something):

i. iWatch Brochure (Block 6): iWatch Army is a community awareness program created to educate the public about behaviors and activities that may have a connection to terrorism. This program is a community program to help your neighborhood stay safe from terrorist activities. All contract personnel shall receive initial and annual refresher brochure training from the RA representative on the local suspicious activity reporting program. This locally developed training brochure provides contract personnel with general information on suspicious behavior, and guidance on reporting suspicious activity to the project manager, security representative or law enforcement entity. The contractor and all associated sub-contractors shall receive an overview on the local Suspicious Activity Reporting Program through a customized brochure, which outlines the iWatch program details and provides instruction for reporting suspicions activities to the local representative at LRC. The program review shall be completed within 10 calendar days of contract award and within 10 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

c) CLAUSE 14--E-Verify Verification: 1.28.3 AT OPSEC 6055 Clause 14 - Pre-screen Candidates Using E-Verify

i. Program Contractors shall comply with the requirements set forth in FAR clause 52.222-54 Employment Eligibility Verification and FAR Subpart

22.18 in using the E-Verify Program at (https://www.e-verify.gov/) (website subject to change) to meet the contract employment eligibility requirements. Contractors are encouraged to cooperate with Federal and State agencies responsible for enforcing labor requirements to include eligibility for employment under United States immigration laws in accordance with FAR 22.102-1(i). An E-Verify verification sheet, must be provided to the COR no later than 5 business days after the initial contract award. (The purpose of using E-Verify is to ensure all contractors are U.S.

citizens or documented foreign citizens with authority to work in the United States of America). The COR will submit the sheet to the Contracting Officer to become part of the official contract file. How to provide proof of enrollment in E-Verify-From the “Supplemental Guide for Federal Contractors” states, Federal contractors that are subject to the Federal Acquisition Regulation (FAR) E Verify clause may be asked to provide proof of enrollment in E-Verify. Program administrators and corporate administrators can get proof of participation by downloading a copy of their company information page. To provide proof, access the ‘Edit Company Profile’ link on the left navigation menu and print the screen containing your company information. This page contains proof of your enrollment in E-Verify. The contracting company can print a roster of those names from the E-Verify site and provide to contracting officer/representative. The COR will forward the verification sheets to the USACE, Chicago District Security Office for validation.

1.10 Safety Requirements: The Contractor will be subject to USACE safety policies while performing services on Federal Government property. The Corps of Engineers Safety Manual (EM 385-1-1 [15 MAR 2024]) can be found at the following location: https://www.publications.usace.army.mil/Portals/76/EM%20385- 1-1%20_EFFECTIVE%2015March2024.pdf (copy and paste the link) All chapters of the EM385-1-1 will apply to the contractor, it is beneficial for the Contractor to review Chapter 2, Safety and Occupational Health for Contractors.

1.10.1 Accident Prevention Plan (APP): An ENG Form 6293 (mandatory use form) must be filled out and returned to the TPOC/COR, including all required Appendices, Activity Hazard Analyses for each definable feature of work as noted in APP, and must be submitted in compliance with EM 385-1-1. Before initiation of work at the job site, an APP must be reviewed and assessed as acceptable by the TPOC/COR. The Contractor shall not commence any work on the site until the APP is designated as acceptable by the TPOC/COR. The ENG Form 6293 can be provided to the contractor if needed.

a) Please utilize original ENG Form 6293 electronic form. Please do not modify, photocopy, or scan in document with edits for submission.

b) An additional document is required for the contractor to compile all the required information requested in the APP for the Appendices 1-6.

Appendices cover Project Map(s), Subcontractor/Suppliers, Personal Qualifications and Designations, Activity Hazard Analysis, Site-specific plans and procedures, and any additional plans, procedures, etc.

c) All required Site Safety Plans the Contractor identifies in the APP will be included in the additional document under Appendix 5. Be mindful to review the APP EM 385 reference listed to verify if the plan will apply. Each EM 385 reference will cover Minimum Plan Requirements.

d) Contractor shall meet EM385-1-1 Chapter 3 Medical and First Aid Requirements and provide necessary certification documents in the additional document under Appendix 3.

e) Rollover Protection Structures (ROPS) (EM385-1-1, Chapter 18, 18-8.b(15) must be installed on crawler and rubber-tire tractors, off-the-highway self-propelled pneumatic-tire ear movers, motor graders, water tank trucks, other self-propelled construction equipment such as front-end loaders, backhoes, rollers, and compactors.

