AMENDMENT_NO._0002_W912P619B0009_EAST_CHICAGO_IL_SECTION_219_PROJECT_USACECHICAGOrgb.pdf

PDF 652 KB Posted

Attached to
Water Main Replacement Phase 2, at Indianapolis Boulevard, East Chicago, Indiana
Solicitation number
W912P619B0009
Issued by

About this file

THIS FILE CONTAINS AMENDMENT NO. 0002 (WHICH ENCLOSES THE WAGE RATES THAT WERE INADVERTENTLY OMITTED VIA AMENDMENT NO. 0001)

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

W81G6691085302

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

SUBJECT: ADMINISTRATIVE CORRECTION - INVITATION FOR BIDS NO. W912P619B0009, "CITY OF EAST CHICAGO INDIANAPOLIS

BOULEVARD WATER MAIN REPLACEMENT PHASE 2 - SECTION 219 PROJECT"

A. The Bid Opening Date and Time is NOT EXTENDED by this Amendment. Therefore, bids are due by 2:00 p.m. (Central Time) on August 29, 2019. Detailed information regarding the submission of bids is located at Section 00 22 13 of the Solicitation document – See “IMPORTANT

BID NOTES.”

B. This amendment encloses the most current w age determination that w as to be included under the previously issued Amendment No.

0001 (re: paragraph F., Wage Determination, General Decision IN20190001 08/16/2019)

C. Prior to the designated time and opening of bids, BIDDERS may email their acknow ledgement of this amendment to Ericka Hillard at ericka.d.hillard@usace.army.mil..

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 26-Aug-2019

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P619B0009

X 9B. DATED (SEE ITEM 11)

29-Jul-2019

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

26-Aug-2019

CODE

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

W912P6 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P619B0009

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00 10 00 - SOLICITATION

The Issued By organization below has been added:

U.S. ARMY ENGINEER DISTRICT, CHICAGO

231 SOUTH LASALLE STREET SUITE 1500

CHICAGO IL 60604-1437

(End of Summary of Changes)

"General Decision Number: IN20190001 08/16/2019

Superseded General Decision Number: IN20180001

State: Indiana

Construction Types: Building, Heavy and Highway

Counties: La Porte, Lake, Porter and St Joseph Counties in

Indiana.

BUILDING CONSTRUCTION PROJECTS (does not include single family homes and apartments up to and including 4 stories, HEAVY AND

HIGHWAY CONSTRUCTION PROJECTS

Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.60 for calendar year 2019 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January

1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.60 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year

2019. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to

Page 1 of 42beta.SAM.gov

8/24/2019https://beta.sam.gov/wage-determination/IN20190001/12/document the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the

Davis-Bacon Related Acts, including those set forth at 29 CFR

5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.

Modification Number Publication Date

0 01/04/2019

1 01/18/2019

2 01/25/2019

3 02/08/2019

4 03/08/2019

5 04/12/2019

6 05/17/2019

7 06/07/2019

8 06/21/2019

9 07/05/2019

10 07/12/2019

11 08/09/2019

12 08/16/2019

ASBE0017-002 06/01/2019

LAKE AND PORTER COUNTIES

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 50.50 27.80

HAZARDOUS MATERIAL HANDLER

(INCLUDES PREPARATION,

WETTING, STRIPPING REMOVAL

SCRAPPING, VACUUMING, BAGGING

AND DISPOSAL OF ALL

Page 2 of 42beta.SAM.gov

INSULATION MATERIALS, WHETHER

THEY CONTAIN ASBESTOS OR NOT,

FROM MECHANICAL SYSTEMS).........$ 37.80 24.54

ASBE0075-001 06/01/2017

REMAINING COUNTIES

Rates Fringes

ASBESTOS WORKER/HEAT & FROST

INSULATOR........................$ 31.50 20.79

HAZARDOUS MATERIAL HANDLER

(includes preparation, wetting, stripping, removal, scrapping, vaccuming, bagging, and disposal of all insulation materials, whether they contain asbestos or not, from mechanical systems).........$ 23.00 14.40

BOIL0001-005 05/01/2017

LAKE COUNTY, City of Hammond; North of 114th Street

Rates Fringes

BOILERMAKER......................$ 46.18 29.58

BOIL0374-003 03/01/2018

Rates Fringes

BOILERMAKER......................$ 37.22 27.65

BRIN0004-011 06/01/2018

Page 3 of 42beta.SAM.gov

LAKE, LAPORTE AND PORTER COUNTIES

Rates Fringes

BRICKLAYER

Bricklayer; Stone Mason;

Pointer, Cleaner, Caulker...$ 37.80 23.42

Marble Finisher; Tile

Finisher....................$ 29.00 15.54

Marble Mason; Terrazzo

Worker; Tile Layer..........$ 37.05 21.64

Terrazzo Finisher...........$ 30.00 15.54

BRIN0004-018 06/01/2018

SOUTH BEND: ST. JOSEPH COUNTY

Rates Fringes

BRICKLAYER

BRICKLAYER; STONE MASON;

POINTER, CAULKER, CLEANER...$ 29.00 15.96

MARBLE AND TILE FINISHER....$ 29.00 15.54

MARBLE AND TILE LAYER.......$ 30.57 18.36

TERRAZZO FINISHER...........$ 30.00 15.54

TERRAZZO WORKER.............$ 31.57 18.36

CARP0413-002 06/01/2019

St. Joseph County

Rates Fringes

CARPENTER........................$ 27.72 20.27

CARP0765-001 06/01/2019

Page 4 of 42beta.SAM.gov

LAKE, LAPORTE AND PORTER COUNTIES

CARPENTER........................$ 37.93 27.30

MILLWRIGHT.......................$ 38.03 27.30

CARP1029-001 06/01/2019

ADAMS, ALLEN, CASS, DEKALB, ELKHART, FULTON, GRANT, HOWARD,

HUNTINGTON, KOSCIUSKO, LAGRANGE, MARSHALL, MIAMI, NOBLE, ST.

JOSEPH, STEUBEN, TIPTON, WABASH, WELLS and WHITLEY COUNTIES

Rates Fringes

MILLWRIGHT.......................$ 27.70 24.34

ELEC0153-001 06/03/2019

ST JOSEPH COUNTY

Rates Fringes

Communication Technician.........$ 26.50 18.33

ELECTRICIAN......................$ 34.67 24.27

Includes the installation, operation, inspection, modification, maintenance and repair of systems used for the transmission and reception of signals of any nature, for any purpose, including but not limited to, sound and voice transmission/transference systems, communication systems that transmit or receive information and/or control systems, television and video systems, micro-processor controlled fire alarm systems, and security systems and the performance of any task directly related to such installation or service. The scope of work shall exclude

Page 5 of 42beta.SAM.gov the installation of electrical power wiring and the installation of conduit raceways exceeding fifteen (15) feet in length.

