This document is an amendment to a solicitation for a debris removal push boat. The purpose of the amendment is to: 1) Provide revisions to the government's previous answers to contractor questions to clarify any confusion, 2) Update the FAR clause on alterations to the solicitation, and 3) Confirm the quote due date remains unchanged at May 23, 2024 at 1:00 PM CT.

The underlying solicitation is a total small business set-aside to procure a fabricated push boat for use on Lake Cumberland, Kentucky. The contractor will be required to furnish all equipment, materials, labor, and a completed/approved design to fabricate the push boat, as well as provide final assembly, training, and boat launch. Delivery of the boat is an optional line item. Questions were due by April 24, 2024 and quotes are due by May 23, 2024. The solicitation is being issued by the U.S. Army Corps of Engineers, Nashville District.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Project: Debris Removal Push Boat The purpose of this amendment is to:

1.) Provide a revision to the Government answ ers to Contractor questions submitted in order to clarify any confusion.

2.) Update FAR Clause 52.252-3, Alterations in Solicitation.

3.) The quote due date remains unchanged - 23 May 2024 at 1:00PM CT.

4.) All other terms and conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 3

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912P524Q0015

X 9B. DATED (SEE ITEM 11)

08-Apr-2024

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO.

5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

16-May-2024

CODE

US ARMY CORPS OF ENGINEERS-CELRN-RC-N

DIRECTORATE OF CONTRACTING

110 9TH AVENUE SOUTH, RM A680

NASHVILLE TN 37203

W912P5 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912P524Q0015

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 1449 - CONTINUATION SHEET

The following have been added by full text:

AM 003 - Q&A REVISIONS

Contractor Question:

1.What stability standards does the boat have to meet (i.e. Intact, damage)? If damage stability is required, two transverse bulkheads will not be enough, and depth of hull may not be enough.

Government Answer:

We are on Inland Non-navigable lake, Protected waters. Reference below eCFR :: 46 CFR Part 170 -- Stability Requirements for All Inspected Vessels

See 46 CFR 170.170 and 46 CFR 170.173 – Protected Waters Standards for Stability Addition: No damage stability criteria required.

Contractor Question:

2. What are the structural standards the boat has to meet?

Government Answer:

Remove: Single Compartment Survival, but No Coast Guard Requirements

Addition: The question falls under Section 11.1.3 of the Scope of Work. Below is a clarification:

Gov allows Contractor to submit a recognized standard of structural design of their choice. (ie: ABS, ISO, or others)

W912P524Q0015

The following have been modified:

52.252-3 ALTERATIONS IN SOLICITATION (APR 1984)

Portions of this solicitation are altered as follows:

Amendment 0001

The purpose of this amendment is to:

1) Extend the Quote due date from 8 May 2024 at 1:00 PM CT to 23 May 2024 at 1:00 PM CT.

2) FAR Clause 52.252-3 Alterations in Solicitation has been added and updated to reflect Amendment 0001.

3) FAR Clause 52.252-4 Alterations in Contract has been added.

4) All other terms and conditions remain unchanged.

Amendment 0002

The purpose of this Amendment is to:

1) Provide Government answers to Contractor questions submitted via ProjNet, and provide Pilot House height information in Section 10.1.8.3 of the Scope of Work.

2) Update FAR Clause 52.252-3 Alterations in Solicitation.

3) The Quote due date remains unchanged, 23 May 2024 at 1:00 PM CT.

4) All other terms and conditions remain unchanged.

Amendment 0003:

The purpose of this amendment is to:

1) Provide a revision to the Government answers to Contractor questions submitted in order to clarify any confusion.

2) Update FAR Clause 52.252-3, Alterations in Solicitation.

3) The quote due date remains unchanged - 23 May 2024 at 1:00PM CT.

4) All other terms and conditions remain unchanged.

(End of Summary of Changes)