1.10.1 Site Safety & Health Officer (SSHO): An ENG Form 6282 (mandatory use form) must be filled out and returned to the TPOC/COR as part of the APP, including an instructor-signed OSHA 30-hr card (or course completion certificate if within 90 days of completing the OSHA 30-hour training), and proof of 24 hours of competency of SOH training within the last 3 years. The Contractor shall not commence any work on the site until the ENG Form 6282 is designated as acceptable by the TPOC/COR. The ENG Form 6282 can be provided to the contractor if needed.

a. Please utilize original ENG Form 6282 electronic form. Please do not modify, photocopy, or scan in document with edits for submission.

1.10.2 Check-In: The Contractor is responsible for ensuring that all workers, prior to start of daily work, check-in with assigned USACE Operations personnel at the facility, and receive a site-specific safety and activity update briefing. The Contractor is responsible for ensuring that all workers always comply with EM 385-1-1 and the Safety and Health Plan (ENG Form 6293) during the execution of the work.

1.10.3 Activity Hazard Analysis (AHA): The Contractor shall prepare and use an AHA as one of many tools to insure safe performance of work. It is the Contractor's responsibility to prepare the AHA per the APP for each definable feature of work to include meeting EM 385-1-1 (2-6.d) AHA Minimum Requirements. The AHA shall be reviewed and accepted by the TPOC/COR prior to commencement of work. All on-site employees shall review the approved AHA prior to performing work at the site. The Contractor can utilize non-mandatory ENG Form 6206 AHA and can be provided to the contractor if needed.

1.10.4 Accident Reporting: The Contractor shall maintain an accurate record of ENG Form 3394, and report to the COR/TPOC all accidents within 24 hours of the occurrence. All serious accidents (those resulting in death or injury requiring medical attention) shall be reported immediately. The Contractor shall maintain an OSHA Log of Work Related Injuries and Illnesses, OSHA Form 300.

1.11 Environmental Compliance: The Contractor shall comply with all federal, state, and local environmental regulations, as well as any site-specific safety and environmental guidelines. The Contractor shall be liable for all personnel injuries and damage that result from their negligence or failure to follow safety/health guidelines. The Contractor shall take proper safety, health, and environmental precautions to protect work, the workers, the public, and the property of others, to include appropriate insurance.

1.11.1 Unforeseen Hazardous Materials: USACE shall identify and communicate all known hazardous materials in which the Contractor may come into contact with during the course of activities. If material is encountered that was not indicated, but may be hazardous to human health, the work shall stop and the TPOC shall be notified immediately. The Government will determine, within fourteen business days of notification, if the material is or is not considered hazardous. If the material is not hazardous or poses no danger, the Government will direct the Contractor to proceed without change. If the material is determined to be hazardous or potentially hazardous, the Government will address as appropriate.

1.11.2 Spillages: Special measures shall be taken to prevent chemicals, fuels, oils, greases, and waste washings from releasing into the environment. If a release occurs, the Contractor shall be responsible for cleanup and disposal, and any associated costs in accordance with Federal, State, and local law. Such spills shall be reported to relevant authorities in accordance with all applicable regulations, in addition to the TPOC or the Environmental POC, immediately.

1.11.3 Disposal of Solid Wastes: All handling and disposal shall be conducted to prevent contamination. Unless otherwise specified, the Contractor shall transport all solid waste from Government property and dispose of it in compliance with federal, state, and local requirements. All expenses of arranging for and obtaining the disposal area shall be borne by the Contractor. The Contractor shall be responsible for all operations in connection with the disposal. Disposal of any materials, wastes, effluents, trash, garbage, oil, grease, chemicals, or other debris in areas adjacent to the river or lake will not be permitted. If any waste material is dumped in unauthorized areas, the Contractor shall remove the material and restore the area to its original condition. If necessary, contaminated ground shall be excavated and replaced with suitable fill material, compacted and finished with topsoil and planted as required to reestablish vegetation.