ELEC0531-001 05/28/2018

LAPORTE and PORTER COUNTIES

Rates Fringes

ELECTRICIAN......................$ 39.60 25.73

ELEC0697-001 05/27/2019

LAKE COUNTY

Rates Fringes

ELECTRICIAN......................$ 41.50 37.66

ELEC0697-004 08/28/2017

LAKE COUNTY

Rates Fringes

Telecommunication Technician.....$ 31.00 24.95

Work covers low voltage installation, maintenance and removal of telecommunication facilities (voice, sound, data and video) including, telephone and data inside wire, interconnect, terminal equipment, central offices, PABX, fiber optic cable and equipment, micro waves, V/SAT, bypass, CATV, WAN (WIDE AREA NETWORKS), LAN (local area networks), and ISDN (integrated system digital network).

Does not cover any work which properly comes under the work

Page 6 of 42beta.SAM.gov description of Inside JW (Journeyman Wireman), but shall cover the pulling of wire in raceways, but not the installation of raceways.

ELEC1393-003 01/01/2019

LAKE & PORTER COUNTIES

(Calumet Area, North of U.S. Hwy 30)

Rates Fringes

Line Construction:

EQUIPMENT OPERATOR 1:

(Diggers 5th wheel type trucks, crawler type, D-4 and smaller, bucket trucks and live boom type line trucks).....................$ 34.69 16.21

EQUIPMENT OPERATOR 3

(Backhoe over 1/2 yard bucket capacity, cranes rated at 15 ton or more capacity) 95% of J.L. Rate..$ 43.00 18.62

GROUNDMAN...................$ 25.44 13.53

GROUNDMAN-TRUCK DRIVER......$ 30.79 15.08

LINEMAN.....................$ 44.40 19.03

ELEV0002-005 01/01/2019

ELEVATOR CONSTRUCTION

LAKE AND PORTER COUNTIES

Rates Fringes

ELEVATOR MECHANIC................$ 56.61 33.705+a+b

Page 7 of 42beta.SAM.gov

FOOTNOTES:

a) Eight Paid Holidays: New Year's Day; Veterans Day, Memorial Day; Independence Day; Labor Day; Thanksgiving

Day; Friday after Thanksgiving and Christmas Day.

b) Employer contributes 8% of regular hourly rate to vacation pay credit for employee with more than 5 years of service, and 6% of regular hourly rate for less than 5 years of service.

ELEV0044-002 01/01/2019

Rates Fringes

ELEVATOR MECHANIC................$ 49.72 33.705+a+b

a) PAID HOLIDAYS: New Year's Day, Memorial Day, Independence

Day, Labor Day, Vetern's Day, Thanksgiving Day, the Friday after Thanksgiving, and Christmas Day.

b) Employer contributes 8% of regular hourly rate to vacation pay credit for employee with more than 5 years of service;

6% for less than 5 years' service.

ENGI0150-001 06/01/2019

BUILDING CONSTRUCTION POWER EQUIPMENT OPERATORS:

LAKE, LAPORTE, and PORTER COUNTIES

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 41.00 36.13

Page 8 of 42beta.SAM.gov

GROUP 2.....................$ 40.20 36.13

GROUP 3.....................$ 35.90 36.13

GROUP 4.....................$ 33.70 36.13

GROUP 5.....................$ 28.25 36.13

POWER EQUIPMENT OPERATOR CLASSIFICATIONS:

GROUP 1: Asphalt Plant; Autograde; Batch Plant); Benoto

(requires 2 engineers; Boiler & throttle valve; Boring machine (mining machine); Caisson Rigs; Central redi-mix plant; Combination Backhoe Endloader with backhoe bucket over 1/2 cu. yd. or with attachments; Combination tugger hoist & air compressor; Compressor & throttle; Concrete

Breaker (truck mounted); Concrete conveyor; Concrete conveyor (truck mounted); Concrete paver over 27E cu.ft.;

Concrete paver 27E cu. ft. & under; Concrete placing boom;

Concrete pump/grout pump with boom (truck mounted);

Concrete pump with boom (truck mounted); concrete tower;

Cranes and Backhoes (All Attachments); Cranes, Hammerhead

Tower; Creter Crane; Derricks (all); Derricks (traveling);

Forklift lull type; Forklift, 10 ton & over; Gradall, Hoist

1, 2, and 3 drums; Hoist (2 tugger l floor), Hydraulic Boom truck, Laser Screed, Locomotive (all), Motor patrol, Mucking Machine; Pile Driving and Skid rig, Pit machine, Prestress Machines, Pump cretes (and similar types), Rock

Drill (self-propelled), Rock Drill Truck mounted; Slip form paver, Straddle buggies, Tractor with boom and side boom, Trenching Mechine; Winch Tractors, Welding machines (6-9), GROUP 2: Air Comporessor (3) (feeding a common receiver);

Asphalt Spreader; boilers; bulldozers; Combination Backhoe end loader with Backhoe bucket 1/2 cu. yd. and under or with attachments; Corboy drilling machine; Grader, Elevating; Grouting machines; Guard rail post driver;

Highlift Shovel or frontend loader; Hoist (automatic), Hoist (all elevators); Hoist (tugger and single drum); Post hole digger; rollers (all); Scoop (tractor drawn); Stone

Page 9 of 42beta.SAM.gov crushers; Tournapull; Winch trucks

GROUP 3: Air compressor - small 210 and under (1 to 5 not to exceed a total of 300 feet); Air compressor - large over

210; Air compressor (2) feeding a common receiver;

Combination - small equipment operator; Concrete mixer (two bag & over); Conveyor, portable; Forklift-under 10 ton;

Generator; Pumps (1 to 3 not to exceed a total of 300 feet); Pumps, well points; Steam generators; Tractors, farm

& similar type; Welding machines (2 thru 5); Winches, 4 electric drillo winches

GROUP 4: Bull gang (crane erection crew); Heaters, mechanical (1 to 5); Oilers; Switchmen

GROUP 5: Fork lifts (Housing and commercial only)

ENGI0150-012 06/01/2019

BUILDING CONSTRUCTION

ST. JOSEPH COUNTY

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 29.85 29.60

GROUP 2.....................$ 28.50 29.60

GROUP 3.....................$ 27.70 29.60

GROUP 4.....................$ 26.90 29.60

GROUP 5.....................$ 24.30 29.60

POWER EQUIPMENT OPERATOR CLASSIFICATIONS:

GROUP 1: Mechanic, Asphalt Plant, Asphalt Spreader, Auto

Grader; Batch Plant, Benoto (requires 2 Engineers), Boiler

Page 10 of 42beta.SAM.gov and Throttle Valve, Boring Machine (road), Bulldozers (with engines of 140 net horse power or more) Caisson Rigs, Central Redi-mix Plant, Concrete Conveyor Systems, Concrete

