AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SEE CONTINUATION PAGE

1. CONTRACT ID CODE PAGE OF PAGES

1 4

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P621R0012

X 9B. DATED (SEE ITEM 11)

18-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

U0005

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

14-Oct-2021

CODE

U. S. ARMY ENGINEER DISTRICT, LOUISVILLE

600 DR. MARTIN LUTHER KING, JR. PLACE

ROOM 821

LOUISVILLE KY 40202-2239

W912QR 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P621R0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMDT 0005

Solicitation W912P621R0012 to provide services to treat water for the Indiana Harbor and Canal Confined Disposal Wastewater Treatment Plant located in Lake County, IN is hereby modified as follows:

a. DFARS Clause 252.223-7999 DEV is hereby added in its entirety.

b. The proposal due date is hereby changed from 15 October 2021 at 1:00pm ET to 29 Octobter 2021 at

1:00pm ET.

c. Below are Questions and Responses to RFI’s:

1. What is the approximate distance from the water treatment pad to the properties electrical service drop? Our understanding is we can tie in the systems service prior to the facilities meter.

Response: Please see Specification Section 44 41 13.10 03, part 1.3.4, second paragraph.

2. Please provide the number of gallons treated and months of operation for recent years.

Response: Please see Specification Section 44 41 13.10 03, part 1.4.2, third paragraph.

3. Section 44 41 13.10 03 Part 2.1 calls for double-walled pipe for any piping extending beyond the CDF interior, including piping over the dike, are we correct to assume this includes any piping/ hose used as a part of the water treatment system? Can we use a secondary containment berm under the water treatment equipment in lieu of double walled pipe? Does the discharge line need to be double-walled?

Response: Please see Specification Section 44 41 13.10 03, part 2.1 and part 2.3.

4. Are there any schematics available for previous systems used onsite? Based on the available information it appears as if the previous contractor’s treatment train should have worked just fine however the violations say otherwise. We are trying to see if there were any deficiencies in their design and compare it to our own current plan.

Response: Please reference the NPDES permit Briefing Memo on page 7

5. In lieu of electrical equipment are we able to use diesel powered pumps and generators as needed to avoid the costs associated with running power to the water treatment pad location?

Response: Please bid as shown.

6. What is the weight limit of the decant structure bridge?

Response: Please see Specification Section 44 41 13.10 03, part 1.4.4, fifth paragraph.

7. Historically speaking, how often have media change-outs been required (carbon, multi-media, etc)?

Response: Please bid as shown.

8. For purposes of the bid are we to assume spent media including bag filters, sand/ gravel, carbon, etc will be disposed of as a non-hazardous waste? Is the Government able to provide historical waste characterization data?

Response: Please bid as shown.

9. When is the initial WWTP scheduled to be mobilized?

Response: Moblization can occur once the contract is awarded, Notice to Proceed is given to the awardee and various required subittals are approved.

10. Are concrete pipe supports required or can pipe lay directly on the ground?

Response: Please reference Plan Sheet CS-301 and Note 5.

11. Will the work included on the Reference Only Drawings be completed by others? Are there air monitoring pads currently available and when the new pads are completed with we be required to move from the existing pads to the new pads?

Response: Please bid as shown.

12. The specification states the limit of .6 MGD volume in the NPDES may be increased in the future. If the plant is designed for .6 MGD in 12 hours will additional operational hours, 24 hours per day, be allowed to meet the volume increase? If the plant already designed for 24 hours will additional equipment be funded?

Response: Please bid as shown.

13. If there is a containment liner under the package plant will there need to be double walled pipe connecting each piece of equipment?

Response: Please bid as shown.

14. Are there water level indicators currently in the ponds to monitor and record water levels?

Response: Please bid as shown.

15. Regarding bid items 2, 8, 14, 20, & 26, as described on page 129 of the specification PDF, that includes the full removal of equipment and restoration. If we are going to be leaving equipment on site for the options would it be possible to have a line item for demobilizing staffing and mothballing equipment? If left over the winter months there will need to be steps taken to winterize.

Response: Please see Specification Section 01 22 00.00 10, part 1.2.1.1.

d. All other terms and conditions remain unchanged.

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 24-Sep-2021 01:00 PM to 29-Oct-2020 01:00 PM.

The following have been added by reference:

252.223-7999 (Dev) Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

OCT 2021

The following have been modified:

SPECIAL INSTRUCTIONS

This Request for Proposal (RFP) is for a contract to provide services to treat water from the Confined Disposal Facility (CDF) ponds and discharge the treated water to the Indiana Harbor and Canal (IHC).

This procurement is full and open, NAICS 221310, Water Supply & Irrigation Systems (Size Standard $30M).

Method of Payment under this contract will be Electronic Funds Transfer (EFT) to a commercial bank account specified by the Contractor.