The Contractor is responsible for determining means and methods for proper reuse, recycling, and/or disposal of the IBCs and their contents, the empty IBCs, the empty metal drums, and the IBC containing used oil, in accordance with all federal, state, and local laws. The Contractor will prepare a Waste Management and Transportation Disposal Plan (WMTDP) to be reviewed by the TPOC and Environmental POC, prior to any work beginning.

1.11.4 Disposal of Used Oil: All handling and disposal of used oil shall be conducted to prevent contamination. Unless otherwise specified, the Contractor shall transport all used oil from Government property and dispose of it in compliance with federal, state, and local requirements for used oil management and disposal.

1.11.5 Waste Management, Transportation and Disposal Plan: Contractor shall prepare a WMTDP to describe the means and methods for removal and reuse, recycling, and/or disposal of the IBCs and their contents, the empty IBCs and metal drums, and the IBC containing used oil. Proof of final disposition of the containers and their contents is required as part of the WMTDP. This plan must be approved by the TPOC and the Environmental POC prior to commencement of any work.

1.12 Coordination Requirements and Submittals: The Contractor may be required to attend a pre-work conference with the TPOC/COR prior to beginning work. The TPOC/COR may be contacted telephonically and/or virtually. The purpose of this meeting is to establish the Contractor’s start date, plan of work, safety procedures, training requirements, and submittal requirements. All submittals must be transmitted to the TPOC for review and approval at least 14 calendar days before the start of work on-site. The Government reserves the right to delay or stop work if safety concerns are present.

1.12.1 Proof of Insurance: The Contractor will, at its own expense, procure liability insurance and maintain such insurance throughout the entire term of the contract and any option year extensions. The minimum types and amounts of required liability insurance are defined within the clauses of the proposal and made part of the awarded contract. The Contractor shall furnish a copy of the Certificate of Insurance for the minimum liability coverage. Additional Certificates of Insurance shall be submitted following any subsequent policy renewal or policy change(s).

Subcontractors (if any) shall be held to the same minimum insurance requirements.

1.12.2 Permits and Licenses: The Contractor shall, at his own expense, obtain any licenses or permits required to perform all aspects, requirements, and work under this contract. The Contractor shall comply with all current Federal, State, and local laws and regulations and shall comply with any subsequent changes.

1.13 Quality

1.13.1 Quality Control (QC): The Contractor’s existing quality assurance system shall utilize IAW FAR 12.208. Contractor’s QC shall include the following:

a) A method of identifying and correcting deficiencies in the quality of services performed before the level of performance is unacceptable.

b) A method of insuring that employees have full knowledge of their work tasks and that appropriate technical expertise is utilized during performance of those tasks.

1.13.2 Quality Assurance: The Government will monitor the Contractor’s work, track deficiencies, and inspect workmanship. If the Contractor fails to perform, or if performance is determined to be unsatisfactory, the Government will take corrective action.

1.14 Protection of Government and Contract Information and Site: Per Public Use Notice of Limitations stated by Defense Imagery Management Operations Center and contained at www.dimoc.mil/resources/limitations/, the Contractor shall not cite any information (e.g., contract information, pictures, locations, etc.) obtained through this contract on any hard copy or digital marketing tools that include its company website.

1.15 Protection/Restoration of Government Property: The Contractor, at no expense to the Government, is required to protect all Government facilities, equipment, and structures from damage in all phases of work during contractual performance. All Government structures and equipment damaged by the Contractor during the performance of work shall be returned to a pre-work condition at the end of the project. Damage to Government property that was caused by Contractor and/or subcontractor will be repaired at no expense to the Government.

1.16 Housekeeping: The Contractor is to provide labor necessary to maintain good housekeeping throughout the duration of the contract. All packaging materials and trash are to be collected and properly disposed of daily by the Contractor.

1.17 Notice to Proceed: The effective date of the Contractor’s acceptance of the contract award will constitute the date of notice to proceed and for the Contractor to start performing work onsite.