Power (over 27E cu. ft.), Concrete Paver (27E cu. ft. and under), Concrete Pumps/Grout cncrete placer (Truck

Mounted), Concrete Tower, Cranes and backhoes (all), Cranes, Hammerhead Tower, Creter Crane, Derricks (all), Forklift (capble of hoisting and mechanically moving forks horizontally), Grader, Elevating, Highlift Shovels or Front

End Loaders (over 3 yd bucket), Hoists (2 or more drums), Locomotives (all), Laser screed, Motor Patrol, Pile Drivers and Skid Rig, Pre-Stress Machines, Pump Cretes & Similar

Types, Rock Drill (Self-Propelled), Rock Drill (self propelled Truck Mounted), Scoops (tractor drawn), Slip-Form

Paver, Tournapull, Tractor with Boom & Side Boom, Trenching

Machine (12 or more inches in width), Combination Backhoe

Front End Loader Machine with backhoe 1/2 yd bucket or attachments.

GROUP 2: Air Compressor (600 cu. ft. and over), Bob Cat

(over 3/4 cu. yd.), Boilers, Broom (all powered propelled), Bull Dozers with engines of less than 140 net horsepower, combination backhoe front end loader 1/2 yf bskhhoe or under, Compressor and Throttle Valve, Concrete Breaker

(truck mounted), Concrete Mixer (of moore than 21 cu. ft.

capacity), Forklift (with fixed or tilt mast), Greaser

Engineer, Highlift shovel or front endloader 3 yd bucket and under, Hoists (1 drum), Hydrulic Boom Truck, Post Hole

Digger (vehicle mounted), Pump Cretes (squeze crete type pumps, Gypsum, bulker , Rollers(all), Steam Generators, Stone Crushers, Stradddle Buggies, Tractors, Winch Trucks

(with ""a"" frame.

GROUP 3: Buck Hoist, Combination (small equipment operator), .Conveyor (portable), Grouting Machine, Hoist Elevators

(material and personnel), Hydraulic Power Units, Grouting and Pile Driving, Stud Welder, Trenching Machines less than

Page 11 of 42beta.SAM.gov

12 inches in width, Welding Machines (8 through 15).

GROUP 4: Bobcat (up to and including 3/4 cu. yd.).

Compressor (over 210 cu. ft. and less than 600 cu. ft.), Generator (over 50 kw.), Heaters, Mechanical, Hoists (all elevator, permanent installation), Hoist (automatic), Hoist

(tugger single drum), Oilers, Pumps, Well Points and electric submersible, Small Rubber Tired End Loaders (1/4

cu. yd. and under), Tractors (farm type) Welding Machines

(2 through 8).

GROUP 5: Bobcats and forklifts (commercial or residential).

ENGI0150-014 05/01/2019

POWER EQUIPMENT OPERATOR HEAVY/HIGHWAY

LAKE, LAPORTE, PORTER AND ST. JOSEPH COUNTIES

Rates Fringes

POWER EQUIPMENT OPERATOR

GROUP 1.....................$ 41.20 34.65

GROUP 2.....................$ 40.75 34.65

GROUP 3.....................$ 40.30 34.65

GROUP 4.....................$ 39.10 34.65

GROUP 5.....................$ 38.05 34.65

POWER EQUITMENT OPERATOR CLASSIFICATIONS

GROUP 1: Asphalt plants (construction), Asphalt plant

(permanent), Auto Patrol (Maintainer), Automatic Dry

Batch Plant, Automated Concrete Placer, Automated

Sub-Grader, Automated Slip Form Paver, Automated Finish

Machine, Combination Backhoe Front, End Loader Machine

(1/2 cu. yd.), Backhoe bucket or over or with attachments), Page 12 of 42beta.SAM.gov

Combination backhoe 1 cu yd, Backhoe bucket or over or with attachments, Ballast Regulator (RR), Belt Loader

(stationary), Boring Machine (road), Bulldozer, Concrete

Mixer(27 cu. ft. or over), Concrete Pump (truck mounted), Concrete Breaker (truck mounted and self-propelled), Core

Drilling Machine, Cranes and Backhoes (all attachments), Cranes, Hammerhead, Creter Crane, Crushers (concrete, rock, recycling, etc.), Derricks , Derricks (traveling), Dredge

Operator, Formless Curb and Gutter Machine (36 inches and over), Formless Curb and Gutter Machine under 36 inches, Gradall and Machines (of a like nature), Guardrail Post

Driver (truck mounted), Lead Greaser, Helicopter, Highlift

Shovel (3 yd. and over), Hoist (1 drum), Hoist (2, and 3 drums), Hydraulic Power Units (grouting, piledriving and extracting) Hydro or water blaster (self-propelled), Locomotive Operators, Mechanic, Welder, Mucking Machine, Panelboard Concrete Plant (central mix type), Paver

(Hetherington), Pile Driver (Skid or Crawler), Road Paving

Mixer, Rock Drill Crawler or Skid Rig, Rock Drill (truck

Mounted), Ross Carrier, Roto Mill Grinder (36"" and over), Roto mill grinder (less than 36""), Throttle Valve and

Compressor or Clever Brooks Type Combination, Throttle

Valve and Fireman Combination or Horizontal or Upright

Boiler, Tournapull or similar type equipment, Tractor

(boom), Tractor Drawn Belt Loader with attached Pusher

(requires two engineers), Trench Machine, Tug Boat

Operator, Wheel Excavator, Winch Tractor with ""a"" frame, Scoops, Turnapull or similar types machine used in Tandem

(add $1.00 to class l hourly rate for each machine attached there to).

GROUP 2: Combination Backhoe Front End Loader Machine with less than 1/2 cu. yd., Backhoe Bucket or with attachments, Bituminous Mixer, Bituminous Paver, Bridge Deck Finisher, Concrete Mixer (less than 27 cu. ft.), Compressor and throttle valve, Compressor (common receiver 3), Greaser, Highlift Shovels (under 3 cu. yds.), Jersey Spreader or

Page 13 of 42beta.SAM.gov

Base Paver, Pavement Bump Grinder (self-propelled), Roller

(Asphalt, waterbound, Macadam, Bituminous Macadam, Brick

Surface, Sheepfoot Roller (self- propelled with blade), Surface Heater and Planer, Tamper (mutiple vibrating, asphalt waterbound macadam, bituminouus macadam, brick surface), Tractor (push), Tractor with scoop, Widener, Apsco or similar type.