One award will be made from this Solicitation. The contract award will be based on Lowest Price to the Government. This is full and open procurement. In accordance with Federal Acquisition Regulation 19.1307, this project requires the HUBZone 10% price evaluation.

Note: In addition to the completed price breakout schedule/price proposal, the Offeror must complete their Representation and Certifications located in the solicitation.

***********************************AMDT 0005******************************************** Proposals are due 29 October 2021 at 01:00 PM Eastern Time. Please submit proposals to Miriaha.D.Sigmon@usace.army.mil. Fax submittals will not be accepted.

***********************************AMDT 0005******************************************** A site visit may be arrangeed during normal duty hours 8:00am-4:00pm Central Time:

POC – Damian Allen

(312) 951-3357 All contractors must be registered in the System for Award Management (www.SAM.gov) prior to award of a contract. All prposed contractors are highly encouraged to review FAR Clause 52.232-33 Payments by Electronic Funds Transfer – System for Award Management, which indicates “All payments by the Government under this contract shall be made by electronic funds transfer (EFT).” Those not currently registered can obtain registration by going to the website http://www.SAM.gov. The process can usually be completed from 24 to 48 hours after submission. Contractors will need to obtain a Unique Entity Identifier (formerly DUNS number) for processing their registration. If you do not already have a Unique Entity Identifier, one can be obtained from http://www.SAM.gov.

Refer to www.SAM.gov for information formerly found in CCR, EPLS, ORCA and FedReg.

Please begin the registration process immediately in order to avoid delay of the contract award should your firm be selected.

ALERT: You must submit a notarized letter appointing the authorized Entity Administrator before your registration will be activated. This requirement now applies to both new and existing entities. Effective 29 April 2018, the notarized letter process is now mandatory on all CURRENT registrants at SAM who have a requirement to update data on their SAM record. The notarized letter is mandatory and is required before the GSA Federal Service Desk (FSD) will activate the entity's registration.

Effective 29 June 2018, vendors creating or updating their registration can have their registration activated prior to the approval of the required notarized letter. However, the signed copy of the notarized letter must be sent to the GSA Federal Service Desk (FSD) within 30 days of activation or the vendor risks no longer being active in SAM.

Vendors can check whether an account is active by performing a query by their CAGE or Unique Entity Identifier (known as DUNS). The new registration process may now take several weeks, so vendors are highly encouraged to begin registering as soon as possible to avoid any possible delays in future contract awards. Remember, there is no cost to use SAM.

To find out additional information about the changes of the SAM registration process, contractors should visit the Frequently Asked Questions (FAQ) link located at the top of the SAM homepage (www.sam.gov).

Note: Page numbering in this document may not be accurate.

(End of Summary of Changes)

SECTION 44 41 13.10 03

WASTEWATER TREATMENT PLANT

PART 1 GENERAL

The Wastewater Treatment Plant (WWTP) will be designed to treat the effluent from the Confined Disposal Facility which is a combination of groundwater, dredge water, and precipitation that falls within the CDF cells all of which will be in contact with the dredged material after dredging starts.

The Contractor is responsible for process selection, sizing, and design of treatment processes and all piping and supporting equipment, and for providing and competently operating all equipment and materials necessary to treat the water from the IHC Confined Disposal Facility to achieve discharge limits required by the site National Pollution Discharge Elimination System (NPDES) permit. Granular activated carbon filtration will be a required process treatment part of the plant. The minimum requirement for the activated carbon filtration process is an Empty Bed Contact Time of 10 minutes. The Contractor shall size and select an appropriate carbon type and other processes, the plant sequence, chemicals/additives, and other relevant operating parameters needed to meet the NPDES permit discharge limits.

The treatment plant will operate on an as-needed basis. Water treatment service will be ordered as required during the contract period. A lead time of 30 days will be given to the contractor to mobilize and be ready for treatment after a task order is accepted.

It is expected that the treatment plant will be a package unit that can be mobilized to the site, remain at the site during the contract period, and demobilized from the site at the end of the contract. The contractor shall provide a package plant that can be readily mobilized, set up, expanded as required, and demobilized. The contractor shall not install a permanent treatment plant. The contract includes the installation of a water withdrawal and transfer system from the Confined Disposal Facility to the treatment plant, and a return line (for treatment plant backwash water, for disposal of treated water during startup, etc.) from the treatment plant to the CDF. The contractor shall provide/install electrical connection and electrical components required for operating the treatment plant. The contractor shall provide all piping, pumps and appurtenances required for operating the treatment plant. The contractor shall prepare the designated site area as needed to support the treatment plant equipment. All piping, electrical components, equipment, and appurtenances associated with water treatment installed during this project will be removed from the site at the end of the contract.