1.18 Veterans Employment Emphasis for U.S. Army Corps of Engineers Contracts: In addition to complying with the requirements outlined in FAR Part 22.13, FAR Provision 52.222-38, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS222.13 and Department of Labor regulations, USACE contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

a) U.S. Department of Labor Veterans’ Employment and Training Service (VETS): https://www.dol.gov/vets/

b) Federal Veteran Employment Information: https://www.fedshirevets.gov/t

c) Veterans Opportunity to Work (VOW) Program:

https://www.benefits.va.gov/vow/

d) U.S. Army Warrior Transition Command Employment Index:

https://wct.army.mil/modules/employers/index.html

e) Hiring Our Heroes: https://www.uschamberfoundation.org/hiring-our-heroes

PART 3: POINTS OF CONTACT

CONTRACTING POC:

Elizabeth Dennison District Contracting Chief U.S. Army Corps of Engineers, Chicago District 312-846-5371 office elizabeth.a.dennison@usace.army.mil

TPOC:

Damian Allen Facility Manager U.S. Army Corps of Engineers, Chicago District 312-951-3357 cell damian.g.allen@usace.army.mil

ENVIRONMENTAL POC:

Sussan Moussavi Environmental Engineer, District Environmental Compliance Coordinator U.S. Army Corps of Engineers, Chicago District 312-391-3736 cell sussan.moussavi@usace.army.mil

FIGURES & PHOTOS

Figure 1: IHC-CDF Site Location

Entrance Gate

Figure 2: IHC-CDF Totes Storage Area

Figure 3: Stone Dock Location

Entrance Gate

Figure 4: Stone Dock Totes Storage

Access Gate

Picture 1: IHC-CDF Totes

Picture 2: IHC-CDF Totes

Picture 3: Calumet Harbor Totes

Picture 4: Calumet Harbor Totes-Oil

Picture 5: Calumet Harbor Drums

W. R. GRACE

MATERIAL SAFETY DATA SHEET

Product Name: ADVA Cast MSDS ID Number: D-06536 MSDS Date: 08/19/2009 www.graceconstruction.com Page 1 of 4

SECTION 1 - CHEMICAL PRODUCT AND COMPANY IDENTIFICATION

Product Name: ADVA Cast 600

MSDS Number: D-06536

Cancelled MSDS Number: New

MSDS Date: 08/19/2009

Chemical Family Name: Polyacrylate Aqueous Solution

Product Use: Concrete admixture

Chemical Formula: Mixture-NA

CAS # (Chemical Abstracts Service Number):

Mixture-NA

Manufactured by:

W.R.Grace & Co.-Conn. Grace Canada, Inc.

62 Whittemore Avenue 294 Clements Road West Cambridge, MA 02140 Ajax, Ontario L1S 3C6

In Case of Emergency Call:

In USA: (617) 876-1400 In Canada: (905) 683-8561

SECTION 2 - COMPOSITION/INFORMATION ON INGREDIENTS

Ingredient CAS# Percent (max)

Polyacrylate Aqueous Solution NJTSR6031 50-100

SECTION 3 - HAZARDS IDENTIFICATION

Emergency Overview:

Caution!

May cause eye and skin irritation.

HMIS Rating:

Health: 1

Flammability: 1

Reactivity: 0

Personal Protective Equipment: B (See Section 8)

Potential Health Effects:

Inhalation: If inhaled as a vapor or mist, may causes irritation, sore throat, coughing and breathing difficulty.

Effects include: Nausea, vomiting and headache.

Eye Contact: Eye contact may causes irritation.

Skin Contact: Skin contact may causes irritation.

Skin Absorption: Not expected to be harmful if absorbed through the skin.

Ingestion: If ingested, may causes irritation to the linings of the mouth, esophagus and stomach.

Effects include: Nausea, pain and vomiting.

SECTION 4 - FIRST AID MEASURES:

Skin Contact: Wash with soap and water.

If discomfort or irritation persists, consult a physician.

Remove contaminated clothing and wash before reuse.

Eye Contact: Flush eyes with water for at least 15 minutes while holding eyelids open.

If discomfort or irritation persists, consult a physician.

Ingestion: Do not induce vomiting.