GROUP 3: Back Filler, Bituminous Distributor, Broom and Belt

Machine, Bull Float, Compressor (common receiver 2), Concrete cutter wheel type (rockwell), Concrete Finishing

Machine, Concrete Spreader (power driven), Digger, Post

Hole (power driven), Finishing Machine and Bull Float, Forklift, Form Grader, Form Tamper (motor driven), Hydraulic (boom truck) when used for hauling materials, Laser screed, Mutiple Tamping Machine, Paving Breaker, Roller (earth and subbase material), Roller sheepfoot

(self-propelled), Sub-grader, Tamper, Mutipile Vibrating

(earth and subbase material), Tractaire with Drill, Tractor

(with all drawn attachements except backhoe and including

Highlift, Endloader of 1 cu. yd. capacity and less.

GROUP 4: Air Compressors, Conveyor (all), Fireman on Boiler, Generator, Grout Machine, Power curing Spraying Machine

(self-propelled), Broom (self-propelled), Seaman Tiller, Skid steer loaders, Spike Machine (RR), Stripping Machine

(paint, self-propelled), Throttle Valve, Welding Machine, Well Points System.

GROUP 5: Deck Hand, Hetherington Driver, Mechanical Heater

(1 to 5), Outboard or Inboard Motor Boat, Oiler, Power Saw

(Concrete Power Driven), Water Pump, Grasscutter.

IRON0292-001 06/01/2018

ST. JOSEPH and LAPORTE (Remainder of County) COUNTIES

Page 14 of 42beta.SAM.gov

IRONWORKER.......................$ 29.75 22.01

IRON0395-001 06/01/2018

LAKE, PORTER AND LAPORTE (FROM LAKE MICHIGAN ON NORTH TO 50

MILES S. OF LAKE MICHIGAN ON THE S. AND FROM IN/IL STATE LINE

ON W. TO 3 MILES E. OF IN. COUNTIES

Rates Fringes

IRONWORKER

SHEETER.....................$ 40.25 31.22

STRUCTURAL & ORNAMENTAL.....$ 40.00 31.22

LABO0041-001 06/01/2019

BUILDING CONSTRUCTION

LAKE COUNTY (Western Half)

Rates Fringes

Laborers:

CAISSON AND TUNNEL WORK

(Compressed & Free Air).....$ 37.53 22.50

GROUP 1.....................$ 36.03 22.50

GROUP 2.....................$ 36.78 22.50

GROUP 3.....................$ 37.03 22.50

LABORER CLASSIFICATIONS:

GROUP 1: Building and Construction Laborers; Scaffold

Builders (other than for Mason or Plasterers); Railroad

Page 15 of 42beta.SAM.gov

Workers, Masonry Wall Workers, (interior & exterior);

Portable Water, Pumps with discharge up to 3 indches;

Handling of Creosote Lumber or Like Treated Material

(excluding railroad material); Asphalt Rakers and Lutemen;

Earth compactors; Jackmen and Sheetmen Working Ditches

Deeper than Six (6) Feet in Depth; Laborers Working Ditches

Six (6) Feet in Depth or Deeper; Assembly of Unicrete Pump;

Tile Layers (sewer or field) and Sewer Pipe Layers

(metallic or non-metallic); Motor Driven Wheelbarrows and

Concrete Buggies; Hyster Operators; Pump Crete Assemblers;

Core Drill Operators; Cement, Lime or Silica Clay Handler

(bulk or bag); Handling of Toxic Materail Damaging to

Clothing; Pneumatic Spikers; Deck Engine and Winch

Operators; Water main and Cable Ducking (metallic and non-metallic); Screed Man or Screw Operator on Asphalt

Paver; Chain Saw and Demolition Saw Operators; Concrete

Saw; Concrete Conveyor Assemblers; Applying of Curing

Compound; Sinking of Wellpoints; Dewatering Header Systems

GROUP 2: Plaster Tenders, Masons Tenders; Mortar Mixers;

Welders (acetylene or electric); Cutting Torch or Burner;

Cement Nozzle Laborers; Cement Gun Operators; Scaffold

Builders for Plasterers; Scaffold Builders for Masons;

Water Blast Machine Operators; Air Tool Operators and all

Pneumatic Tool Operators, Air and Electric Vibrators and

Chpping Hammer Operators; Asbestos Removal; Hazardous Waste

Removal; All Boiler Setters Laborers, including expediters, bottom men, bell men, and Mason Tenders

GROUP 3: Dynamite Men; Drillers, Air Track or Wagon Drilling for explosives.

CAISSON AND TUNNEL WORK (Compressed & Free Air)

GROUP 1: Cage Tenders, Dump Men, Flagman, Signalman, Top

Laborers, Rod Men, Concrete Repairmen, Motor Men, Muckers, Grout Machine, Track Layers, Air Hoist, Key Board, Agitator

Page 16 of 42beta.SAM.gov

Car, Car Pushers, Concrete Laborers, Grout Laborers, Sttl

Setters, Tuggers, Switchmen, Mucking Machine, Laser Beam, Liner Plate & Ring Setter, Shield Drivers, Power Knife, Burners, Pipe Jacking Machine, Skinners, Maintenance

Technician, Miner, Bricklayer Tenders, Concrete Blowers, Drillers, Erectors, Form Men, Jackhammermen, Mining

Machine, Dynamite Men, Drillers-air track or wagon drilling for explosives.

Premium for all employees working in compressed air shall be as follows:

0 - 15 lbs. $1.00 per hour

16 - 20 lbs. 1.50 per hour

21 - 26 lbs. 2.00 per hour

27 - 33 lbs. 3.00 per hour

34 & over 4.00 per hour

LABO0041-004 04/01/2018

UTILITY CONSTRUCTION

LAKE COUNTY

Rates Fringes

LABORERS

Group 1.....................$ 31.32 17.23

Group 2.....................$ 31.62 17.23

Group 3.....................$ 32.32 17.23

LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)

GROUP 1: Construction Laborer, Carpenter Tender, Fence

Erector, Grade Checker, Guard Rail Erector, Continuous

Steel Rod or Mat Installer, Wire Mesh Layer, Joint Man

Page 17 of 42beta.SAM.gov

(Mortar, Mastic, and all other types), Lighting Installer

(Permanent or Temporary), Lineman for Automatic Grade Maker on Paving Machines, Mortar Man, Multi-Plant Erector, Rip-rap Installer (all Products and Materials), Road

Marking and Delineation Laborer, Setting and Placing of all

Precast Concrete Products, Sing Installation including supporting structure, Spraying of all Epoxy, Curing

Compound, or Like Material, Flagperson, Air Tool, Power

Tool Operator, Asphalt Raker Man, Batch Truck Dumper, Bridge Hand Rail ERector, Handler (bulk or bag cement), Chain Saw Man, Concrete Puddler, Concrete Rubber, Concrete

