AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

W912P621R0012 to provide services to treat w ater for the Indiana Harbor and Canal Confined Disposal Wastew ater Treatment Plant located in Lake County, IN is hereby modified as follow s:

a. Questions and Responses to RFI's (see AMDT 0002 continuation page)

b. All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 6

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P621R0012

X 9B. DATED (SEE ITEM 11)

18-Aug-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

15-Sep-2021

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P621R0012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been added by full text:

AMDT 0002

What treatment process is presently being deployed for treating the CDF pond water?

Response: As shown in the NPDES permit (on page 339 of 432 of the Specifications package), the process that have been used by the current treatment plant include: 1) addition of alum (aluminum sulfate) to remove high TSS, 2) a multi-media filter (sand and gravel), 3) addition of chlorine (sodium hypochlorite) when Ammonia removal is required (low levels of ammonia are observed in summer and chlorine addition is not required when ammonia levels are below NPDES permit limits in the WWTP influent), 4) granular activated carbon filter, 5) addition of sodium bisulfite to remove residual chlorine during chlorination, 6) bag filters for final polishing prior to discharge to the Canal. It should be noted that dosage of chemicals (e.g., alum and chlorine) can vary depending on influent concentrations. It should also be noted that the current plant had various violations (shown in permit).

According to the drawings provided in the solicitation, there is a WWTP plant adjoining the ponds. Is this plant currently in operation and would that facility be available for operating by a contractor awarded the contract addressed in this RFB?

Response: The current treatment plant contract ends September 2021 and the plant which is a package plant provided by the current treatment plant contractor will be demobilized from the site and is not available for use after September 2021.

How much area is available for setting up a WWTP to address this solicitation?

Sheet CS-102 in the Drawings package shows the area designated for the WWTP. The area is approximately 220’ by 70’, not including areas which will be required for piping from the CDF to the plant and from the plant to the Canal.

Some additional area may be available with coordination with the COR/facility manager/other contractors using the site.

(End of Summary of Changes)