The contractor shall coordinate, communicate, and report to the Indiana Department of Environmental Management (IDEM) and/or other relevant regulatory agencies as needed to satisfy regulatory requirements related to operating the treatment plant and discharging treated water. This includes meeting all requirements in the NPDES permit, and as requested/required, participating in meetings, responding to comments, providing information related to treatment processes, reporting, and/or analytical results.

The Contractor is only authorized to mobilize, demobilize and operate the WWTP as described in this section, after Notice to Proceed, when the Contractor accepts a Task Order for work..

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

NFPA 70 (2011) National Electrical Code

NFPA 101 (2009; TIA 09-1; TIA 09-2) Life Safety Code

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only (FIO).

When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES.

SD-01 Preconstruction Submittals

General Schematic Drawing; G, DH, CT

The Contractor shall provide a General Schematic Drawing showing the layout of the treatment system components, processes, and piping. Include locations of injection of chemicals/additives and dosages, as appropriate.

Component sizing information, dimensions and the arrangement of valves shall be illustrated in the drawing. The DRAFT Schematic Drawings of the Wastewater Treatment Plant and connection shall be submitted within 45 calendar days of Notice to Proceed (NTP) of the task order ordering the equipment setup and/or water treatment. Final Schematic Drawings shall be submitted 21 days after comments on the draft are provided. If during the operation of the treatment plant, additional and/or alternative treatment processes are added to the plant, the Contractor shall submit a revised General Schematic Drawing, with all relevant revised information such as sizing, type of additive, dosage, etc., prior to implementation at the plant.

Material Safety Data Sheets; FIO

The Contractor shall submit Material Safety Data Sheets (SDS) for all chemicals and products brought onsite, including but not limited to treatment chemicals (i.e. acids, alkalis, polymers, etc.), activated carbon, and ion exchange media.

Flowmeters; FIO

The Contractor shall submit manufacturer literature, cutsheets, and installation details for the influent and effluent Flowmeters.

Design and Drawings - Electrical; G, DT

Provide Electrical design analysis, design documents, and design drawings required for the project.

Indicate on drawings (as applicable):

- Circuit Breaker Size and Type

- Disconnect Size and Type

- Load Calculations

- Motor Size and Type

- Transformer Size and Type

- Wire and Conduit Routing Size and Type

Provide one line diagram indicating incoming line voltage and size, capacity rating, and how temporary power will be derived. Provide calculations showing existing demand load and new demand load. Show that the existing power distribution system has capacity to power existing demand load plus new demand load. Submit the Design and Drawings - Electrical within 45 calendar days of NTP of the task ordering equipment setup and/or water treatment.

Startup Test Plan; G, DH

The Contractor shall submit a Startup Test Plan including the procedures and checklist for verifying satisfactory equipment and system operation.

Identify location and method of disposal for test water. Identify types and frequency of sampling and analysis procedures for initiating treatment of the CDF effluent and to verify the system is effectively treating the water and meeting the permit limits. The DRAFT Startup Test Plan of the wastewater treatment plant shall be submitted within 45 calendar days of Notice to Proceed (NTP) of the task order ordering equipment setup and/or water treatment. Final Startup Test Plan shall be submitted 21 days after comments on the draft are provided. .

Treatment Plant Operator Certification

Provide the treatment plant certified operator name and credentials as a pre-construction submittal in accordance with the requirements in the site NPDES permit. Coordinate with the Government and IDEM to have the certified operator enabled to submit NPDES monthly discharge reports on the IDEM NETdmr. Submit the Treatment Plant Operator Certification and credentials within 45 calendar days of NTP of the task order ordering equipment setup and/or water treatment.

Wastewater Treatment Plant Project Manager Qualifications

Provide the treatment plant project manager qualifications and credentials as described in this specification. Submit the Wastewater Treatment Plant Project Manager Qualifications and credentials within 45 calendar days of NTP of the task order ordering equipment setup and/or water treatment.

SD-06 Test Reports

Startup Report; G, DH

The Contractor shall submit a Startup Report to the Contracting Officer 30 calendar days after each successful startup of the wastewater treatment plant.

Process Upset Report

The Contractor shall follow all protocols of the NPDES permit for process upset reporting for NPDES permit limit exceedances. The Contractor shall also provide written Process Upset Report to the Contracting Officer within 24 hours of discovery.

Quarterly Operations Summary and Quarterly Data Report; G, DH

The Contractor shall submit to USACE a Quarterly Operations Summary and Quarterly Data Report that will include a summary of total daily volume treated, documentation/results of daily and weekly inspections, and a summary of alarms/issues and their subsequent resolution and/or corrective actions. If an NPDES permit exceedance occurs, document all actions performed to remedy the exceedance, including but not limited to, change in chemical dosage, treatability study performed, plant shutdown schedule, how compliance is re-achieved. The Quarterly Operations Summary shall include a Data Report with the daily influent and effluent sampling results, NPDES effluent sampling results, toxicity testing results, pond sampling results, and any other sampling results, prepared in accordance with Section 01 35 45 CHEMICAL DATA QUALITY CONTROL. The Quarterly Operations Summary and Quarterly Data Report shall be submitted within 45 days after each quarter.

