tspecs_w912p522b0023_bar drainage remediation_amendment 0002.pdf
PDF 42 KB Posted
- Attached to
- Barkley Dam Drainage Remediation
- Solicitation number
- W912P522B0023
About this file
This solicitation package describes a federal construction contract opportunity with the U.S. Army Corps of Engineers Nashville District. The project involves drainage remediation work at Barkley Dam in Kuttawa, Kentucky, including earthwork, culvert installation, site grading, and erosion control. The estimated value is between $250,000 and $500,000. The performance period is 365 calendar days from notice to proceed. The solicitation is a 100% total small business set-aside under NAICS code 237990. Electronic bids are due through the PIEE system by the deadline. The pre-bid site visit will be held on August 10, 2022, with registration required through submission of security forms for U.S. citizens and foreign nationals.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Drainage Remediation Barkley Lock and Dam W912P522B0023 Amendment 0001 Lyon County, KY
PROJECT TABLE OF CONTENTS
DI VI SI ON 01 - GENERAL REQUI REMENTS
01 00 00 GENERAL REQUIREMENTS
01 11 00 SUMMARY OF WORK
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 01 PROJECT SCHEDULE
01 33 00 SUBMITTAL PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 35 50 PROJECT SITE SECURITY AND AT/OPSEC PROCEDURES
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
01 78 00 CLOSEOUT SUBMITTALS
01 95 00 FORMS AND ATTACHMENTS
DI VI SI ON 31 - EARTHWORK
31 00 00 EARTHWORK
31 11 00 CLEARING AND GRUBBING
DI VI SI ON 32 - EXTERI OR I MPROVEMENTS
32 92 19 SEEDING
DI VI SI ON 33 - UTI LI TI ES
33 40 00 STORMWATER UTILITIES
33 51 39 PIEZOMETER ABANDONMENT AND REPLACEMENT
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1
THIS PAGE INTENTIONALLY LEFT BLANK
PROJECT TABLE OF CONTENTS Page 2
SECTION TABLE OF CONTENTS
DIVISION 33 - UTILITIES
SECTION 33 40 00
STORMWATER UTILITIES
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
1.2 REFERENCES
1.3 SUBMITTALS
1.4 DELIVERY, STORAGE, AND HANDLING
1.4.1 Delivery and Storage
1.4.2 Handling
PART 2 PRODUCTS
2.1 PIPE FOR CULVERTS AND STORM DRAINS
2.1.1 Concrete Pipe
2.1.1.1 Reinforced Culvert and Storm Drain Pipe
2.1.1.2 Reinforced Arch Culvert and Storm Drain Pipe
2.1.1.3 Reinforced Elliptical Culvert and Storm Drain Pipe
2.1.1.4 [Enter Appropriate Subpart Title Here]
2.2 MISCELLANEOUS MATERIALS
PART 3 EXECUTION
3.1 EXCAVATION FOR PIPE CULVERTS, BOX CULVERTS, STORM DRAINS, AND
DRAINAGE STRUCTURES
3.1.1 Trenching
3.1.2 Removal of Unstable Material
3.2 BEDDING AND INITIAL BACKFILL
3.2.1 Trenches
3.2.2 Fill Sections
3.2.3 Trenches
3.2.4 Fill Sections
3.3 PLACING PIPE
3.3.1 Multiple Culverts
3.4 JOINTING
3.4.1 Flexible Watertight Joints
3.4.2 Flexible Watertight, Gasketed Joints
3.5 FINAL BACKFILL
3.6 FIELD QUALITY CONTROL
3.6.1 Tests
3.6.1.1 Leakage Test
3.6.1.1.1 Exfiltration Test
3.6.1.1.2 Individual Pipe Joint Testing
3.6.1.2 Deflection Testing
3.6.2 Inspection
3.6.2.1 Post-Installation Inspection
3.6.2.1.1 Concrete Pipe
3.6.2.1.2 Flexible Pipe
SECTION 33 40 00 Page 1
3.6.2.1.3 Post-Installation Inspection Report
3.6.2.2 Low Impact Development Inspection
3.6.3 Repair of Defects
3.6.3.1 Leakage Test
3.6.3.2 Deflection Testing
3.6.3.3 Inspection
3.6.3.3.1 Concrete Pipe
3.6.3.3.2 Flexible Pipe
3.7 PROTECTION
3.8 WARRANTY PERIOD
ATTACHMENTS:
LID Verification Report
-- End of Section Table of Contents --
SECTION 33 40 00 Page 2
SECTION 33 40 00
STORMWATER UTILITIES
PART 1 GENERAL
1.1 MEASUREMENT AND PAYMENT
Measurement and payment will be made as specified in Section 01 20 00
PRICE AND PAYMENT PROCEDURES.