Saw Operator, Core Drill Operator, Eye Level, Hand Blade

Operator Hydro Seeder Man, Motor Driven Georgia Buggy

Operator, Power Driven Compactor or Taper Operator, Power

Saw Operator, Pump Crete Assembly Man, Sreed Man or Screw

Man on Asphalt Paver, Regar Installer, Sandblaster Man, Sealer Applicator for Asphalt (toxic), Setting and Placing pre-stressed on Pre-cast Concrete Structural Members, Side

Rail Setters (for Sidewalk, Side Ditches, Radii, and

Pavement), Spreader Box Tender (manua or power driven), Straw Blower Man, Subsureface Drain and Culvert Pipe Layer, Concrete Conveyor, Horizonal Boring and Jackman and

Sheetman, Pipe Greade Man, Winch and Windless Operator

Conduit Installer, Sod Layer

GROUP 2: Cutting Torch Burner, Laser Beam Aligner, Manhole

Erector, Sewer Pipe Layer, Water Line Installer, Temporary or Permanent Welders (electric or Oxy Acetylene)

GROUP 3: Air Track and Wagon Drillman, Dynamite and Powder

Man, Concrete Barrier Rail Form Setter, Concrete Saw Joint

Control Cutting

LABO0081-001 04/01/2019

HEAVY and HIGHWAY CONSTRUCTION:

Page 18 of 42beta.SAM.gov

LAKE, LA PORTE, and PORTER COUNTIES

Laborers:

GROUP 1.....................$ 30.79 18.78

GROUP 2.....................$ 31.09 18.78

GROUP 3.....................$ 31.79 18.78

LABORERS CLASSIFICATIONS (HEAVY AND HIGHWAY)

GROUP 1: Construction Laborer; Carpenter Tender; Fence

Erector; Grade Checker; Guard Rail Erector; Continuous

Steel Rod or Mat Installer; Wire Mesh Layer; Joint Man

(Mortar, Mastic, and all other types); Lighting Installer

(Permanent or Temporary); Lineman for Automatic Grade Maker on Paving Machines; Mortar Man; Multi-Plant Erector;

Rip-rap Installer (all Products and Materials); Road

Marking and Delineation Laborer; Setting and Placeing of all Precast Concrete Products; Sing Installation including

Supporting Structure; Spraying of all Epoxy, Curing

Compound, or Like Material; Flagperson; Air Tool, Power

Tool Operator; Asphalt Raker Man; Batch Truck Dumper;

Bridge Hand Rail Erector; Handler (bulk or bag cement);

Chain Saw Man; Concrete Puddler; Concrete Rubber; Concrete

Saw Operator; Core Drill Operator, Eye Level; Hand Blade

Operator Hydro Seeder Man; Motor Driven Georgia Buggy

Operator; Power Driven Compactor or Tamper Operator; Power

Saw Operator; Pump Crete Assembly Man; Screed Man or Screw

Man on Asphalt Paver; Rebar Installer; Sandblaster Man;

Sealer Applicator for Asphalt (toxic); Setting and Placeing

Prestressed on Precast Concrete Structural Members; Side

Rail Setters (for Sidewalk, Side Ditches, Radii, and

Pavement); Spreader Box Tender (manual or power driven);

Straw Blower Man; Subsurface Drain and Culvert Pipe Layer;

Concrete Conveyor; Horizonial Boring and Jackman and

Page 19 of 42beta.SAM.gov

Sheetman; Pipe Grade Man; Winch and Windlass Operator

Conduit Installer, Sod Layer.

GROUP 2: Cutting Torch Burner: Laser Beam Aligner; Manhole

Erector; Sewer Pipe Layer; Water Line Installer, Temporary or Permanent; Welders (electric or Oxy-Acetylene).

GROUP 3: Air Track and Wagon Drillman; Dynamite and Powder

Man; Concrete Barrier Rail Form Setter; General Laborer;

concrete saw, joint control cutting

LABO0081-002 04/01/2019

UTILITY CONSTRUCTION

LA PORTE & PORTER COUNTIES

Rates Fringes

Laborers:

GROUP 1.....................$ 31.09 18.78

GROUP 2.....................$ 31.39 18.78

GROUP 3.....................$ 32.09 18.78

LABORERS CLASSIFICATIONS (UTILITY CONSTRUCTION)

GROUP 1: Construction laborer; Fence erector; Flagger; Grade checker; Guard rail erector; Wire mesh layer; Joint man

(mortar, mastic and all other types); Lighting installer

(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plate erector;

Rip-rap installer (all products and materials); Road marking and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power

Page 20 of 42beta.SAM.gov tool, and power equipment operator; Asphalt lute man;

Asphalt raker man; Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man;

concrete puddler; concrete rubber; Concrete saw operator;

Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven Georgia buggy operator;

Power-driven compactor or tamper operator; Power saw operator; Pumpcrete assembly man; Screed man or screw man on asphalt paver; Rebar installer; Sandblaster man; Sealer applicator for asphalt (toxic); Setting and placing prestressed or precast concrete structural memebers; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven);

Straw blower man; Subsurface drain and culvert pipe layer;

Transverse and longitudinal hand bull float man; Concrete conveyor assembly man; Horizontal boring and jacking man;

Jackman and sheetman; Pipe grade man; Winch and windlass operator

GROUP 2: Cutting torch burner; Laser beam aligner; Manhole erector; Sewer pipe layer; Water line installer, temporary or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier

(tending bricklayers); TVing and associated grouting of utility lines

GROUP 3: Air track and wagon drillman; Concrete barrier rail form setter; Dynamite and powder man; General leadman;

Concrete Saw Joint Control cutting

LABO0081-004 06/01/2019

LAKE (Eastern Half), LA PORTE, and PORTER COUNTIES

Rates Fringes

Page 21 of 42beta.SAM.gov

Laborers

GROUP 1.....................$ 36.03 22.50

GROUP 2.....................$ 36.78 22.50

GROUP 3.....................$ 37.03 22.50

LABORER CLASSIFICATIONS (Building Construction)

GROUP 1: Building and Construction Laborers; Scaffold

Builders (other than for Mason or Plasterers); Mechanic

Tenders; Rodmen and Chainmen, Railroad Workers, Masonry

Wall Workers, (interior & exterior); Roofer Tenders, Cement

Finisher Tenders, Carpenter Tenders, Portable Water, Pumps with discharge up to 3 inches; Waterproofing; Hauling of

Creosote Lumber or Lutemen; Asphalt Rakers; Kettlem, Earth

Compactors; Jackman and Sheetmen in Ditches more than 6 ft.

deep; Laborers in ditches 6' deep or deeper; Assembly of

Uncrete Pump; Tile Layers (sewer or field); Sewer Pipe

Layers; Motor driven Wheelbarrows and Concrete Buggies;

Hyster Operator; Pump Crete Assemblers; Core Drill

Operator; Cement, Line or Silica Clay Handers; Handling of

Toxic Materials damaging to clothing; Pneumatic Spikers;

