CHEATHAM LOCK DAM SITE STOPLOG SLAB-ACCESS ROAD WIDENING (Amendment 01).docx
DOCX document 23 KB Posted
- Attached to
- Cheatham Dam Stoplog Storage Slab Federal contract opportunity
- Solicitation number
- W912P522B0007
About this file
This document outlines an upcoming federal contract opportunity for construction services at Cheatham Lock and Dam. The Nashville District of the U.S. Army Corps of Engineers intends to issue an Invitation for Bid for a firm fixed-price construction contract to build a concrete storage pad at Cheatham Dam in Ashland City, Tennessee. The pad will house six stoplogs used at the lock when not in use, and accommodate a pedestrian bridge provided under separate contracts. The base work includes removing an asphalt slab, culvert, and tree before installing a 125-foot by 50-foot by 1-foot-deep reinforced concrete slab with steel lateral supports for the stoplogs. Additional work comprises installing drainage, earthwork, reseeding, and relocating a grounding mat and terminals. Optional work includes milling and paving asphalt, additional earthwork, tree removal, fencing, a smaller slab, curbing, and drainage improvements. The estimated value is between $1,000,000 to $5,000,000. The solicitation is anticipated for release on June 7, 2022 under NAICS code 238110 with a 100% small business set-aside.
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 01 20 00 SLSSlab Bid Schedule.pdf | ||
| 01 20 00 SLSSlab Bid Schedule.pdf | ||
| 09 97 02 spec.pdf | ||
| W912P522B0007 0002.pdf | ||
| 01 20 00 Spec.pdf | ||
| Cheatham Stoplog Pad Bid Opening Info.pdf | ||
| Section 01 45 00 spec.pdf | ||
| Section 01 20 00 spec.pdf | ||
| Q12-30 35.pdf | ||
| W912P522B0007 0001 Amendment 1.pdf | ||
| US Citizen_Site Visit Form .pdf | ||
| FN _Site Visit Form.pdf | ||
| TSpecs_W912P522B0007_Cheatham Stoplog Storage Slab_RTA.pdf | ||
| TPlans_W912P522B0007_Cheatham Stoplog Storage Slab_RTA_All Signatures.pdf | ||
| PIEE Offeror Submittal Guide.pdf | ||
| PIEE Vendor Registration Guide.pdf | ||
| W912P522B0007 Cheatham Stoplog Storage Slab.pdf | ||
| Bid Schedule W912P522B0007 Cheatham Dam Stoplog Storage Slab.pdf |
Show all 18
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
W912P5-22-B-0007
AMENDMENT 0001
CHEATHAM LOCK & DAM
110’ LOCK STOPLOG STORAGE SLAB/ACCESS ROAD WIDENING
DESCRIPTION OF CHANGES
PLAN CHANGE
1. Q12-30/35 (STOPLOG STORAGE SLAB SITE DESIGN): Changed the 4” perforated pipe to utilize 4 oz. fabric in lieu of 12 oz. fabric.
SPECIFICATION CHANGE
1. Section 01 45 00: paragraph 3.4.2, Changed the second sentence to read “CQC System Manager will be a graduate Civil or Construction Management Engineer and have 4 years of experience in CQC Management or be a Construction Professional with 10 years of experience in CQC Management on Projects similar to this Contract.”
2. Section 01 45 00: paragraph 3.4.3, Added “or have successfully completed the Level 1 Tennessee Erosion Prevention and Sediment Control Training Program for Construction Sites” to the Environmental portion of the Experience Matrix.
3. Section 01 20 00: paragraph 1.2.10.1, Changed the paragraph to read “Payment for the laying of both Base and Surface courses of Asphaltic Concrete will be made at the contract unit price per Ton with both Base and Surface courses falling under a single line item on the bid schedule. Price and payment constitute full compensation for furnishing all plant, labor, equipment, and materials, and performing all operations necessary to perform the laying of both Base and Surface courses of Asphaltic Concrete. No payment for the laying of both Base and Surface courses of Asphaltic Concrete will be made until acceptance by the Contracting Officer or his/her representative.”
4. Section 01 20 00: paragraph 1.2.10.2, Changed the sentence to read “Laying of both Base and Surface courses of Asphaltic Concrete will be measured for payment by the Ton.”
5. Section 01 20 00: paragraph 1.2.10.1, Added the paragraph “No measurement will be taken for the Prime and Tack coat. It will be considered incidental to the laying of both Base and Surface courses of Asphaltic Concrete.