1.2 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
ASTM INTERNATIONAL (ASTM)
ASTM C76 (2020) Standard Specification for Reinforced Concrete Culvert, Storm Drain, and Sewer Pipe
ASTM C506 (2020) Standard Specification for Reinforced Concrete Arch Culvert, Storm Drain, and Sewer Pipe
ASTM C507 (2020) Standard Specification for Reinforced Concrete Elliptical Culvert, Storm Drain, and Sewer Pipe
ASTM D2321 (2020) Standard Practice for Underground Installation of Thermoplastic Pipe for Sewers and Other Gravity-Flow Applications
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for information only. When used, a code following the "G" classification identifies the office that will review the submittal for the Government.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-08 Manufacturer's Instructions
Placing Pipe and Concrete Culverts; G
SD-11 Closeout Submittals
Post-Installation Inspection Report; G
SECTION 33 40 00 Page 3
1.4 DELIVERY, STORAGE, AND HANDLING
1.4.1 Delivery and Storage
Inspect materials delivered to site for damage and unload and store materials with minimum handling. Do not store materials directly on the ground. Keep the inside of pipes and fittings free of dirt and debris.
Before, during, and after installation, protect plastic pipe and fittings from any environment that would result in damage or deterioration to the material. Keep a copy of the manufacturer's instructions available at the construction site at all times and follow these instructions unless directed otherwise by the Contracting Officer. Store solvents, solvent compounds, lubricants, elastomeric gaskets, and any similar materials required to install plastic pipe in accordance with the manufacturer's recommendations and discard if the storage period exceeds the recommended shelf life. Discard solvents in use when the recommended pot life is exceeded.
1.4.2 Handling
Handle materials in a manner that ensures delivery to the trench in sound, undamaged condition. Carry pipe to the trench.
PART 2 PRODUCTS
2.1 PIPE FOR CULVERTS AND STORM DRAINS
Pipe sizes for culverts and storm drains are indicated on the drawings.
2.1.1 Concrete Pipe
2.1.1.1 Reinforced Culvert and Storm Drain Pipe
Manufactured in accordance with and conforming to ASTM C76M ASTM C76, or
ASTM C655M ASTM C655.
2.1.1.2 Reinforced Arch Culvert and Storm Drain Pipe
Manufactured in accordance with and conforming to ASTM C506M ASTM C506.
2.1.1.3 Reinforced Elliptical Culvert and Storm Drain Pipe
Manufactured in accordance with and conforming to ASTM C507M ASTM C507.
2.1.1.4 [Enter Appropriate Subpart Title Here] Nonreinforced Culvert and Storm Drain Pipe
Manufactured in accordance with and conforming to ASTM C14M ASTM C14.
2.2 MISCELLANEOUS MATERIALS
Resilient Connectors
Provide flexible, watertight connectors conforming to ASTM C923/C923M for connecting pipe to manholes and inlets.
SECTION 33 40 00 Page 4
PART 3 EXECUTION
3.1 EXCAVATION FOR PIPE CULVERTS, BOX CULVERTS, STORM DRAINS, AND DRAINAGE
STRUCTURES
Excavate trenches, excavate for appurtenances and backfill for culverts and storm drains, in accordance with the elevations and grades shown on the Design Plans and the requirements specified below.
3.1.1 Trenching
Excavate trenches to the width indicated on the drawings or as specified herein. Trench width should permit satisfactory jointing and thorough tamping of the bedding material under and around the pipe. Place sheeting and bracing, where required, within the trench width as specified, without any overexcavation.
3.1.2 Removal of Unstable Material
Where wet or otherwise unstable soil incapable of properly supporting the pipe or box culvert, as determined by the Contracting Officer, is unexpectedly encountered in the bottom of a trench, remove such material to the depth required and replace with select granular material to the proper grade. Compact select granular material as specified in paragraph FINAL BACKFILL. When removal of unstable material is due to the fault or neglect of the Contractor while performing shoring and sheeting, water removal, or other specified requirements, perform such removal and replacement at no additional cost to the Government.
3.2 BEDDING AND INITIAL BACKFILL
Provide a firm bedding foundation of uniform density throughout the entire length of the pipe or box culvert.
3.2.1 Trenches
After the pipe has been properly bedded and haunch material placed to the midpoint (springline) of the pipe, backfill and compact the remainder of the trench by spreading and rolling or compacting by mechanical rammers or tampers in layers not exceeding 6 inches. Test for density as necessary to ensure conformance to the compaction requirements specified below.