Deck Engine and Winch Operator; Water Main and Cable

Ducking; Screed Man or Screw Operator on Asphalt Paver;

Chain Saw and Demolition Saw Operator; Concrete Conveyor

Assembler

GROUP 2: Plaster Tenders, Masons Tenders; Mortar Mixers;

Welders (acetylene or electric); Cutting Torch or Burner;

Cement Nozzle; Cement Gun; Scaffold Builders when working for Plasterers, and Mason; Water Blast Machine Operator;

Air Tool Operators and all Pheumatic Tool Operators; Air and Electric Vibrators and Chipping Hammer Operators;

Asbestos Removal; Hazardous Waste Removal

GROUP 3: Dynamite Men; Drillers, Air Track or Wagon Drilling for explosives; Laborer Specialist

Page 22 of 42beta.SAM.gov

LABO0645-001 06/01/2018

BUILDING CONSTRUCTION

ST JOSEPH COUNTY

Rates Fringes

Laborers:

GROUP 1.....................$ 22.58 15.05

GROUP 2.....................$ 22.78 15.05

GROUP 3.....................$ 23.33 15.05

BUILDING CONSTRUCTION

GROUP 1: Building and Construction Laborers; Scaffold

Builders (other than for Plasterers); Mechanic Tenders;

Window Washers and cleaners; Waterboys and Toolhousemen;

Roofers Tenders; Railroad Workers; Masonry Wall Washers

(interior and exterior); Cement Finisher Tenders; Carpenter

Tenders; All Portable Water pumps with discharge up to (3) inches; Plaster Tenders; Mason Tenders; Flag & Signal

Person.

GROUP 2: Waterproofing; Handling of Creosot Lumber or like treated material (excluding railroad material); Asphalt

Rakers and Lutemen; Kettlemen; Air Tool Operators and all

Pneumatic Tool Operators; Air and Electric Vibrators and

Chipping Hammer Operators; Earth Compactors Jackmen and

Sheetmen working Ditches deeper than (6) ft.in depth;

Laborers working in ditches (6) ft.in depth or deeper;

Assembly of Unicrete Pump; Tile Layers (sewer or field) and

Sewer Pipe Layer (metallic or non-metallic); Motor driven

Wheelbarrows and Concrete Buggies; Hyster Operators; Pump

Crete Assemblers; Core Drill Operators; Cement, Lime or

Silica Clay Handlers (bulk or bag); Handling of Toxic

Page 23 of 42beta.SAM.gov

Materials damaging to clothing; Pneumatic Spikers; Deck

Engine and Winch Operators; Water Main and Cable Ducking

(metallic and non-metallic); Screed Man or Screw Operator on Asphalt Paver; Chain and Demolition Saw Operators;

Concrete Conveyor Assemblers.

GROUP 3: Water Blast Machine Operator; Mortar Mixers; Welders

(Acetylene or electric); Cutting Torch or Burner; Cement

Nozzle. Laborers; Cement Gun Operator; Scaffold Builders when Working for Plasterers. Dynamite Men; Drillers - Air

Track or Wagon Drilling for explosives Hazardous and Toxic material handler, asbestos removal or handler.

LABO0645-002 04/01/2019

UTILITY CONSTRUCTION

ST JOSEPH COUNTY

Rates Fringes

Laborers:

GROUP 1.....................$ 24.27 15.70

GROUP 2.....................$ 24.57 15.70

GROUP 3.....................$ 25.27 15.70

LABORER CLASSIFICATIONS (UTILITY CONSTRUCTION)

GROUP 1: Construction laborer; Fence erector; Flagger; Grade checker; Guard rail erector; Wire mesh layer; Joint man

(mortar, mastic and all other types); Lighting installer

(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plateerector; Rip-rap installer (all products and materials); Road markin and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting

Page 24 of 42beta.SAM.gov structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power tool, and power equipment operator; Asphalt lute man; Asphalt raker man;

Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man; concrete puddler; concrete rubber; Concrete saw operator; Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven

Georgia buggy operator; Power-driven cmpactor or tamper operator; Power saw operator; Pumpcrete assembly man;

Screed man or screw man or asphalt paver; Rebar installer;

Sandblaster man; Sealer applicator for asphalt (toxic);

Setting and placing prestressed or precast concrete structural members; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven); Straw blower man; Subsurface drain and culvert pipe layer; Concrete conveyor assembly man;

Horizontal boring and jacking man; Jackman and sheetman;

Pipe grade man; winch and windlass operator.

GROUP 2: Cutting torch burner; Laser beam aligner; Manhole erector; Sewer pipe layer; Water line installer, temporary or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier

(tending bricklayers); TVing and associated grouting of utility lines.

GROUP 3: Air track and wage drillman; Concrete barrier rail form setter; Dynamite and powder man; General leadman;

Concrete Saw Joint Cutting.

LABO0645-004 04/01/2019

HEAVY AND HIGHWAY

ST. JOSEPH COUNTY

Page 25 of 42beta.SAM.gov

LABORERS

GROUP 1.....................$ 24.27 15.70

GROUP 2.....................$ 24.57 15.70

GROUP 3.....................$ 25.27 15.70

LABORER CLASSIFICATIONS (HEAVY AND HIGHWAY CONSTRUCTION)

GROUP 1: Construction laborer; Fence erector; Flagger; Grade checker; Guard rail erector; Wire mesh layer; Joint man

(mortar, mastic and all other types); Lighting installer

(permanent or temporary); Lineman for automatic grade maker on paving machines; Mortar man; Multi-plateerector; Rip-rap installer (all products and materials); Road markin and delineation laborer; Setting and placing of all precast concrete products; Sign installation including supporting structure; Spraying of all epoxy, curing compound, or like material; sod layer; Air tool, power tool, and power equipment operator; Asphalt lute man; Asphalt raker man;

Batch truck dumper; Bridge handrail erector; Handler (bulk or bag cement); Chain saw man; concrete puddler; concrete rubber; Concrete saw operator; Core drill operator, eye level; Hand blade operator; Hydro seeder man; Motor-driven

Georgia buggy operator; Power-driven cmpactor or tamper operator; Power saw operator; Pumpcrete assembly man;

Screed man or screw man or asphalt paver; Rebar installer;

Sandblaster man; Sealer applicator for asphalt (toxic);

Setting and placing prestressed or precast concrete structural members; Side rail setter (for sidewalks, side ditches, radii, and pavements); Spreader box tender (manual or power-driven); Straw blower man; Subsurface drain and culvert pipe layer; Concrete conveyor assembly man;

Horizontal boring and jacking man; Jackman and sheetman;

Pipe grade man; winch and windlass operator

GROUP 2: Cutting torch burner; Laser beam aligner; Manhole

Page 26 of 42beta.SAM.gov erector; Sewer pipe layer; Water line installer, temporary or permanent; Welder (electric or exy-acetylene) in connection with waterline and sewer work, Hod Carrier

(tending bricklayers); TVing and associated grouting of utility lines.

