MOCCASIN BEND - Riverbank Protection Project Station 10900 to 8600 - TSpecs - RTA - 03AUG2022.pdf

PDF 3 MB Posted

Attached to
Moccasin Bend Bank Stabilization
Solicitation number
W912P522B0005
Issued by

About this file

This solicitation seeks construction services for bank stabilization along the Tennessee River in Chattanooga, Tennessee. Services include transportation and placement of approximately 16,000 tons of riprap and aggregate, 13,600 square yards of geotextile fabric, 3,000 cubic yards of soil fill, 2,200 square yards of geogrid, and tree/shrub planting across 2,000 feet of bank. Peripheral tasks involve limited excavation, clearing and debris removal via barge, and temporary erosion control measures. Award will be contingent upon execution of a Memorandum of Agreement between the USACE Nashville District and local Native American Tribes regarding the project area. The solicitation, technical plans and specifications provide bidding information for this requirement, with the designated contracting point of contact available to answer questions.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation No. W912P522B0005

US Army Corps Of Engineers Nashville District

Moccasin Bend Riverbank Protection Project Reach 2A Station 109+00 to 86+00

Chickamauga and Chattanooga National Park Tennessee River Chattanooga, Tennessee

Technical Specifications - Ready to Advertise (RTA) Certified Final

August 2022

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Moccasin Bend Riverbank Protection Reach 2A Tennessee River W912P522B0005 Ready To Advertise Chattanooga, TN

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 00 00 GENERAL REQUIREMENTS

01 20 00 PRICE AND PAYMENT PROCEDURES

01 32 01.10 PROJECT SCHEDULE FOR SMALL CONTRACTS

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 78 00 CLOSEOUT SUBMITTALS

01 95 00 FORMS AND ATTACHMENTS

DI VI SI ON 31 - EARTHWORK

31 05 19.13 GEOTEXTILES FOR EARTHWORK

31 11 00 CLEARING AND GRUBBING

31 23 00.00 20 EXCAVATION AND FILL

31 32 19.13 GEOGRID SOIL STABILIZATION

31 32 39 BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE

STABILIZATION

DI VI SI ON 35 - WATERWAY AND MARI NE CONSTRUCTI ON

35 31 19 STONE PROTECTION

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

PROJECT TABLE OF CONTENTS Page 2

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL SCOPE OF WORK

1.1.1 18" Force Main Utility Survey

1.2 REFERENCES

1.3 PARTNERING

1.4 COORDINATION CONFERENCES

1.5 EVALUATION OF CONTRACTOR PERFORMANCE

1.6 CONCURRENT WORK

1.7 EXISTING WORK

1.8 LOCATION OF UNDERGROUND UTILITIES

1.8.1 Notification Prior to Excavation

1.9 SPECIFIC ENVIRONMENTAL PROVISIONS FOR MOCCASIN BEND NATIONAL

ARCHAEOLOGICAL DISTRICT

1.9.1 Access by Water

1.9.2 Additional Environmental Conditions

1.10 ACCIDENT PREVENTION

1.11 SUBMITTALS

1.12 MEASUREMENT AND PAYMENT

1.13 PROJECT SIGNS

1.13.1 General

1.13.2 Materials

1.13.3 Painting

1.13.4 Erection and Maintenance

1.14 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 LAYOUT OF WORK AND INITIAL SURVEYS

3.1.1 Layout of Work

3.1.2 Pre-Construction Survey

3.2 POST CONSTRUCTION QUANTITY AND FINAL SURVEYS

3.2.1 Quantity Surveys

3.2.1.1 Quantity Survey Method for Cubic Yard items

3.2.2 Post-Construction Surveys

3.2.3 Surveys for Progress Payments

3.3 FIELD SURVEY SUBMITTALS

3.4 COORDINATION WITH THE GOVERNMENT

3.5 FINAL AS-BUILT SURVEY

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00 Page 2

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL SCOPE OF WORK

The Contractor is required to provide bank stabilization by furnishing all necessary technical expertise; planning; management; supervision;