3.2.2 Fill Sections
For pipe placed in fill sections, uniformly spread fill material longitudinally on both sides of the pipe in layers not exceeding 6 inches in compacted depth, and compact by rolling parallel with pipe or by mechanical tamping or ramming. Prior to commencing normal filling operations, the crown width of the fill at a height of 12 inches above the top of the pipe must extend a distance of not less than twice the outside pipe diameter on each side of the pipe or 12 feet, whichever is less.
After the backfill has reached at least 12 inches above the top of the pipe, place and thoroughly compact the remainder of the fill in layers not exceeding 8 inches.
3.2.3 Trenches
After the culvert trenches have been properly bedded, place selected material from excavation or borrow, at a moisture content that will
SECTION 33 40 00 Page 5 facilitate compaction, along both sides of the culvert in layers not exceeding 6 inches in compacted depth. Bring the backfill up evenly on both sides of the culvert for the full length of the culvert. Thoroughly compact each layer with mechanical tampers or rammers. Continue this method of filling and compacting until the fill has reached an elevation equal to the top of the culvert. Backfill and compact the remainder of the trench by spreading and rolling or by compacting with mechanical rammers or tampers in layers not exceeding 6 inches. Test density as necessary to ensure conformance to the compaction requirements specified below.
3.2.4 Fill Sections
Use backfill material and placement and compaction procedures for the culvert placed in fill sections as specified below. Uniformly spread the fill material longitudinally on both sides of the culvert in layers not exceeding 6 inches in compacted depth. Compacted by rolling parallel with pipe or by using mechanical tamping or ramming. After the backfill has reached at least 12 inches above the top of the culvert, place and thoroughly compact the remainder of the fill in layers not exceeding 6 inches.
3.3 PLACING PIPE
Submit printed copies of the pipe manufacturer's recommended pipe installation procedures prior to installation. Thoroughly examine each section of pipe before being laid; do not use defective or damaged pipe.
Protect plastic pipe, excluding SRPE pipe, from exposure to direct sunlight prior to laying, if necessary to maintain adequate pipe stiffness and meet installation deflection requirements. Lay pipelines to the grades and alignment indicated. Provide proper facilities for lowering sections of pipe into trenches. Do not lay pipe in water or when trench conditions or weather are unsuitable for such work. Divert drainage or dewater trenches during construction as necessary. Deflection of installed flexible pipe must not exceed the following limits:
TYPE OF PIPE MAXIMUM ALLOWABLE
DEFLECTION (percent)
Corrugated Steel and Aluminum 5
Plastic (PVC, HDPE, SRPE, and PP) 5
3.3.1 Multiple Culverts
Where multiple lines of pipe are installed, adjacent sides of pipe must be at least half the nominal pipe diameter or 3 feet apart, whichever is less.
3.4 JOINTING
Plastic Sealing Compound Joints for Tongue-and-Grooved Pipe and Box Culverts
Follow the recommendation of the particular manufacturer in regard to sealing compound special installation requirements. When lubricants, primers, or adhesives are used, only apply on surfaces that are dry and clean. Affix sealing compounds to the pipe or box culvert not more than 3 hours prior to installation of the pipe or box culvert. Protect sealing compounds from the sun, blowing dust, and other deleterious agents at all
SECTION 33 40 00 Page 6 times. Inspect sealing compounds before installation of the pipe or box culvert, and remove and replace any loose or improperly affixed sealing compound. Align the pipe or box culvert with the previously installed pipe or box culvert, and pull the joint together.
3.4.1 Flexible Watertight Joints
Use lubricants, cements, adhesives, and other special installation requirements for gaskets and jointing materials as recommended by the manufacturer. When lubricants, cements, or adhesives are used, only apply on surfaces that are clean and dry. Affix gaskets and jointing materials to the pipe not more than 24 hours prior to the installation of the pipe, and protect from the sun, blowing dust, and other deleterious agents at all times. Inspect gaskets and jointing materials before installing the pipe; remove and replace any loose or improperly affixed gaskets and jointing materials. Align the pipe with the previously installed pipe, and push the joint home. If the gasket becomes visibly dislocated when joining sections of pipe, remove the pipe and remake the joint.