(Quarters are defined as: First quarter - January through March; Second quarter - April through June; Third quarter - July through September;

Fourth quarter - October through December.)

Discharge Monitoring Reports; G, DH

The Contractor shall complete the state and federal Discharge Monitoring Reports (DMRs) for Industrial Discharge Permit as required in the NPDES permit. The contractor shall submit DMRs during the entire contract period, including periods with no discharge. Contractor is responsible for electronic reporting to IDEM as specified in the NPDES permit during the entire contract duration. The DMRs shall be submitted to the Indiana Department of Environmental Management (IDEM) on the NETdmr system. Draft Discharge Monitoring Reports shall be submitted to USACE prior to submittal to IDEM, with sufficient time for USACE review and comment, to meet DMR reporting schedule in the NPDES permit. Allow 3 working days for USACE review of draft DMR/MMR. The Contractor shall submit DMRs as required by the NPDES permit during the non-treatment periods.

The NPDES permit requires additional reporting such as Whole Effluent Toxicity testing. The Contractor shall comply with all regulatory required testing and reporting. All submittals to IDEM shall also be submitted to USACE. Formal submittal of the DMR/MMRs, and all other reports to USACE must be no later than 7 days after submittal to IDEM.

Preoperational Test Report In The Water Treatment Startup Report

1.3 GENERAL REQUIREMENTS

1.3.1 Standard Products

Material and equipment shall be the standard products of manufacturers regularly engaged in the manufacture of the products and shall essentially duplicate items that have been in satisfactory use for at least 2 years prior to bid opening.

1.3.2 Contractor Requirements

Contractor shall have had a cumulative minimum of 5 years of experience in the design, construction, and operation of water treatment plants, wastewater treatment plants, industrial wastewater treatment plants, or industrial wastewater pretreatment plants.

1.3.3 Wastewater Treatment Plant Project Manager

The Wastewater Treatment Plant Project Manager (WWTP PM) shall be the responsible person for all aspects of wastewater treatment operation. The WWTP PM shall be a qualified person and shall hold a valid professional engineering license or equivalent. Additionally, the WWTP PM shall have at least five (5) years experience with design, and/or operation and maintenance of water treatment plants, wastewater treatment plants, industrial wastewater treatment plants, or industrial wastewater pretreatment plants. The Wastewater Treatment Plant Project Manager can be the plant licensed operator. The WWTP PM shall assemble/oversee, review, and sign all reports/submittals required above for the wastewater treatment plant, including but not limited to the General Schematic Drawing, Startup Test Plan, Startup Report, Process Upset Report, Treatment Plant Operations Summary and Data Report, and Discharge Monitoring Report, prior to submittal to USACE.

In accordance with IDEM NPDES permit (pages 36, 37 and 38 of 41 of NPDES permit), para. C.6.a, para. C.6.a.(3), para. C.6.b: the contractor shall designate a person (such as the treatment plant project manager or the licensed plant operator) who will sign and certify all communication with IDEM pertaining to the NPDES permit. This person shall be the duly authorized representative of Linda Sorn, Chief of Engineering and Construction Division, USACE Chicago District. The contractor shall prepare an authorization letter to USACE, with the name of the duly authorized representative. USACE shall sign the authorization letter and the contractor shall submit the authorization letter to IDEM prior to any communication with IDEM pertaining to the IHC CDF treatment plant and/or the site's NPDES permit.

1.3.4 Electrical

The Contractor shall furnish and install all electrical materials and equipment for a complete and fully operable electrical service installation, including but not limited to power (as appropriate), controls, communications, and grounding, within the WWTP and shall conform to the requirements of local electrical codes, NFPA 70, and NFPA 101 unless more stringent requirements are indicated for electrical work within the facility. All electrical equipment shall be kept in a suitable weatherproof enclosure as appropriate.

The Contractor shall set up a separate electrical service account with NIPSCO for the wastewater treatment plant and related operation, and shall pay all electrical power bills as appropriate. The account shall be terminated at the end of this contract.

The Contractor shall furnish and install all grounding materials (grounding rods, copper ground conductors, clamps, and accessories) necessary for a complete grounding system of all current and non-current carrying equipment designated for the treatment plant. Grounding installation shall comply with all local electrical codes. The existing power pole with the site meter is approximately 1400 feet from the water treatment pad area.

Alternate power sources (diesel, generator, solar) may be used as appropriate.