GROUP 3: Air track and wage drillman; Concrete barrier rail form setter; Dynamite and powder man; General leadman;

Concrete Saw Joint Cutting

PAIN0027-004 06/01/2019

LAKE COUNTY, West of Highway #41, including HAMMOND area

Rates Fringes

GLAZIER..........................$ 44.85 37.57

PAIN0091-004 06/01/2019

LA PORTE (Everything East of Hwy 39 and North of Hwy 20, including the Cities of LaPorte and Michigan City); ST. JOSEPH

COUNTIES

Rates Fringes

PAINTER

Brush & Roller, Drywall

Taping & Finishing, Vinyl/Paper Hanging.........$ 26.00 16.09

Spray.......................$ 26.50 16.09

PAIN0460-003 06/01/2019

PORTER, LAKE and the remainder of LA PORTE COUNTY)

Page 27 of 42beta.SAM.gov

Painters:

DRYWALL FINISHING..........$ 35.30 25.46

PAINTER.....................$ 34.50 25.46

PAIN1165-005 07/01/2019

LAKE (EAST OF HIGHWAY #41 EXCLUDING HAMMOND AREA), LAPORTE and

PORTER COUNTIES

Rates Fringes

GLAZIER..........................$ 36.00 24.27

PAIN1165-009 07/01/2019

ST. JOSEPH COUNTY

Rates Fringes

GLAZIER..........................$ 28.86 17.68

PLAS0101-006 06/01/2018

HEAVY/HIGHWAY

ST. JOSEPH COUNTY

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 31.50 14.30

PLAS0101-007 06/01/2018

Page 28 of 42beta.SAM.gov

BUILDING CONSTRUCTION

ST. JOSEPH COUNTY

Rates Fringes

CEMENT MASON/CONCRETE FINISHER...$ 28.84 14.48

PLASTERER........................$ 26.81 12.40

PLAS0165-001 07/01/2018

LAKE COUNTY (EXCEPT BY THE NORTHEAST SECTION LYING NORTH OF

CROWN POINT AND EAST OF GRIFFITH)

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

BUILDING CONSTRUCTION.......$ 37.28 18.53

HEAVY & HIGHWAY

CONSTRUCTION................$ 33.94 13.80

PLASTERER........................$ 32.70 17.70

PLAS0406-001 07/01/2018

LAKE COUNTY (NORTHWARD ON LAKE COUNTY LINE TO AND INCLUDING THE

CITY OF MERRILLVILLE, BUT NOT THE CITY LIMITS OF CROWN POINT)

and PORTER COUNTIES

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

BUILDING CONSTRUCTION.......$ 35.48 21.68

HEAVY & HIGHWAY

CONSTRUCTION................$ 32.00 15.74

PLASTERER........................$ 33.28 17.32

Page 29 of 42beta.SAM.gov

PLAS0438-001 06/01/2018

LAPORTE COUNTY, EASTERN PORTION OF PORTER COUNTY WEST TO BUT

NOT INCLUDING CHESTERTON IN THE NORTH AND WEST TO AND INCLUDING

KOUTS IN THE SOUTH

Rates Fringes

CEMENT MASON/CONCRETE FINISHER

BUILDING CONSTRUCTION

Cement Mason...............$ 36.01 25.40

HEAVY & HIGHWAY

CONSTRUCTION

Cement Mason...............$ 30.89 17.34

PLUM0172-006 05/28/2018

LA PORTE COUNTY (CITY OF LAPORTE) and ST. JOSEPH COUNTIES

Rates Fringes

Plumber, Pipefitter, Steamfitter......................$ 33.60 20.26

PLUM0210-001 06/01/2018

LAKE, LAPORTE (Excluding the City of LaPorte) and PORTER

COUNTIES

Rates Fringes

PLUMBER..........................$ 40.07 24.16

PLUM0597-003 06/01/2018

Page 30 of 42beta.SAM.gov

LAKE (Entire County), LA PORTE (Excluding the city of La

Porte), PORTER (Entire County)

Rates Fringes

PIPEFITTER.......................$ 48.50 31.12

ROOF0023-006 06/01/2018

LA PORTE and ST. JOSEPH COUNTIES

Rates Fringes

ROOFER

COMPOSITION.................$ 29.00 15.58

SLATE & TILE................$ 30.00 15.58

ROOF0026-003 06/01/2019

LAKE AND PORTER COUNTIES

Rates Fringes

ROOFER...........................$ 37.64 20.33

SFIN0281-001 01/01/2018

PORTER COUNTY (North of U.S. Route 30)

Rates Fringes

Sprinkler Fitters................$ 48.10 27.05

SFIN0669-002 04/01/2017

Page 31 of 42beta.SAM.gov

SPRINKLER FITTER.................$ 37.96 19.25

SHEE0020-013 07/01/2017

ST. JOSEPH COUNTY

Rates Fringes

Sheet metal worker...............$ 30.02 25.29

SHEE0020-015 07/01/2017

LAKE, LAPORTE, and PORTER COUNTIES

Rates Fringes

Sheet metal worker...............$ 42.98 23.41

TEAM0135-004 04/01/2019

LA PORTE COUNTY

Rates Fringes

TRUCK DRIVER (BUILDING

CONSTRUCTION ONLY)

GROUP 1.....................$ 29.60 A

GROUP 2.....................$ 30.10 A

GROUP 3.....................$ 30.30 A

GROUP 4.....................$ 30.45 A

GROUP 5.....................$ 30.95 A

A: $36.40 PER DAY & 450.00 PER WEEK.

TRUCK DRIVER CLASSIFICATIONS

Page 32 of 42beta.SAM.gov

GROUP 1: Single Axle Trucks, seven (7) cu. yds. or less than ten and one-half (10 1/2) tons, dupsters, scoop-mobiles five (5) cu.yds. and under or less than seven and one-half

(7 1/2) tons, mixer trucks three (3) cu.yds. and under, air compressors and welding machines, including those pulled by separate units, batch trucks-wet or dry- 2""34-E"" batches or less, truck driver helpers, warehousemen, mechanic's helpers, greasers and tiremen, all pick-up trucks and other vehicles. Drivers on dumpsters or similar dumpsters, mounted on four (4) wheel truck rated two (2) cu.yds. or less, and small pallet type fork-lift operator and drivers on pallet jacks or similar type equipment.