Never give anything by mouth to an unconscious person.

If discomfort or irritation persists, consult a physician.

Inhalation: If symptoms develop, get fresh air. If symptoms persist, consult a physician.

If breathing has stopped, give artificial respiration then oxygen if needed.

INDIANA HARBOR CDF

Product Name: ADVA Cast MSDS ID Number: D-06536 MSDS Date: 08/19/2009 www.graceconstruction.com Page 2 of 4

SECTION 5 - FIRE AND EXPLOSION HAZARD DATA

Flash Point: >200°F

Flash Point Method: Penske-Martens Closed Cup Lower Explosion Limit: Not Available

Upper Explosion Limit: Not Available

Auto-Ignition Temperature: Not Available

NFPA Rating:

Health: 1

Flammability: 1

Reactivity: 0

Extinguishing Media: In case of fire, use water spray, dry chemical, Carbon dioxide or foam.

Special Fire Fighting Procedures: Wear self-contained breathing apparatus and complete personal protective equipment when potential for exposure to vapors or products of combustion exist. Water may be used to cool containers to prevent pressure build-up and possible auto-ignition or explosion. Avoid breathing hazardous vapors or products of combustion, keep upwind.

Isolate area and keep unnecessary people away. Prevent run-off from fire control or dilution from entering streams or drinking water supplies.

No special procedures specific to this product.

Unusual Fire and Explosion Hazards: None unless noted below.

SECTION 6 - ACCIDENTAL RELEASE MEASURES:

Spills/Leaks: Use proper personal protective equipment. Do not flush to sewer or allow to enter waterways. Keep unnecessary people away.

Contain and/or absorb spill with inert material (i.e. sand, vermiculite) then place in a suitable container. For large spills, dike area and pump waste material into closed containers for disposal or reclamation.

SECTION 7 - HANDLING AND STORAGE

Precautionary Measures: Avoid contact with eyes, skin and clothing.

Do not take internally.

Practice good personal hygiene to avoid ingestion.

Use only with adequate ventilation.

Wash clothing before reuse.

FOR PROFESSIONAL USE ONLY. KEEP OUT OF CHILDREN'S REACH.

SECTION 8 - EXPOSURE CONTROLS AND PERSONAL PROTECTIVE EQUIPMENT

EXPOSURE GUIDELINES (US)

Ingredient ACGIH TLV OSHA PEL

TWA STEL Ceiling TWA STEL Ceiling Substance Specific and Mineral Dust PELs

Polyacrylate Aqueous Solution - - - -

EXPOSURE GUIDELINES (CANADA)

Employers should consult local Provincial regulatory limits for exposure guidelines which may vary locally.

Engineering Controls: Not generally required.

Personal Protective Equipment:

Respiratory Protection: Respiratory protection is not normally required. However, a chemical cartridge respirator with organic vapor cartridge and a prefilter for dusts/mists is required at or above the applicable exposure limits (Consult above Exposure Guidelines). If no limits exist, use an approved respirator whenever a vapor or mist is generated or if respiratory irritation occurs.

Supplied air respirator (SCBA) is required at exposure levels above the capabilities of a chemical cartridge respirator.

Skin Protection: Rubber or other impervious gloves should be worn to prevent skin contact.

Product Name: ADVA Cast MSDS ID Number: D-06536 MSDS Date: 08/19/2009 www.graceconstruction.com Page 3 of 4

Eye Protection: At minimum, safety glasses with side shields should be worn where exposure to excessive dust or spray is likely.

Work/Hygienic Practices: Use good personal hygiene practices.

None beyond those noted above.

SECTION 9 - PHYSICAL AND CHEMICAL PROPERTIES

Physical State: Liquid

Appearance/Odor: Not Available

Odor Threshold: (ppm) Not Determined pH: 5.1 - 6.1

Vapor Pressure: (Mm Hg) Unknown

Vapor Density: (Air = 1) Unknown

Solubility In Water: Miscible

Specific Gravity: (Water = 1) 1.065 - 1.085

Evaporation Rate: (Butyl Acetate = 1) Unknown

Boiling Point: >212°F/100°C

Viscosity: Unknown

Bulk Density: (Pounds/Cubic Foot)(Pcf) Not Applicable

% Volatiles (gr/L): (70°F)(21°C) Not Available

SECTION 10 - STABILITY AND REACTIVITY

Chemical Stability: Stable

Conditions To Avoid: None known for this product.