All Electrical analysis and design documents must be in accordance with Unified Facilities Criteria (UFC) UFC 3-501-01 Electrical Engineering, UFC 3-550-01 Exterior Electrical Power Distribution and UFC 3-520-01 Interior Electrical Systems, as applicable. Use UFGS 26 20 00 Interior Distribution System and UFGS 33 71 02 Underground Electrical Distribution and other Specifications as applicable in the selection of components to be used in the design.

1.4 SYSTEM OPERATION

1.4.1 Influent Characteristics

The characteristics of the water to be treated are from samples collected from the CDF cells since 2013, which are attached at the end of this specification in Table 1 "IHC Pond Sampling Results-WWTP". The range of concentrations presented in the table is expected to be representative of the water to be treated. However, concentrations outside the range presented on Table 1 can also potentially occur. Table 2 summarizes the parameters that are on the NPDES permit along with the minimum and maximum concentrations observed in the CDF pond from 2013 through 2021.

Water will be extracted from the IHC CDF east or west dredged material disposal cells as directed by the COR via the two (2) decant structures for treatment. Water must be withdrawn in a manner that minimizes sediment resuspension and the inclusion of solids in the water stream, and must also be withdrawn in a manner that prevents a visible sheen or separate phase oil from entering the water stream.

The Contractor shall collect one sample from each cell of the CDF monthly during water treatment. Collect one sample from each cell of the CDF monthly when the plant is not operating, unless the ponds are frozen.

Coordinate so that the monthly samples prior to each treatment season shall be collected 2 weeks before treatment starts, for every treatment period.

The samples shall be collected from the pond at mid-depth, from a location within the pond with water depth of at least 2 feet. The samples can be collected from the decant structures when the decant structures are accessible. After the center dike submergence and the CDF becomes one pond, collect one sample from the CDF near the point of water withdrawal for treatment. The samples shall be analyzed for all parameters on Table 1.

All pond sampling results shall be presented in the Quarterly Data Report.

In addition, laboratory pond sampling data shall be provided to the Government as they are received from the laboratory as draft submittals for information only. Data collection, analysis, review, validation, documentation shall be in accordance with 01 35 45 CHEMICAL DATA QUALITY

CONTROL.

1.4.2 Wastewater Treatment Plant Flowrate and Operation Period

The estimated maximum volume of water for treatment is 70 to 80 million gallons per year. A more typical volume of water requiring treatment is 30 to 50 million gallons per year. In the past, annual treatment duration ranged from 3 to 8 months, and annual treatment volumes ranged from 30 to 80 million gallons. The wide range of possible water treatment volumes is due to a variety of factors: precipitation volume, whether dredging will occur requiring capacity in the CDF, the progress of the CDF dike expansion resulting in increase in CDF capacity, the frequency of water treatment.

Water will accumulate in the CDF and the Government will order water treatment as needed. Water treatment can be ordered from either cell of the CDF. A lead time of 30 days will be given to the contractor to mobilize and be ready for treatment after a task order is accepted. Water treatment may be required at any time during a year, and therefore, the treatment plant shall have the capability of operating during the winter season.

The NPDES permit flow rate is 0.6 million gallons per day and contaminant mass limits in the NPDES permit are based on this flow rate. Larger flow rates may be allowed in the future if mass limits are not exceeded based on quality of the treated water. The contractor shall size the treatment plant to efficiently remove water from the CDF to not delay dredging if CDF capacity is required to hold dredged material.

1.4.3 Effluent Characteristics

The Contractor is required to size, install, and operate the appropriate equipment in order to comply with the discharge requirements of the NPDES Industrial Discharge Permit obtained by United States Army Corps of Engineers, Chicago District (USACE). A copy of the NPDES permit is included as an Attachment to Section 01 57 20.02 03 ENVIRONMENTAL

PROTECTION FOR INDIANA.

1.4.4 Extraction of Water from CDF and Return Water to CDF

The Contractor shall provide all equipment, pumps, piping, and appurtenances in order to deliver water from the decant structures to the treatment plant and return water/backwash from the plant to the CDF . When extracting water from the CDF for treatment, the Contractor must not pump directly from the CDF (i.e., CDF effluent must be pumped from the existing decant structures), except as described below.

The CDF is currently undergoing an expansion where the height of the exterior dikes of the CDF will be increased, potentially in two stages. The initial dike height increase will be 3 feet, and the second dike height increase will be an additional 8 feet for a total increase of 11 feet. The possibility of the dike expansion occurring in one stage or two stages is dependent on availability of funding which is unknown at the current time.

An impact of the dike expansion on wastewater treatment will be the removal and re-installation of the WWTP piping as required. Piping that is placed over the CDF dike will require removal/reinstallation to accommodate the dike expansion. Piping that is placed on top of the dike can be assumed to require three installation/removal (at current height, at 3-foot increase, at 11-foot increase) in addition to installation/removal that may be determined by the contractor as needed. Piping that is not installed on the dike can remain during the contract. All piping will be removed from the site at the end of the contract.