3.4.2 Flexible Watertight, Gasketed Joints
Use lubricants or cements and other special installation requirements as recommended by the gasket manufacturer. Where sleeve type gaskets are used, place the gasket over one end of a section of pipe for half the width of the gasket. Then double over the other half over the end of the same pipe. When the adjoining section of pipe is in place, roll the doubled-over half of the gasket over the adjoining section. Correct any unevenness in overlap so that the gasket covers the end of pipe sections equally. Center connecting bands over adjoining sections of pipe, and place rods or bolts in position and tighten nuts. Band Tightening:
Tighten the band evenly, keep even tension on the rods or bolts, and the gasket; properly seat the gasket in the corrugations. Keep watertight joints uncovered for a period of time designated by the Contracting Officer. Before covering joints, measure the tightness of the nuts with a torque wrench. If the nut has tended to loosen its grip on the bolts or rods, retighten the nut with a torque wrench and keep uncovered until a tight, permanent joint is assured.
3.5 FINAL BACKFILL
Backfill trenches with satisfactory material deposited in layers of a maximum of 8 inches loose thickness and compacted to 90 percent of maximum density for cohesive soils and 95 percent of maximum density for cohesionless soils in accordance with Section 31 00 00 EARTHWORK .
Testing is the responsibility of the Contractor and will be performed at no additional cost to the Government. Unless otherwise specified, determine field in-place density of final backfill at a frequency of one test per 50 linear feet, or fraction thereof, of each lift of backfill.
Submit test results in accordance with Section 31 00 00 EARTHWORK . Do not displace or damage pipe or box when compacting final backfill by rolling or operating heavy equipment parallel with the pipe or box.
Movement of construction machinery over a culvert or storm drain at any stage of construction will be at the Contractor's risk. Repair or replace any damaged pipe. Protect concrete pipes with a minimum of 3 feet of cover prior to permitting heavy construction equipment to pass over them during construction. Provide the minimum cover for construction loads over corrugated steel pipes as specified in Section 26, Division II of AASHTO HB-17. Provide minimum cover for construction loads over plastic pipes as specified in ASTM D2321.
SECTION 33 40 00 Page 7
3.6 FIELD QUALITY CONTROL
3.6.1 Tests
Testing is the responsibility of the Contractor. Perform all testing and retesting at no additional cost to the Government.
3.6.1.1 Leakage Test
Test pipe lines for leakage prior to completing backfill by performing either an exfiltration test, low pressure air pipeline test or by individual pipe joint testing. Submit leakage test results to the Contracting Officer.
3.6.1.1.1 Exfiltration Test
Prior to exfiltration tests, backfill the trench up to at least the lower half of the pipe. If required, place sufficient additional backfill to prevent pipe movement during testing, leaving the joints uncovered to permit inspection. When the water table is 2 feet or more above the top of the pipe at the upper end of the pipeline section to be tested, measure infiltration using a suitable weir or other device acceptable to the Contracting Officer. Perform exfiltration test by filling the line to be tested with water so that a head of at least 2 feet is provided above both the water table and the top of the pipe at the upper end of the pipeline to be tested. Allow the filled line to stand until the pipe has reached its maximum absorption, but not less than 4 hours. After absorption, reestablish the head. Measure the amount of water required to maintain this water level during a 2-hour test period. Correct visible leaks encountered regardless of leakage test results.
3.6.1.1.2 Individual Pipe Joint Testing
Testing of individual joints for leakage by low pressure air or water must conform to ASTM C1103M ASTM C1103.
3.6.1.2 Deflection Testing
Conduct deflection test no sooner than 30 days after completion of final backfill and compaction testing. Clean or flush all lines prior to testing. Perform a deflection test on entire length of installed flexible pipeline upon completion of work adjacent to and over the pipeline, including backfilling, placement of fill, grading, paving, placement of concrete, and any other superimposed loads. Deflection of pipe in the installed pipeline under external loads must not exceed the limits in paragraph PLACING PIPE AND BOX CULVERT above as percent of the average inside diameter of pipe.
3.6.2 Inspection
3.6.2.1 Post-Installation Inspection
Inspect each segment of pipe for alignment, settlement, joint separations, soil migration through the joint, cracks, buckling, bulging and deflection. An engineer must evaluate all defects to determine if any remediation or repair is required.
SECTION 33 40 00 Page 8
3.6.2.1.1 Concrete Pipe
An engineer must evaluate all pipes with cracks with a width greater than
0.01 inches, but less than 0.10 inches to determine if any remediation or repair is required.
3.6.2.1.2 Flexible Pipe
Check each flexible pipe (PE, PVC, PP, corrugated steel and aluminum) for rips, tears, joint separations, soil migration through the joint, cracks, localized buckling, bulges, settlement and alignment.