Hazardous Polymerization: Will not polymerize.

Hazardous Decomposition Products: None known for this product.

SECTION 11 - TOXICOLOGICAL INFORMATION

Ingredient(No data unless listed.) CAS Number LD50 and LC50

Carcinogenicity:

Ingredient IARC Group 1

IARC

Group 2A

IARC

Group 2B

NTP

Known

NTP

Suspect

OSHA

Polyacrylate Aqueous Solution No No No No No No

Mutagenicity: Not applicable.

Teratogenicity: Not applicable.

Reproductive Toxicity: Not applicable.

SECTION 12 - ECOLOGICAL INFORMATION

Environmental Fate: No data available for product.

Ecotoxicity: No data available for product.

SECTION 13 - DISPOSAL CONSIDERATIONS

Waste Disposal Procedures: Consult all regulations (federal, state, provincial, local) or a qualified waste disposal firm when characterizing waste for disposal. According to EPA (40 CFR § 261), waste of this product is not defined as hazardous. Dispose of waste in accordance with all applicable regulations.

SECTION 14 - TRANSPORTATION INFORMATION

Proper Shipping Name: Not Applicable

UN/NA Number: Not Applicable

Domestic Hazard Class: Nonhazardous

Surface Freight Classification: Not Applicable

Label/Placard Required: Concrete/Masonry Plasticizer and Water Reducing Compound

SECTION 15 - REGULATORY INFORMATION

REGULATORY CHEMICAL LISTS:

CERCLA (Comprehensive Response Compensation and Liability Act):

(None present unless listed below)

Product Name: ADVA Cast MSDS ID Number: D-06536 MSDS Date: 08/19/2009 www.graceconstruction.com Page 4 of 4

Chemical Name CAS # Wt % CERCLA RQ

SARA Title III (Superfund Amendments and Reauthorization Act)

SARA Section 312/Tier I & II Hazard Categories:

Health Immediate (acute) Yes Health Delayed (chronic) No Flammable No Reactive No Pressure No

302 Reportable Ingredients (Identification Threshold 1%.):

Chemical Name CAS # Wt % SARA 302 TPQ

313 Reportable Ingredients (Chemicals present below reporting threshold are exempt):

Chemical Name CAS # Wt % Nitrate Compounds RR-03804-0 .0035

National Volatile Organic Compound Emission Standards For Architectural Coatings:

Volatile Organic Content: (gr/L) Not Applicable

WHMIS Classification(s): Not WHMIS controled

This product has been classified in accordance with the hazard criteria of the Controlled Products Regulations (CPR). This MSDS contains all the information required by the CPR.

State Regulatory Information:

California Proposition 65: This product does not contain substances known to the state of California to cause cancer, birth defects or other reproductive harm.

Massachusetts Hazardous Substance List(Identification threshold 0.0001%(1ppm)):

New Jersey Hazardous Substance List(Identification threshold (0.1%)):

Pennsylvania Hazardous Substance List(Identification threshold 0.01%):

CHEMICAL INVENTORY STATUS:

All chemicals in this product are listed or exempt from listing in the following countries:

US CANADA EUROPE AUSTRALIA JAPAN KOREA PHILIPPINES

TSCA DSL NDSL EINECS/ELINCS AICS ENCS ECL PICCS

Yes Yes No Not Determined

Not Determined

Not Determined

Not Determined

Not Determined

SECTION 16 - OTHER INFORMATION

Non-Hazardous Ingredient Disclosure:

Chemical Name CAS Number Water 007732-18-5

Prepared by: EH&S Department

Approved by: EH&S Department

Approved Date: 08/19/2009

Disclaimer:

"The data included herein are presented in accordance with various environment, health and safety regulations. It is the responsibility of a recipient of the data to remain currently informed on chemical hazard information, to design and update its own program and to comply with all national, federal, state and local laws and regulations applicable to safety, occupational health, right-to-know and environmental protection."

