W81G6641147343
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
REFERENCE: W912P6-14-Q-0025; TREE REMOVAL SERVICES ALONG THE DES PLAINES RIVER BY-PASS FENCE IN LEMONT, IL.
Continued on next page.
1. CONTRACT ID CODE PAGE OF PAGES
J 1 2
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 10-Sep-2014
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912P6-14-Q-0025
X 9B. DATED (SEE ITEM 11)
01-Aug-2014
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
10-Sep-2014
CODE
U. S. ARMY ENGINEER DISTRICT, CHICAGO
231 SOUTH LASALLE STREET SUITE 1500
CHICAGO IL 60604-1437
W912P6 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912P6-14-Q-0025
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
The following items are applicable to this modification:
SUMMARY OF CHANGES
AMENDMENT PARTICULARS
A. Due to USACE’s revising the Scope of Work and providing additional tree removal documentation, USACE is extending the due date to allow time for Contractor’s to review all documentation provided herein. Accordingly, this Amendment EXTENDS the due date for this Solicitation from 12 September 2014 to 17 September 2014; the time for submission of quotes remains 4:30 p.m. (CST); therefore all quotes must be furnished PRIOR to 4:30 p.m. (CST) on 17 September 2014 to be considered timely.
As a reminder and in accordance with Section M of this Solicitation, the Basis for Award is as follows:
The responsive, responsible contractor submitting the lowest priced, technically acceptable proposal. The Government reserves the right to reject any and all offers.
Offerors are reminded to include their best technical and price terms in their initial offer and not to automatically assume that they will have an opportunity to participate in discussions or be asked to submit a revised offer. The Government may make award of a conforming proposal without discussions, if deemed to be within the best interests of the Government.
The Government intends to award a contract without discussions based on initial proposals received; therefore, the proposals shall contain the Offeror’s best terms from a cost and technical standpoint.
A written notice of award or acceptance of an offer, mailed or otherwise furnished to the successful offeror within the time for acceptance specified in the offer, shall result in a binding contract without further action by either party.
Before the offer’s specified expiration time, the Government may accept an offer (or part of an offer), whether or not there are negotiations after its receipt, unless a written notice of withdrawal is received before award
B. AMENDED SCOPE OF WORK: The Scope of Work has been amended to incorporate the correct number of trees. The revised Scope of Work is attached hereto.
C. ADDITIONAL DOCUMENTATION: This Amendment is issued to add a Tree Removal List and an additional map of the project area to assist Contractor’s with identifying the trees requiring removal. Accordingly, the Tree Removal List and the additional map of the project area are hereby made a part of this Solicitation Package and are attached hereto.
D. SITE VISIT: Contractor’s are highly encouraged to conduct a site visit of the project area prior to submitting their proposal. To schedule a site visit, please contact Mr. Jeff MacDonald at (312) 813-2167.
E. POINT OF CONTACT: Greg M. Hermsen at (312) 846-5376 or gregory.m.hermsen@usace.army.mil.
(End of Summary of Changes)
CORPS OF ENGINEERS – CHICAGO DISTRICT
Scope of Work for Tree Removal Along the Des Plaines River By-Pass Fence, Lemont, IL
1. SUMMARY
The U.S. Army Corps of Engineers, Chicago District, requires the removal of 110 trees of various sizes along a section of the Des Plaines River By-Pass Fence located in Lemont, IL. The trees to be removed ranging in size from six (6) inches up to approximately five (5) feet in diameter and are of various heights.
2. TREE FELLING REQUIREMENTS
The Contractor is required to utilize proper equipment and tree felling techniques to ensure the safety of all on-site personnel, as well as to prevent damage to the Des Plaines River By-Pass Fence. The Contractor will be responsible for cutting all trees marked for removal six (6) to twelve (12) inches above ground level. All stumps shall remain in place to prevent erosion in the area. Since some of the trees to be removed are located on the opposite side of the Des Plaines River By-Pass Fence, the Contractor is required to utilize appropriate equipment to lift all fell trees over this four (4) to eight (8) foot fence. At no time shall the Contractor drag downed trees over the top of the fence as it will result in damage to the fence. Any damage that may occur to the Des Plaines River By-Pass Fence as a result of the felling or removal process shall be repaired with like materials by the Contractor, at the expense of the Contractor.
The trees to be removed are located along a gravel access road which is approximately 12 to 16 feet wide. The gravel access road also has a number of turn-around areas which the Contractor may utilize as staging and/or temporary storage areas.
The contractor shall supply all materials and equipment to complete the work.
3. TREE REMOVAL REQUIREMENTS
All fell trees shall be removed from the work area at the end of the project and be properly disposed of in accordance with all federal, state and local regulations. The Contractor has the option of chipping or logging the trees in preparation for removal from the site. The Contractor may store logged trees in eight (8) to twelve (12) foot sections in the various turn-arounds located throughout the work area; however, the Contractor shall at no time store chipped material on site for more than 24 hours.
4. SAFETY
All work specified shall be performed in accordance with US Army Corps of Engineers Safety and Health Requirements manual EM 385-1-1, Appendix A, Paragraph 11, where applicable for work done on Government property. The Contractor must have a site specific Safety Plan submitted and approved by the U.S. Army Corps of Engineers, Chicago District, prior to commencement of work, including fall protection. Work within 10 feet of the water’s edge at the Des Plaines River shall only be performed by personnel using approved work vest type PFDs and a life ring shall be kept close on site when this work is performed.
5. SCHEDULE AND PAYMENT
All work shall be completed within 45 calendar days following Contractor’s acceptance of the Purchase Order. Pay requests shall be in ENG Form 93 and submitted to the Contracting Officer Representative (COR). Payment will be made within 30 days of end of the receipt of the contractor’s invoice.
2 309+48 2 RIVER SIDE
1 310+16 1 TRAIL SIDE
5 320+48 r 320+60r 320+48t 321+08t x2 2 RIVER SIDE & 3 TRAIL SIDE 1 326+50t 1 Trail SIDE 1 330+18r 1 RIVER SIDE 1 332+28r 1 RIVER SIDE 2 333+54t x2 2 TRAIL SIDE 2 334+62t x2 2 TRAIL SIDE 1 337+70t 1 TRAIL SIDE 3 339+56r 339+74r 340+06t 2 RIVER SIDE &1 Trail Side 8 340+72r x8 8 RIVER SIDE (THEY ARE BUNCHED UP) 2 345+42t x2 2 TRAIL SIDE 4 346+74r x4 4 RIVER SIDE 3 356+50r 356+56r 358+28r 3 RIVER SIDE 1 369+44r 1 RIVER SIDE 2 373+00r 372+94t 1 RIVER SIDE & 1 TRAIL SIDE 1 376+68t 1 TRAIL SIDE 3 378+66t 378+96t 379+14t 3 TRAIL SIDE 2 379+88t 380+06r 1 TRAIL SIDE & 1 RIVER SIDE 2 380+48r 380+66r 2 RIVER SIDE 1 382+70t 1 TRAIL SIDE 1 383+60t 1 TRAIL SIDE (LEAVE FALLEN PORTION) 4 388+72r 388+84r 389+14r 388+36t 3 RIVER SIDE & 1 TRAIL SIDE 8 390+48t 390+66t 390+84r x6 6 RIVER SIDE & 2 TRAIL SIDE 1 398+30r 1 RIVER SIDE 1 401+38r 1 RIVER SIDE 2 402+10t 402+52t 2 TRAIL SIDE (MARKED ON FENCE) 4 402+82t 403+12t 403+78t 404+38t 4 TRAIL SIDE (MARKED ON FENCE) 6 405+10r 406+14r 405+84t 402+25t 405+90t 406+86t 4 TRAIL SIDE & 2 RIVER SIDE
1 405+00 1 TRAIL SIDE
1 405+00 1 TRAIL SIDE
2 409+26r 409+32t 1 RIVER SIDE & 1 TRAIL SIDE 3 410+12r 410+30r 410+00 2 RIVER SIDE & 1 TRAIL SIDE (MARKED ON FENCE) 1 410+42r 1 RIVER SIDE 3 410+90 x3 t&r 2 RIVER SIDE & 1 TRAIL SIDE 3 411+80r 412+34r 411+98t 2 RIVER SIDE & 1 TRAIL SIDE 4 415+00 x4 4 RIVER SIDE 8 420+06r 420+48r 420+60r 420+96r 421+98r 422+46r 421+38t 422+04t 6 RIVER SIDE & 2 TRAIL SIDE 2 423+24r 423+54r 2 RIVER SIDE 7 425+78t 426+44t 426+44r x2 427+00r x3 2 Trail Side & 5 River Side
Tree Removal List & Location
# OF TREES LOCATION TRAIL OR RIVER SIDE
310+00 320+00
330+00 340+00
350+00 360+00
370+00 380+00
390+00 400+00
410+00 42 0+
430+00
440+00 450+00
460+00
240+00 250+00
260+00 270+00
280+00 290+00
300+00
0+
480+00 490+00
500+00
510+00 520+00
530+00 540+00
U.S. Army Corps of Engineers Chicago DistrictEfficacy Study Interim I Overflow Fence Inspection 5-6-2011
1 IN = 1,931 FT
Coordinate System: NAD 1983 StatePlane Illinois East FIPS 1201 Feet Projection: Transverse Mercator Datum: North American 1983 False Easting: 984,250.0000 False Northing: 0.0000 Central Meridian: -88.3333 Scale Factor: 1.0000 Latitude Of Origin: 36.6667 Units: Foot US
Path: J:\MXD\Efficacy Study\field map 2-5-6-2011.mxd
Map Date: 5/10/2011
Plate 2/3
Inspect & Repair
None (CL)
Jersey Barrier
Fence
File details come from the government source that posted it. Updated .