The east cell decant structure will be raised along with the dike raise at the 11-foot raise. The west cell decant structure will not be raised and will remain the current height. As required, the Contractor shall coordinate with the dike construction contractor for access to the decant structures.

The west decant structure is accessed by the CDF center dike via the decant structure bridge. The center dike will not be raised when the exterior dikes are raised although the ramp between the expanded dike crest and the west decant structure will be modified during dike expansion to maintain interim access to the west decant structure. The west decant structure will not be accessible via the bridge and center dike after the center dike is eventually submerged by increasing impounded sediment and water levels after future dredging events. After the center dike submergence, the CDF will essentially become one pond. The Contractor shall extract water via the east decant structure when there is no construction work at the east decant structure. During the east decant structure construction, the Contractor may extract water directly from the CDF.

The Contractor shall coordinate with the COR when determining the location for installing the piping between the CDF cells and the treatment plant.

The Contractor is responsible for sizing the equipment, pumps, piping, etc., to be compatible with the proposed operations. Exposed (above ground) piping extending beyond the CDF interior, including piping over the dike, must be double-walled. The Contractor may place supporting equipment on the decant structure bridges so long as access to the structure is not impeded.

The decant structure bridge grating is galvanized steel with welded rectangular grating conforming to standards of National Association of Architectural Metal Manufacturers. Heavy duty rectangular steel bar gratings have bearing bars spaced at a maximum of 15/16-in and crossbars are spaced at a maximum of 2-in. Grating material conforms to ASTM A 36/A 36M. Grating was sized for AASHTO H20-44 wheel loading of 16-k per wheel at 14-ft on center and also for one concentrated load of 61,000-lbs acting on the structural steel to accommodate outrigger loads. Bridge has a maximum deflection of L/240. Slip resistance requirements exceed both wet and dry a static coefficient of friction of 0.5 as tested in accordance with ASTM F 1679A. Storage of equipment on the decant structure bridge shall be subject to approval by the Government with regards to weight and loading on the bridge.

Return piping from the treatment plant to the CDF (for backwash water and for treated water not meeting discharge criteria) shall be a floating pipe.

Treatment plant return piping shall discharge to the CDF west cell. Return piping shall have a flow dissipator at the discharge to minimize disturbance of sediment in the CDF ponds during discharge.

The Contractor shall not excavate through the dike to place the piping between the CDF and the treatment plant. Consequently, the piping between the CDF and the treatment plant shall have to cross the road at the top of the CDF dike. The Contractor shall provide protection for the piping from traffic at the road(s), and the piping shall not interfere with traffic on the road(s). Protection of the conduit, associated with normal operations, shall be the responsibility of the Contractor. The conduit shall be free of leaks at all times.

1.4.5 Disposal

The sludge generated during the treatment process by the WWTP will be disposed within the CDF. All processing water such as water used during the start-up period, backwash water during system operation, etc., shall be discharged to the CDF. Material such as activated carbon, ion exchange media will be regenerated or disposed offsite as appropriate. Water treatment chemicals or spent media, or other leftover materials used by the contractor at the IHC CDF must be disposed of offsite-consistent with all Federal, State, and Local requirements. Other waste generated such as filter membranes, filter media, and decant structure spent oil absorbent booms will be transported off Government property and disposed of in accordance with Federal, State, and local requirements. The Contractor shall verify that the selected transporters and disposal facilities have the necessary permits and licenses to operate.

1.4.6 Government Provided Facilities

The facilities provided at the CDF for the WWTP are specified in 01 10 00 GENERAL PROVISIONS. The area reserved for the wastewater treatment plant is located on the south side of the facility.

Water to be treated will be drawn from existing decant structures, and will be pumped to the wastewater treatment plant by the Contractor, except as described in these specifications. The location of the area for the package WWTP is shown in the drawings The Contractor shall prepare the designated area as needed to install the treatment plant.

1.4.7 Water Treatment Additives

The site NPDES permit does not include approval for any water treatment additives. If the Contractor elects to use water treatment additive(s), the contractor must apply for and obtain approval from IDEM prior to use of the additive(s) in accordance with the NPDES permit.

PART 2 PRODUCTS

2.1 DECANT STRUCTURE PUMPING SYSTEM AND DISCHARGE LINE

The Contractor is responsible for sizing and selecting the appropriate material for all pumps, wiring, controls, valves, and appurtenances to be compatible with the proposed operation and contaminants at the site.

Contractor shall select the appropriate pipe size(s). Piping extending beyond the CDF interior, including piping over the dike, must be double-walled. A secondary containment berm surrounding the water treatment equipment is acceptable as an alternative to double walled piping. Piping outside the containment berm shall be double-walled. Due to the contamination and unknown obstructions in the original site soil, excavation into the original site soil must receive prior approval from the

COR.

