This document is an Amendment (No. 0002) to a federal solicitation for the Williams Street Detention Structure project, detailing technical changes to specifications and plans. The amendment modifies multiple technical sections including Price and Payment Procedures, Government Safety Requirements, Quality Control, Seeding, and Articulating Concrete Block Revetments. Specific changes include revisions to payment paragraphs, planting dates, seed mixtures, and concrete block mattress specifications.

Technical plan changes involve updates to several sheets (G-003, C-301, L-101, CU-501), such as adding hydroseeding embankment hatching, leveling planting displays, and updating detail references. These modifications are part of the U.S. Army Corps of Engineers' solicitation for a small business construction contract valued between $1-5 million, focused on creating a flood risk management structure in Cleveland, Tennessee, with a 190-calendar day delivery timeline.

View the file

Other files

Show all 18

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912P5-25-B-A005 Amendment No. 0002

I. CHANGES TO TECHNICAL SPECIFICATIONS

A. Section 01 20 00 PRICE AND PAYMENT PROCEDURES. Remove Section 01 20 00 in its entirety and replaced with revised Section 01 20 00 PRICE AND PAYMENT

PROCEDURES.

1. Revised Paragraph 1.3.4.1 - Payment

2. Revised Paragraph 1.3.2 - Clearing, Grubbing, and Miscellaneous Demolition.

B. Section 01 35 26 GOVERNMENT SAFETY REQUIREMENTS. Remove Section 01 35 26 in its entirety and replaced with revised Section 01 35 26 GOVERNMENT

SAFETY REQUIREMENTS.

C. Section 01 45 00 QUALITY CONTROL. Remove Section 01 45 00 in its entirety and replaced with revised Section 01 45 00 QUALITY CONTROL.

D. Section 32 92 19 SEEDING. Remove Section 32 92 19 in its entirety and replace with revised Section 32 92 19 SEEDING.

1. Revised Table 2.1.2 - Planting Dates

2. Revised paragraph 2.1.4- Seed Mixtures by Weight.

E. Section 35 31 19.20 ARTICULATING CONCRETE BLOCK REVETMENTS.

Remove Section 35 31 19.20 in its entirety and replaced with revised Section 35 31

19.20 ARTICULATING CONCRETE BLOCK REVETMENTS.

1. Revised Paragraph 2.1 - Articulating Concrete Block Mattress

2. Revised Paragraph 3.9 - Quality Control

II. CHANGES TO TECHNICAL PLANS

A. SHEET G-003: Added Hydroseeding – Embankment Hatching B. SHEET C-301: Leveled off planting display on detail J1 C. SHEET L-101: Added Hydroseeding – Embankment Hatching D. SHEET CU-501: Updated detail reference in note

--- END OF AMENDMENT NO. 0002 TECHNICAL CHANGES---