GROUP 2: Drivers on tandem axle eighteen (18) cu.yds. or twenty- four (24) tons gross, six (6) wheel trucks, Koehring or similar dumpsters, tract trucks, Euclids, hug bottom dumps, tournapulls, trounatrailers, tournarockers, or similar equipment when used for transportation purposes under nine (9) cu.yds. or less than thirteen and one-half

(13 1/2) tons, tandems and semi-trailer service trucks, mixer trucks over three (3) cu.yds. and including six and one-half (6 1/2) cu.yds., fork lift, four (4) wheel A-frame trucks when used for transportation purposes, four

(4) wheel winch trucks, pavement breakers, batch trucks-wet or dry- over 2 up to and including 4-""34-E"" batches two (2) men oil distributors, fork-lift under four (4) ton and vacuum trucks.

GROUP 3: Koehring or similar dumpsters, tract trucks, semi-trailer water trucks, Euclids, hug bottom dumps, tournapulls, tournatrailers, tournarockers, tractor trailers, tandems, Q- frame winch trucks, hydrolift turcks or similar equipment when used for transportation purposes, mixer trucks over six and one- half (6 1/2) cu.yds, batch trucks wet or dry over 4 - ""34-E"" batches single equipment operated by employees withing this Bargaining unit. Six

Page 33 of 42beta.SAM.gov

(6) wheel pole trailers and one (1) man oil distributors, fork-lift over four (4) ton and mobile mixers.

GROUP 4: Drivers on heavy equipment over sixteen (16) cu.yds.

or twenty-four (24) ton, such as Koehring or similar dumpsters, tract trucks, Euclids, hug bottom dumps, tournapulls, tournarockers or similar equipment when used for transportation purposes, pole trailers over six (6) wheels, water pulls, low-boy trailers tandem axles, quad axle or more no-weight limitation, diesel and/or heavy equipment mechanics.

GROUP 5: Mechanic furnishing his own tools.

TEAM0135-011 04/01/2019

Rates Fringes

TRUCK DRIVER (HEAVY AND

HIGHWAY CONSTRUCTION (LaPorte

& St. Joseph Counties))

GROUP 1.....................$ 29.66 15.94

GROUP 2.....................$ 29.71 15.94

GROUP 3.....................$ 29.76 15.94

GROUP 4.....................$ 29.81 15.94

GROUP 5.....................$ 29.86 15.94

GROUP 6.....................$ 29.91 15.94

GROUP 7.....................$ 29.96 15.94

GROUP 8.....................$ 30.01 15.94

GROUP 9.....................$ 30.06 15.94

GROUP10.....................$ 29.51 15.94

GROUP11.....................$ 30.06 15.94

GROUP12.....................$ 30.16 15.94

TRUCK DRIVER CLASSIFICATIONS

Page 34 of 42beta.SAM.gov

GROUP 1: Single/batches axle straight trucks; Batch trucks, wet or dry 3 (34E) axle or less; Single axle Grease and maintenance truck

GROUP 2: Single axle fuel and water trucks

GROUP 3: Single axle ""dog-legs"", and tandem truck or dog-legs; Winch trucks or A-frames when used for transportation purposes; Drivers on batch trucks, wet or dry over 3 (34E) batches and tandem axle grease and maintenance truck

GROUP 4: Tandem axle fuel trucks; tandem axle water trucks;

butuminous distributors (two-man)

GROUP 5: Tandem trucks over 15 tons payload; Single axle semi trucks; Farm tractors hauling material; Mixer trucks (all types); Trucks pulling tilt-top trailer single axle; Single axle low- boys; Truck-mounted pavement breakers

GROUP 6: Tandem trucks or ""dog-legs""; Semi-water Truck;

Sprinkler Truck; Heavy equipment-type water wagons, 5,000 gallons and under; butuminous distributors (one-man)

GROUP 7: Tri-axle trucks; Tandem axle semi trucks; Equipment when not self-loaded or pusher loaded, such as Koehring or similar dumpsters, track trucks, Euclid bottom dump and hug bottom dump, tournatrailers, tournarockers, Acey wagons or for similar equipment (12 cu yds or less); Mobile mixer truck; Tandem Axle trucks pulling tilt-top trailer; Tandem

- Axle lowboy; Tri- Axle batch Truck; Tri-Axle grease and maintenance truck

GROUP 8: Tandem-tandem semi trucks; Truck mechanics and welders; Heavy equipment-type water wagon over 5,000 gallons; Tri-Axle Trucks pulling tilt-top trailer;

Low-boys, tandem-tandem axle

Page 35 of 42beta.SAM.gov

GROUP 9: Low-boys, tandem tri-axle; Acey wagons up to and including 3 buckets; Equipment when not self-loaded or pusher loaded, such as koehring or similar dumpsters, Track

Trucks, Euclid bottom dump and hug bottom dump, Tournatrailers, Tournarockers, Acey wagons or for similar equipment (over 12 cu yds.)

GROUP 10: Pick-up trucks

GROUP 11: Helpers; Greasers; Tire men; Batch board tenders;

Warehouseman

GROUP 12: Acey wagon (over 3 buckets); Quad Axle Trucks;

Articulating Dump

* TEAM0142-002 06/01/2019

Rates Fringes

TRUCK DRIVER (BUILDING, HEAVY

AND HIGHWAY CONSTRUCTION

(INCLUDING ASPHALT PAVING

WORK))

LAKE AND PORTER COUNTIES

GROUP 1....................$ 32.29 28.83

GROUP 2....................$ 32.49 28.83

GROUP 3....................$ 32.69 28.83

GROUP 4....................$ 32.89 28.83

GROUP 5....................$ 33.24 28.83

GROUP 6....................$ 34.54 28.83

BUILDING, HEAVY & HIGHWAY AND ASPHALT PAVING

LAKE AND PORTER COUNTIES

GROUP 1: 2 and 3 Axle

GROUP 2: 4 Axle

Page 36 of 42beta.SAM.gov

GROUP 3: 5 Axle

GROUP 4: 6 Axle

GROUP 5: Over 6 Axles

GROUP 6: Articulated Dumps

TEAM0364-004 06/01/2018

Rates Fringes

TRUCK DRIVER

BUILDING CONSTRUCTION (St.

Joseph County)

GROUP 1....................$ 27.66 a+b

GROUP 2....................$ 27.87 a+b

GROUP 3....................$ 27.95 a+b

GROUP 4....................$ 28.53 a+b

FOOTNOTE:

a. FRINGE BENEFITS: $367.90 per week

b. HOLIDAYS: New Year's Day, Memorial Day, Fourth of July, Labor Day, Thanksgiving Day and Christmas Day.

TRUCK DRIVERS BUILDING CLASSIFICATIONS

GROUP 1: Pickup Trucks

GROUP 2: Single Axle Trucks

GROUP 3: Tandem, Triaxle and Fuel Trucks

GROUP 4: Semi Trailer Trucks

WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.

Page 37 of 42beta.SAM.gov

Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the

Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.

Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is…

This is the start of the file's text. The full file is on GovTribe.