Grace Concrete Products

ADVA® CAST 600

High-range water-reducing admixture ASTM C494 Type A and F, and ASTM C1017 Type I

Product Description ADVA® Cast 600 is a polycar-boxylate based high-range water reducer designed for the production of conventional and Self Consolidating Concrete.

ADVACast 600 is formulated to provide extended slump life along with excellent workability without segregation.

ADVACast 600 meets requirements of ASTM C494 Type A and F, and ASTM C1017 Type I plasticizing admixtures.

ADVACast 600 is supplied as a ready to use liquid that weighs approximately 8.9 lbs/gal (1.1 kg/L).

ADVACast 600 does not contain intention-ally added chlorides.

Uses ADVACast 600 is a plant added superplasti-cizer that is formulated to impart improved workability to concrete over an extended period of time while still achieving high early age compressive strength. ADVACast 600 can be used for the production of Self Consol-idating Concrete (SCC) in precast/prestressed applications and may also be used in conven-tional concrete production.

ADVACast 600 may be used to produce concrete in applications with very low water/cementitious ratios, where concrete stability and improved tolerance to material variability are required, while maintaining high levels of workability over long periods of time.

Addition Rates ADVACast 600 is an easy to dispense liquid admixture. Dosage rates can be adjusted to meet a wide spectrum of concrete perform-ance requirements. Addition rates for ADVA Cast 600 can vary from 2 to 10 fl oz/100 lbs (130 to 650 mL/100 kg) with the type of application, but will typically range from 3 to 6 fl oz/100 lbs (200 to 390 mL/100 kg) of cementitious. Should conditions require using more than the recommended addition rate, please consult your Grace representative.

Product Advantages

• Excellent moisture and air control

• Extended slump retention up to one hour

• Enhanced concrete cohesiveness with low viscosity for rapid placement

• Superior finish on cast surfaces

• Excellent early and later age compressive strength

Mix proportions, cementitious content, aggre-gate gradations and ambient conditions will affect ADVACast 600 dosage requirements.

If materials or conditions require using more than the recommended addition rates, or when developing mix designs for Self Consolidating Concrete please consult your Grace represen-tative for more information and assistance.

Compatibility with Other Admixtures and Batch Sequencing ADVACast 600 is compatible with most Grace admixtures as long as they are added separately to the concrete mix. However, ADVA products are not recommended for use in concrete containing naphthalene based admixtures including Daracem®19 and Daracem 100, and melamine based admix-tures including Daracem ML330 and Daracem 65. In general, it is recommended that ADVACast 600 be added to the concrete mix near the end of the batch sequence for optimum performance. Different sequencing may be used if local testing shows better performance. Please see Grace Technical Bulletin TB-0110, Admixture Dispenser Discharge Line Location and Sequencing for Concrete Batching Operations for further recommendations. ADVACast 600 should not come in contact with any other admixture before or during batching.

Pretesting of the concrete mix should be performed before use and as conditions and materials change in order to assure compati-bility with other admixtures, and to optimize dosage rates, addition times in the batch sequencing and concrete performance. For concrete that requires air entrainment, the use of an ASTM C260 air entraining agent (such as Daravair®, Darex®, or Airalon® 3000 product lines) is recommended to provide suitable air void parameters for freeze thaw resistance. Please consult your Grace representative for guidance.

Packaging & Handling ADVACast 600 is available in bulk, delivered by metered trucks, in 275 gal (1040 L) totes, and 55 gal (210 L) drums. ADVACast 600 will freeze at approximately 32°F (0°C) but will return to full functionality after thawing and thorough mechanical agitation.

Dispensing Equipment A complete line of accurate, automatic dispensing equipment is available.

www.graceconstruction.com North American Customer Service: 1-877-4AD-MIX1 (1-877-423-6491)

ADVA, the ADVA logo, Daracem, Daravair, Darex and Airalon are trademarks of W. R. Grace & Co.–Conn. registered in the United States and other countries.