3.6.2.1.3 Post-Installation Inspection Report
The deflection results and final post installation inspection report must include: pipe location identification, equipment used for inspection, inspector name, deviation from design, grade, deviation from line, deflection and deformation of flexible pipe, inspector notes, condition of joints, condition of pipe wall (e.g. distress, cracking, wall damage dents, bulges, creases, tears, holes, etc.).
3.6.2.2 Low Impact Development Inspection
Inspect Low Impact Development (LID) features indicated on the design portion of the LID Verification Report. Certify LID features were constructed according to plans and specifications or by submitting as-built drawings in accordance with UFGS 01 78 00 Closeout Submittals.
When as-built drawings show deviations to the LID features, document the deviations on the LID Verification Report.
3.6.3 Repair of Defects
3.6.3.1 Leakage Test
When leakage exceeds the maximum amount specified, correct source of excess leakage by replacing damaged pipe and gaskets and retest.
3.6.3.2 Deflection Testing
When deflection readings are in excess of the allowable deflection of average inside diameter of pipe are obtained, remove pipe which has excessive deflection and replace with new pipe. Retest 30 days after completing backfill, leakage testing and compaction testing.
3.6.3.3 Inspection
Replace pipe or repair defects indicated in the Post-Installation Inspection Report.
3.6.3.3.1 Concrete Pipe
Replace pipes having cracks with a width greater than 0.1 inches.
3.6.3.3.2 Flexible Pipe
Replace pipes having cracks or splits.
SECTION 33 40 00 Page 9
3.7 PROTECTION
Protect storm drainage piping and adjacent areas from superimposed and external loads during construction.
3.8 WARRANTY PERIOD
Pipe segments found to have defects during the warranty period must be replaced with new pipe and retested.
-- End of Section --
SECTION 33 40 00 Page 10
| PROJECT TABLE OF CONTENTS |
| DIVISION 33 - UTILITIES |
| 33 40 00 - STORMWATER UTILITIES |
| STORMWATER UTILITIES |
| PART 1 GENERAL |
| 1.1 MEASUREMENT AND PAYMENT |
| 1.2 REFERENCES |
| 1.3 SUBMITTALS |
| 1.4 DELIVERY, STORAGE, AND HANDLING |
| 1.4.1 Delivery and Storage |
| 1.4.2 Handling |
| PART 2 PRODUCTS |
| 2.1 PIPE FOR CULVERTS AND STORM DRAINS |
| 2.1.1 Concrete Pipe |
| 2.1.1.1 Reinforced Culvert and Storm Drain Pipe |
| 2.1.1.2 Reinforced Arch Culvert and Storm Drain Pipe |
| 2.1.1.3 Reinforced Elliptical Culvert and Storm Drain Pipe |
| 2.1.1.4 Enter Appropriate Subpart Title HereNonreinforced Culvert and |
2.2 MISCELLANEOUS MATERIALS
| PART 3 EXECUTION |
| 3.1 EXCAVATION FOR PIPE CULVERTS, BOX CULVERTS, STORM DRAINS, AND DRAINAGE |
| 3.1.1 Trenching |
| 3.1.2 Removal of Unstable Material |
| 3.2 BEDDING AND INITIAL BACKFILL |
| 3.2.1 Trenches |
| 3.2.2 Fill Sections |
| 3.2.3 Trenches |
| 3.2.4 Fill Sections |
| 3.3 PLACING PIPE |
| 3.3.1 Multiple Culverts |
| 3.4 JOINTING |
| 3.4.1 Flexible Watertight Joints |
| 3.4.2 Flexible Watertight, Gasketed Joints |
| 3.5 FINAL BACKFILL |
| 3.6 FIELD QUALITY CONTROL |
| 3.6.1 Tests |
| 3.6.1.1 Leakage Test |
| 3.6.1.1.1 Exfiltration Test |
| 3.6.1.1.2 Individual Pipe Joint Testing |
3.6.1.2 Deflection Testing
| 3.6.2 Inspection |
| 3.6.2.1 Post-Installation Inspection |
| 3.6.2.1.1 Concrete Pipe |
| 3.6.2.1.2 Flexible Pipe |
| 3.6.2.1.3 Post-Installation Inspection Report |
3.6.2.2 Low Impact Development Inspection
| 3.6.3 Repair of Defects |
| 3.6.3.1 Leakage Test |
| 3.6.3.2 Deflection Testing |
| 3.6.3.3 Inspection |
| 3.6.3.3.1 Concrete Pipe |
| 3.6.3.3.2 Flexible Pipe |
| 3.7 PROTECTION |
| 3.8 WARRANTY PERIOD |