2.2 FLOWMETERS

The Contractor shall provide a tamper-proof totalizing flowmeter on WWTP influent line, and on the WWTP effluent discharge line to indicate the instantaneous flow rate and to record the total volume of water entering and discharged from the treatment plant. The flowmeters shall have an accuracy of +/- 0.5%. The flowmeters shall have data logging capability.

The reading on the effluent flowmeter will be used for payment. The purpose of the influent flowmeter is to confirm quantity treated by the treatment plant. The flowmeters will be placed in an area so that they can be read by a representative of the Contracting Officer at any time. Calibrate the flowmeters prior to each water treatment season, and provide calibration reports in the Startup Reports.

2.3 WWTP EFFLUENT DISCHARGE LINE

Contractor shall furnish, install, and protect a continuous discharge conduit that provides positive drainage from the treatment facility to Lake George Canal. The location of the discharge line shall be coordinated with the COR. The Contractor shall provide any protection and support of the conduit as appropriate. The Contractor is responsible for sizing the conduit to be compatible with the proposed operations. The conduit shall be free of leaks at all times, and shall extend to the CDF south cutoff wall at all times, with no discharge on the land side of the cutoff wall.

The discharge shall not be through the cutoff wall. There is a gravel access road and drainage ditch on the south side of the site between the treatment plant pad and the south cutoff wall. The discharge line shall not interfere with traffic on this access road or capacity of the ditch.

Protection of the conduit, associated with normal operations, shall be the responsibility of the Contractor. Contractor shall determine the need for an air release. Discharge velocity in the pipe shall not exceed 6 feet per second. The conduit shall maintain a sufficient slope to maintain a downhill discharge and prevent ponding. Lower the discharge pipe to minimize spraying at the exit to the Canal. The WWTP effluent discharge line does not require double walled piping. The effluent discharge line shall be removed at the end of the contract.

PART 3 EXECUTION

3.1 FIELD QUALITY CONTROL

3.1.1 Preoperational Test

Inspect, operate, and test all equipment before startup.

3.1.1.1 Tests

Tests shall include but not be limited to the following:

a. Soundness (without cracked or otherwise damaged parts).

b. Completeness in all details, as specified.

c. Correctness of setting, alignment, and relative arrangement of each component.

d. Verification of proper operation for all system components.

3.1.1.2 Preoperational Investigation and Test Report

Submit the Preoperational Test Report in the water treatment Startup Report.

Document inspections, operations, adjustments, and tests performed and indicate whether they were acceptable or not. For unacceptable items, describe corrective action taken. Include detailed descriptions of points inspected, tests and adjustments made, and quantitative results obtained.

3.1.2 Electrical Continuity and Insulation Resistance Tests

Perform wire and cable continuity and insulation tests before the conductors are energized. Perform continuity test to insure correct cable connection (i.e., correct phase conductor, grounded conductor, and grounding conductor wiring) end-to end as appropriate. Repair and re-verify any damages to existing or new electrical equipment resulting from mis-wiring.

3.2 WWTP STARTUP

Startup Testing will be done prior to the initial operating period of the WWTP, and also to every operating period if the previous operating period had ended more than 6 months previously. The results of the startup testing will be included in the Startup Report.

3.2.1 Clean Water Test

Once the treatment plant equipment has been installed and piped, the Contractor shall perform a clean water test using potable water from the site. This test will be performed to demonstrate that there are no leaks in the equipment or piping and that all gauges, sensors, pumps, and alarms are working properly. The Contractor shall notify the Contracting Officer at least 2 days before the test is performed. The clean water test shall be performed at the treatment plant design flow rate and shall be for a period of time sufficient to prove-out all equipment and controls.

Adjustments will be made and the tests repeated, as necessary, until satisfactory performance is achieved. The clean test water may be discharged to the Lake George Branch in compliance with the NPDES permit requirement. Alternatively, the clean water may be discharged to the CDF cells per USACE direction.

3.2.2 Initial Treatment/Startup Test

Once the system has been proven out by the clean water test, the system will be tested by pumping and treating water from the CDF. During the initial treatment testing, influent and effluent grab samples will be collected daily and analyzed for all required parameters. The samples will be analyzed by a certified laboratory on a 24 hour turn around time. The system will be considered fully operational if the effluent samples meet the NPDES permit requirements for 2 consecutive days. If the first test passes and the second test fails, the requirement is to start over until two consecutive tests (i.e., samples from two consecutive days) pass all NPDES permit limits. The initial treatment test shall be performed at the treatment plant design flow rate and shall be for a period of time at least equivalent to the 2 consecutive day period where effluent samples that meet NPDES permit requirements are collected. Adjustments will be made and the tests repeated, as necessary, until effluent samples meet all NPDES permit requirements for two consecutive days. During the initial treatment testing, the effluent will be discharged to the CDF. Inform the Government when startup testing is initiated, as the Government may choose to observe the startup testing sample collection.

Results from the initial treatment/startup test will be reported in the Startup Report. The report shall include the laboratory results, tabulated sampling data, and a record of operating parameters and adjustments made if required. Documentation of successful startup as described above will be required in the startup report.

3.3 ROUTINE OPERATION

3.3.1 Influent Sampling

During treatment plant operation, collect WWTP influent samples on the same schedule as the effluent sampling for NPDES reporting, to be sent for offsite laboratory analysis for all required parameters on the NPDES permit. Samples shall be collected from the influent line into the treatment plant. The purpose of influent sampling, along with the "real-time" influent sampling described below, is to understand variability in the influent, and/or to determine whether additional treatment is needed. The samples will be analyzed on the same turn around time as the effluent samples for NPDES permit reporting.

During treatment plant operation, collect daily WWTP influent samples for Ammonia and Total Suspended Solids analysis. The analyses shall be performed in "real-time" to inform the treatment plant operation.

Typically, ammonia levels in the CDF ponds have been higher in the fall through spring. Perform daily influent ammonia sampling when ammonia treatment is required. Influent ammonia sampling can provide information on whether ammonia treatment is required, and/or the level of treatment required. During summer water treatment, after it can be demonstrated that ammonia levels are low enough to not require treatment (7 days of treatment plant influent ammonia levels below NPDES discharge limit with no treatment), daily sampling for ammonia can halt. The contractor shall propose the methodology for measuring Ammonia to a detection limit below 1 mg/L, and which can provide results in "real-time" (less than 1 hour).

Total suspended solids (TSS) is a highly variable parameter in the CDF water, and can vary based on wind conditions, water volume in the CDF, precipitation, season of the year, presence of vegetation/algae, among other factors. Because TSS levels can change quickly, and because TSS can be an indication of other regulated parameters such as mercury and other metals, it is critical to sample WWTP influent daily for TSS during treatment. Daily TSS sampling can provide information on the level of treatment that is required. The contractor shall propose the methodology (Standard Method 2540D or equivalent) for measuring TSS levels which can provide results in "real-time".

The contractor shall determine a sampling schedule to be compatible with the treatment schedule/duration that complies with the requirements of this specification.

All influent sampling results (laboratory and real-time) shall be presented in the Quarterly Data Report in tabulated form. In addition, laboratory influent data shall be provided to the Government as they are received from the laboratory as draft submittals for information only. Data collection, analysis, review, validation, documentation shall be in accordance with

01 35 45 CHEMICAL DATA QUALITY CONTROL.

3.3.2 Effluent Sampling

The Contractor shall collect effluent compliance samples at the frequency indicated in the NPDES permit. The samples will be analyzed by a National

Environmental Laboratory Accreditation Program (NELAP) approved laboratory (www.epa.gov/nelac/nelap.html) and the results reported to the Contracting Officer within 1 week of sampling. The results of the analysis will be compared to the NPDES permit discharge requirements. If a sample result indicates a compound concentration exceeds the discharge limit, the Contracting Officer shall be notified immediately and the cause of the exceedance shall be determined and rectified. Additional samples will be collected to confirm compliance with the discharge requirements. The Contractor shall also follow all protocols for reporting upsets to IDEM, as detailed in the NPDES permit. The results of the sampling and a summary of the corrective action will be included in the following month's Discharge Monitoring Reports and Quarterly Data Report.

The Contractor shall collect daily WWTP effluent samples for Ammonia and Total Suspended Solids analysis. The analyses shall be performed in "real-time" to inform the treatment plant operation.

Daily ammonia effluent sampling shall be conducted when daily ammonia influent samples are collected. Requirements for effluent ammonia sampling and analysis are the same as for the influent sampling.

The Contractor shall collect daily WWTP effluent samples for TSS analysis.

Requirements for effluent TSS sampling and analysis are the same as for the influent sampling.

If the daily effluent Ammonia or TSS sampling result exceeds the NPDES permit limit, discharge of treatment plant effluent to the Canal will cease immediately. Discharge to the Canal can resume when the daily effluent sampling passes the NPDES permit limit for the failed parameter as indicated by the "real-time" analysis, and confirmed by laboratory results.

The contractor shall determine a sampling schedule to be compatible with the treatment schedule/duration that complies with the requirements of this specification. Effluent testing for NPDES permit reporting shall be a methodology that is approved by IDEM for wastewater discharge testing.

All effluent sampling results (laboratory and real-time) shall be presented in the Quarterly Data Report. In addition, laboratory effluent data shall be provided to the Government as they are received from the laboratory as draft submittals for information only. Data collection, analysis, review, validation, documentation shall be in accordance with 01 35 45 CHEMICAL

DATA…