We hope the information here will be helpful. It is based on data and knowledge considered to be true and accurate and is offered for the users’ consideration, investigation and verification, but we do not warrant the results to be obtained. Please read all statements, recommendations or suggestions in conjunction with our conditions of sale, which apply to all goods supplied by us. No statement, recommendation or suggestion is intended for any use which would infringe any patent or copyright. W. R. Grace & Co.–Conn., 62 Whittemore Avenue, Cambridge, MA 02140.

In Canada, Grace Canada, Inc., 294 Clements Road, West, Ajax, Ontario, Canada L1S 3C6.

This product may be covered by patents or patents pending. Copyright 2010. W. R. Grace & Co.–Conn.

DCAC-36A Printed in U.S.A. 12/10 FA/PDF

Product Name: V-MAR 3 MSDS ID Number: D-06477 MSDS Date: 01/20/2009 www.graceconstruction.com Page 1 of 4

SECTION 1 - CHEMICAL PRODUCT AND COMPANY IDENTIFICATION

Product Name: V-MAR 3 MSDS Number: D-06477 Cancelled MSDS Number: D-06441 MSDS Date: 01/20/2009 Chemical Family Name: Dispersed Carbohydrate Product Use: Viscosity Modifying Agent for Concrete Chemical Formula: Mixture-NA CAS # (Chemical Abstracts Service Number):

Mixture-NA

Manufactured by:

W.R.Grace & Co.-Conn. Grace Canada, Inc.

62 Whittemore Avenue 294 Clements Road West Cambridge, MA 02140 Ajax, Ontario L1S 3C6

In Case of Emergency Call:

In USA: (617) 876-1400 In Canada: (905) 683-8561

SECTION 2 - COMPOSITION/INFORMATION ON INGREDIENTS

Ingredient CAS# Percent (max) Oxirane, methyl-, polymer with oxirane, 2-aminopropyl methyl 083713-01-3 1-10 Tributyl phosphate 000126-73-8 < 1

SECTION 3 - HAZARDS IDENTIFICATION

Emergency Overview:

Caution!

Causes eye irritation.

Causes skin irritation.

HMIS Rating:

Health: 1 Flammability: 0 Reactivity: 0 Personal Protective Equipment: B (See Section 8)

Potential Health Effects:

Inhalation: Acute inhalation not expected to result in adverse effects.

Effects include: No other effects expected unless listed below.

Eye Contact: Eye contact causes irritation.

Skin Contact: Skin contact causes irritation.

Skin Absorption: Not expected to be harmful if absorbed through the skin.

Ingestion: Ingestion not expected to be harmful.

Effects include: No other effects expected unless listed below.

SECTION 4 - FIRST AID MEASURES:

Skin Contact: Wash with soap and water.

If discomfort or irritation persists, consult a physician.

Remove contaminated clothing and wash before reuse.

Eye Contact: Flush eyes with water for at least 15 minutes while holding eyelids open.

If discomfort or irritation persists, consult a physician.

Ingestion: Do not induce vomiting.

Never give anything by mouth to an unconscious person.

If discomfort or irritation persists, consult a physician.

Inhalation: If symptoms develop, get fresh air. If symptoms persist, consult a physician.

If breathing has stopped, give artificial respiration then oxygen if needed.

Product Name: V-MAR 3 MSDS ID Number: D-06477 MSDS Date: 01/20/2009 www.graceconstruction.com Page 2 of 4

SECTION 5 - FIRE AND EXPLOSION HAZARD DATA

Flash Point: >200F (Aqueous System) Flash Point Method: Not Applicable Lower Explosion Limit: Not Available Upper Explosion Limit: Not Available Auto-Ignition Temperature: Not Available

NFPA Rating:

Health: 1 Flammability: 0 Reactivity: 0

Extinguishing Media: In case of fire, use water spray, dry chemical, Carbon dioxide or foam.

Special Fire Fighting Procedures: Wear self-contained breathing apparatus and complete personal protective equipment when potential for exposure to vapors or products of combustion exist.

Water may be used to cool containers to prevent pressure build-up and possible auto-ignition or explosion. Avoid breathing hazardous vapors or products of combustion, keep upwind. Isolate area and keep unnecessary people away. Prevent run-off from fire control or dilution from entering streams or drinking water supplies.

No special…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .