This document is an Amendment (No. 0002) to a solicitation for the Tow Haulage Gearbox and Limit Switch Rehabilitation at the Nickajack Auxiliary Lock in Jasper, Tennessee. The base contract requires the contractor to remove the tow haulage high-speed gearbox, replace all seals, gaskets, flexible couplings, bearings, and the limit switch, recoat the interior of the gearbox, and diagnose a high-pitch noise. Removal and installation of the gearbox will be performed by others. Option 1 of the contract includes replacing all shafts and gears.
The amendment adds language allowing the government to request additional work not initially specified, with the contractor required to submit a price schedule and timeline for such work. The solicitation also emphasizes veteran employment, encouraging U.S. Army Corps of Engineers contractors to promote training and employment of U.S. veterans, and provides resources for veteran employment assistance. The contract is identified by Solicitation No. W912P525QA032 and is focused on mechanical rehabilitation of lock and dam equipment.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Solicitation No. W912P525QA032
Amendment No. 0002
I. CHANGES TO TECHNICAL SPECIFICATIONS.
a. Section 01 11 00 “Summary of Work” Paragraph 1.1 “Scope”, “If upon review of the report the government agrees that additional work that is not specifically identified herein is necessary, the contractor shall submit a price schedule for the additional work. The contractor shall also submit the additional time needed to complete the agreed upon work. The contact will be amended to reflect the addition of the agreed upon work.” has been added.
-- END OF AMENDMENT NO. 0002 TECHNICAL CHANGES --
Tow Haulage Gearbox and Limit Switch Rehab Nickajack Auxiliary Lock W912P525QA032 Amendment 0002 Jasper, TN
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 Scope
1.1.1 Base Contract
1.1.2 Option 1
1.2 VETERAN EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS
CONTRACTS
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 01 11 00 Page 2
SECTION 01 11 00
SUMMARY OF WORK
PART 1 GENERAL
1.1 Scope
The work covered under this contract consists of the replacement of all seals, all gaskets, flexible couplings, all bearings, and limit switch for the tow haulage high speed gearbox. The interior of the gear box must also be recoated. Under this contract the contractor must also diagnose the high pitch noise made by the highspeed gear box and give recommendations on repairs. A description of the breakdown of the work can be found herein or in Specification Section 01 20 00 PRICE AND PAYMENT PROCEDURES. All work must be performed in strict accordance with this specification and the applicable drawings, and must be subject to the terms and conditions of the contract.
If upon review of the report the government agrees that additional work that is not specifically identified herein is necessary, the contractor shall submit a price schedule for the additional work. The contractor shall also submit the additional time needed to complete the agreed upon work. The contact will be amended to reflect the addition of the agreed upon work.
See Section 35 01 41 ELECTROMECHANICAL OPERATING MACHINERY FOR LOCKS AND DAMS for more information.
1.1.1 Base Contract
Under the Base Contract, the tow haulage high speed gearbox and flexible coupling will be picked up by the contractor and taken to their shop. The flexible coupling, seals, gaskets, bearings, and the limit switch will be replaced. The gearbox half of the coupling must be assembled, the electric motor half of the coupling will be assembled by others. The interior of the gear box must also be recoated. The contractor must also diagnose the high pitch noise made by the highspeed gear box and give recommendations on repairs. Removal and installation of gearbox from base will be done by others.
1.1.2 Option 1
Under option 1 of this contract the contractor must replace all shafts and gears.
1.2 VETERAN EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
In addition to complying with the requirements outlined in FAR Part 22.13 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-35 EQUAL OPPORTUNITY FOR VETERANS, FAR Clause 52.222-37 EMPLOYMENT REPORTS ON VETERANS, DFARS
222.13 SPECIAL DISABLED AND VIETNAM ERA VETERANS, and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the
SECTION 01 11 00 Page 3 solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:
- U.S. Department of Labor Veterans employment: www.vets.gov/
- Federal veteran employment information:
www.fedshirevets.gov/index.aspx
- Veterans' Employment and Training Service (VETS):
http://www.dol.gov/vets/
- Veterans Opportunity to Work (VOW) Program:
http://benefits.va.gov/vow/
- U.S. Army Warrior Transition Command Employment Index:
http://www.wct.army.mil/modules/employers/index.html
- Hiring Our Heroes initiative:www.uschamberfoundation.org/hiring-our-heroes
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --
SECTION 01 11 00 Page 4
| DIVISION 01 - GENERAL REQUIREMENTS |
| 01 11 00 - SUMMARY OF WORK |
| SUMMARY OF WORK |
| PART 1 GENERAL |
| 1.1 Scope |
| 1.1.1 Base Contract |
| 1.1.2 Option 1 |
1.2 VETERAN EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS
| PART 2 PRODUCTS |
| PART 3 EXECUTION |
File details come from the government source that posted it. Updated .