inspection; personnel; parts; tools; fuel; equipment; vehicles and transportation; materials and supplies; except as otherwise provided for herein, required to perform the required tasks. Site access shall be exclusively from the river; however the Contractor may safely move equipment and material within the work limits to the extent required to successfully complete the project as specified herein. The Contractor is required to commence work within ten (10) days of the issuance of the Notice to Proceed, and provide the services in the performance period specified in the contract. All work shall be completed as specified, detailed and/or in strict accordance with all Terms, Conditions, General, Specific and Technical Provisions, contained herein or incorporated by reference. Survey data utilized in the contract package include a hydrographic survey completed by the Operations Branch of the USACE Nashville District in November 2020 and a topographic survey completed by the Surveying and Mapping Section of the USACE Nashville District in January 2021. Incorporation by reference shall include any and all mandatory provisions required by the Federal Acquisition Regulation (FAR) whether it is referenced or not referenced, current at time of award.

1.1.1 18" Force Main Utility Survey

In addition to the requirements provided in the paragraph GENERAL SCOPE OF WORK, the Contractor shall procure, at a minimum, 3 topographic survey shots of the 18" force main shown in the Contract drawings. These three shots shall include horizontal coordinates and elevation of the top of the pipe. The shots shall be taken such that 1) they adequately capture the layout of the utility near the extents of the water surface and the top of bank, with at least one other intermediate shot between these extents and

2) such that the shots collectively capture a full domain similar to that of the design for cross section Station 86+50. Coordination with the utility owner shall be the responsibility of the Contractor who shall not proceed with surveying the utility without first acquiring approval to do so from the utility owner.

The requirements for the survey data and its submission shall conform to the survey requirements provided in this section and the requirements of

01 78 00 CLOSEOUT SUBMITTALS.

1.2 REFERENCES

The publications listed below form a part of this section to the extent referenced. The publications are referred to within the text by the basic designation only.

SECTION 01 00 00 Page 3

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

EP 310-1-6a (2006) Sign Standards Manual, VOL 1

EP 310-1-6b (2006) Sign Standards Manual, VOL 2, Appendices

1.3 PARTNERING

In order to most effectively accomplish this contract, the Government urges the contractor to join with the Government in establishing a cohesive and professional project management team. Through this "partnering" relationship, both entities would strive to draw on the strengths of each organization for the ultimate goal of assuring that the project's intended results are achieved, within budget and on schedule.

This endeavor seeks an environment that nurtures team building, cooperation and trust between the Government and the Contractor. The partnering relationship would be bilateral in make-up, and participation will be totally voluntary.

1.4 COORDINATION CONFERENCES

Routine coordination conferences will be scheduled by the Contracting Officer throughout the life of this contract. Coordination conferences will be held to discuss contract administration, Contractor quality control, phasing, scheduling, and other aspects relating to the required work. The Corps of Engineers and the Contractor will be represented at each of these meetings. Similar information concerning replacement personnel shall be forwarded to the Contracting Officer, should any replacement be required at any time during the life of this contract.

Coordination conferences will be scheduled to occur when notified by the Contracting Officer.

1.5 EVALUATION OF CONTRACTOR PERFORMANCE

The Contractor's performance will be evaluated in accordance with FAR Part

42.15 in the areas of quality, schedule, cost control, management, utilization of small businesses, and regulatory compliance at minimum.

The evaluation will include a written narrative and rating of either exceptional, very good, satisfactory, marginal, or unsatisfactory for each. The format for the evaluation is attached at the end of Section

01 95 00 FORMS AND ATTACHMENTS.

The Contractor's review of the evaluation shall be completed electronically at the CPARS website, http://www.cpars.gov . This website also includes guidance and the user's manual.

Upon contract award, the Contractor shall provide the Contracting Officer with the name and e-mail address of the Contractor's Representative to be registered into the system. Following initial completion by the Government, the Contractor will have sixty (60) calendar days to review, comment, and return the evaluation.

1.6 CONCURRENT WORK

The work required in this contract is in addition to the routine operation

SECTION 01 00 00 Page 4 and maintenance performed by Government personnel and by other contracts.

The Government may, from time to time, perform work beyond the scope of this contract, within the geographic limits of this contract using its own personnel, volunteers or other contract personnel, and the Contractor shall be required to coordinate his efforts with such work. The Contractor's work and responsibility shall include, but shall not be limited to: all planning, programming, administration and management necessary to assure that all work is conducted in accordance with the contract and all applicable laws, regulations, codes, or directives. The Contractor shall insure that all work meets or exceeds critical reliability rates or tolerances specified, or included in referenced documents. The Contractor shall perform all related Contract administrative services necessary to perform the work such as quality control; financial control; maintenance of accurate and complete Contractor records and files; and for preparing and providing reports to the Government.

1.7 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.8 LOCATION OF UNDERGROUND UTILITIES

Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.

Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.

Identify and mark all other utilities not managed and located by the local utility companies. Verify the elevations of existing piping, utilities,and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.

1.8.1 Notification Prior to Excavation

Notify the Contracting Officer at least 15 days prior to starting excavation work.

1.9 SPECIFIC ENVIRONMENTAL PROVISIONS FOR MOCCASIN BEND NATIONAL

ARCHAEOLOGICAL DISTRICT

The following requirements are in addition to those specified in Section

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS.

SECTION 01 00 00 Page 5

1.9.1 Access by Water

Access to the jobsite shall be done from the river. All construction personnel, materials, and equipment shall be delivered to the jobsite from floating plant. Equipment operation must be confined to the floating plant. Access to top of bank will be from water only, except with prior approval of the Contracting Officer. Foot access to the top of bank shall be limited to existing utility roads and trails and shall be with prior approval of the Contracting Officer.

1.9.2 Additional Environmental Conditions

a. The entire bank shall be considered to contain significant and sensitive archeological deposits.

1.10 ACCIDENT PREVENTION

Contract Clause entitled ACCIDENT PREVENTION addresses the contract requirement to comply with the U.S. Army Corps of Engineers Safety and Health Requirements Manual, EM 385-1-1 . Accident prevention requirements for this project are also stated in Section 01 35 26 GOVERNMENTAL SAFETY

REQUIREMENTS.

1.11 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only or as otherwise designated. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Work Plan; G After award of the contract, the Contractor shall, in writing, submit a Work Plan to the Contracting Officer detailing the activities to take place during the performance of this contract.

The plan shall include activities for the protection of historical, archaeological, and cultural resources; clearing methods, operations which will be performed from the floating plant and barges; and placement processes for materials. The Contractor shall not begin work until approval of the Work Plan.

Pre-Construction Survey; G

The submittal of field survey results shall include a legible copy of all field notes, and electronic, scaled drawings of all data, including plotted cross sections. All surveys and CAD work shall also be provided in PDF format. Submittals shall meet requirements provided in paragraph POST CONSTRUCTION QUANTITY AND FINAL SURVEYS of this section. This information shall be certified by the registered land surveyor in charge of the work.

18" Force Main Utility Survey; G

SD-11 Closeout Submittals

Post-Construction Surveys; G

SECTION 01 00 00 Page 6

The submittal of field survey results shall include a legible copy of all field notes, and electronic, scaled drawings of all data, including plotted cross sections. All surveys and CAD work shall also be provided in PDF format. Submittals shall meet requirements provided in paragraph POST CONSTRUCTION QUANTITY AND FINAL SURVEYS of this section. This information shall be certified by the registered land surveyor in charge of the work.

1.12 MEASUREMENT AND PAYMENT

Measurement and payment will be made as specified in Section 01 20 00

PRICE AND PAYMENT PROCEDURES.

1.13 PROJECT SIGNS

1.13.1 General

The Contractor shall furnish and erect within 30 days after issuance of the Notice to Proceed, at an agreed location on his floating plant, a PROJECT IDENTIFICATION SIGN and a SAFETY PERFORMANCE SIGN. The signs shall be lettered on one side only and shall conform to EP 310-1-6a , EP 310-1-6b , and to the details and colors indicated in the sketches attached at the end of Section 01 95 00 FORMS AND ATTACHMENTS. The name of the project shall be as follows:

MOCCASIN BEND RIVERBANK PROTECTION

1.13.2 Materials

The sign shall be constructed with a face sheet of 3/4 inch exterior grade plywood mounted on a substantial framework of treated 4-inch by 4-inch material. Screws shall be commercial quality and of sizes shown.

1.13.3 Painting

The signs and posts shall be given one prime coat and two finish coats of exterior oil paint before lettering. Letters and trim shall be applied to one side only using one coat of enamel of color, style, and size shown.

1.13.4 Erection and Maintenance

The signs shall be erected at a location to be determined by the Contracting Officer. Signs shall be plumb and backfill of post holes shall be well tamped to properly support the signs out the life of the contract.

The signs shall be maintained in good condition until completion of the contract, shall remain the property of the Contractor.

1.14 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract.

While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are

SECTION 01 00 00 Page 7 available to assist USACE contractors in their outreach efforts:

a. U.S. Department of Labor Veterans employment: www.vets.gov/

b. Federal veteran employment information: www.fedshirevets.gov/index.aspx

c. Veterans’ Employment and Training Service (VETS):

http://www.dol.gov/vets/

d. Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/

e. U.S. Army Warrior Transition Command Search for Candidates:

http://wct.army.mil/modules/employers/e1-searchCandidates.html

f. Hiring Our Heroes initiative:

www.uschamberfoundation.org/hiring-our-heroes

PART 2 PRODUCTS (NOT USED)

PART 3 EXECUTION

3.1 LAYOUT OF WORK AND INITIAL SURVEYS

All surveying, including layout of work and quantity surveys, shall be accomplished and certified by a registered land surveyor. It is not required that the Surveyor be registered in the State where the work is being performed. Surveyor shall have no less than 5 years of experience in construction related surveying. Surveys shall be conducted in the presence of the Contracting Officer or an authorized representative unless this requirement is waived by the Contracting Officer. The Contractor shall notify the Contracting Officer not less than five working days in advance of each survey. In the event of unavailability of the Contracting Officer or an authorized representative, the Contractor shall perform the survey and certify to the Contracting Officer that it complies with these specifications. Survey results certified by the registered surveyor shall be provided to the Contracting Officer in the form of raw data and also in legible scaled plots of the data no more than three (3) days after completion.

3.1.1 Layout of Work

Prior to beginning construction, the surveyor shall locate all bench marks and control points and establish baseline(s) provided in the drawings. If a baseline has not already been established, a fixed baseline along the top of the streambank to be protected shall be established. This baseline shall be parallel to the top of bank and shall be located slightly landward of the anticipated maximum landward extent of disturbance. It shall also be located such that cross-sections surveyed perpendicular to this baseline will also be perpendicular to the streambank. From the control points and benchmarks provided by the Government, the Contractor shall complete the layout of the work and shall be responsible for all measurements that may be required for the execution of the work to the location and limit marks prescribed in the specifications or on the contract drawings, subject to such modifications as the Contracting Officer may require to meet changed conditions or as a result of necessary modifications to the contract work. The Contractor shall furnish, at his own expense, such stakes, templates, platforms, equipment, tools and materials, and all labor as may be required in laying out any part of the work. It shall be the responsibility of the Contractor to maintain and

SECTION 01 00 00 Page 8 preserve all stakes and marks established by the Contracting Officer, if any, until authorized to remove them, and if such marks are destroyed, by the Contractor or through his negligence, prior to their authorized removal, they may be replaced by the Contracting Officer, at his discretion, and the expense of replacement will be deducted from any amounts due or to become due the Contractor. The Contracting Officer may require that work be suspended at any time when location and limit marks established by the Contractor are not reasonably adequate to permit checking of the work.

3.1.2 Pre-Construction Survey

A pre-construction survey shall be required to 1) adequately capture the existing condition of entire work area to include condition/location of existing work features and to 2) provide a basis for measurement and payment of dimensionally measured pay items. For linear construction cubic yard (CY) pay items, capture cross sections at intervals that accurately depict the preexisting conditions of the area where excavation or fill operations are taking place with intervals not to exceed 100 feet. For non-linear construction, the Contractor may elect to capture cross sections as previously stated or capture an existing conditions terrain model (.dtm or .tin) depicting the existing area prior to construction operations. Cross-sections for all surveys shall be surveyed perpendicular to the streambank and shall be taken no further than 10 feet from the sections provided in the Contract Drawings, if applicable. Survey data shall 1) be referenced horizontally to the applicable State Plane Coordinate System, NAD83, using U.S. Survey Feet and vertically to NAVD88, using feet and/or 2) match the same datum using on the Contract Drawings.

Acquire adequate data to develop a terrain model with a level of accuracy to plot two-foot contours.

3.2 POST CONSTRUCTION QUANTITY AND FINAL SURVEYS

The Government shall conduct a preparatory meeting with the Contractor prior to the commencement of any work requiring quantity surveys to discuss the requirements and conditions relating to quantity surveys. The Contractor shall furnish to the Contracting Officer the electronic data in MicroStation V8i compatible files (DGN) and a comma delimited ASCII file (containing at a minimum the Point Number, Northing, Easting, Elevation, and Point Descriptor) with all submitted files and drawings being at full scale in same datum as the contract drawings (provided in the general not es) . Addi t i onal l y, pr ovi de al l CAD f i l es t o i ncl ude but not l i mi t ed t o . dt m, . t i n, . al g, . eav, . xyz, . x l s, . xsc, . pod, . t xt (raw data point clouds) and .ASCII or .XML file types used to generate the submitted .dgn electronic drawings such as contours, .dtms, plan views, profiles, and cross sections, along with any accompanying field notes (written or electronically collected) to facilitate USACE QA/QC. In addition to the .dgn electronic drawings, the contractor shall submit all drawings in .pdf format as well. Terrain model .tin files shall be translated into .XML files using the XML translator function available in AutoCAD or online to facilitate terrain model import on the USACE side.

Upon completing surveys, or portions thereof, the contractor shall not disturb the ground surface until such time that the Contracting Officer has completed Quality Assurance checks of the contractors' survey data.

The Contracting Officer reserves the right to disapprove any survey information submitted by the Contractor that lacks sufficient data.

SECTION 01 00 00 Page 9

3.2.1 Quantity Surveys

Quantity surveys as used in this clause means a topographical survey accomplished by ground methods with the display output recorded and stored in an electronic field book for further calculations in a computer.

3.2.1.1 Quantity Survey Method for Cubic Yard items

Unless otherwise authorized by the Contracting Officer, use the same means of data collection for Quantity and post-construction surveys as used for pre-construction surveys. For cubic yard (CY) pay items, capture a post-construction cross section within ten (10) longitudinal feet along the alignment in which each pre-construction cross section was taken so that the end area method of volume calculation can be accurately applied.

The cross sections should accurately display the topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill for all areas requiring cubic yard (CY) unit price measurements and payments. The Pre-Construction Survey and the Post-Construction Surveys shall be submitted in MicroStation (.dgn) format. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations. Cross sections shall be taken at 90-degrees to the linear construction item and at sufficient width beyond the limits of work to delineate the work in place. The Contracting Officer reserves the right to mandate additional cross sections be taken at locations of his or her choosing for quality assurance purposes. For cubic yard (CY) pay items where the contractor elects to capture a terrain model (.dtm or .tin) depicting pre-construction conditions, capture a post construction terrain model that accurately displays all post construction topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill and all breaklines necessary for a level of accuracy to plot two-foot contours. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations.

3.2.2 Post-Construction Surveys

Unless otherwise dictated by the Contracting Officer, the Contractor may elect to use either the cross-section method or terrain model (.dtm/.tin) method for depicting the final post construction conditions. For the Cross-Section method, capture cross sections at intervals that accurately depict the final post-construction site conditions with intervals not to exceed 100 feet. Cross sections should depict the topography of constructed features including, but not limited to: elevation, width, grades, and slopes of all items in this contract. The Contracting Officer reserves the right to mandate additional sections be taken by the Contractor at locations designated by the Contracting Officer for quality assurance purposes. Post-Construction Surveys shall be submitted in MicroStation (.dgn) format. Section observations shall be recorded at all breaks in slopes with a maximum distance of 25' between observations. For the Terrain Model (.dtm/.tin) method, capture a post construction terrain model that accurately displays all post construction topography of constructed features including, but not limited to: height, width, grades, and slopes of excavation or fill and all breaklines necessary for a level of accuracy to plot two-foot contours. Observations shall be recorded at all breaks in slopes with a maximum distance of 25 feet between observations. Provide the Contracting Officer annotated cross-sections in DGN format at locations where cross sections are taken or at 100 foot intervals for terrain model (.dtm/.tin) survey data. At a minimum, the cross sections shall extend ten feet (10') beyond the construction

SECTION 01 00 00 Page 10 footprint or each item. The annotated cross-sections shall indicate the Control line; the theoretical grades and slope-lines as specified; and the actual grades and slope lines as constructed. The Contractor shall plot cross sections from the survey data to visually depict the grade and sections obtained. The Contractor shall use this survey data to develop the as-built drawings.

3.2.3 Surveys for Progress Payments

For periods that progress payments are requested for items measured by the cubic yard, provide the before construction survey data and after/or during construction survey data that represents the actual work in-place and to be considered for payment along with the theoretical grades and slope lines provided in the drawings. For periods that progress payments are requested for items measured by units other than cubic yard, provide the in progress construction survey data that represents the actual work in-place and to be considered for payment along with the applicable theoretical grade, slope, and/or construction lines provided in the drawings. In addition to the survey data, provide plotted cross-sections and profiles indicating the theoretical grades and slope lines as specified by the contract drawings and the actual grades and slope lines as constructed. For cubic yard items, submit quantity computations calculated by the end area method or other approved method most applicable to the nature of the construction (volumes between surfaces) that verifies quantities of the completed work. For non-cubic yard items submit applicable, sections, profiles, construction lines, and/or survey boundaries to verify the work in place.

3.3 FIELD SURVEY SUBMITTALS

The submittal of field survey results shall include a legible copy of all field notes, and electronic, scaled drawings of all data, including plotted cross sections. This information shall be certified by the registered land surveyor in charge of the work.

3.4 COORDINATION WITH THE GOVERNMENT

For the purpose of coordinating with the Government, the Contractor shall schedule surveys and interactions with the Government during the normal business hours of Monday through Friday 7:30 a.m. to 4:00 p.m. Eastern Time. The Government will make every effort to make design determinations and approve segments of completed work during the performance of this contract in a timely manner.

3.5 FINAL AS-BUILT SURVEY

A final as-built survey shall be performed after all materials have been placed at the site and have been accepted by the Contracting Officer. The results of this survey will be used to check for any volume of material placed in excess of that required by the Contract Documents and the Contracting Officer, and in the preparation of the as-built drawings required in Section 01 78 00 CLOSEOUT SUBMITTALS.

-- End of Section --

SECTION 01 00 00 Page 11

SECTION 01 00 00 Page 12

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SUBMITTALS

1.2 CONTRACT COST BREAKDOWN

1.3 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.3.1 Submission of Invoices

1.4 SINGLE JOB PAYMENT ITEMS

1.4.1 Performance and Payment Bonds

1.4.1.1 Payment

1.4.1.2 Unit of Measure

1.4.2 Mobilization/Demobilization

1.4.2.1 Payment

1.4.2.2 Unit of Measure

1.4.3 Survey of Force Main Utility

1.4.3.1 Payment

1.4.3.2 Unit of Measure

1.5 UNIT PRICE PAYMENT ITEMS

1.5.1 Hand Clearing

1.5.1.1 Payment

1.5.1.2 Measurement

1.5.1.3 Unit of Measure

1.5.2 Toe Trench Excavation

1.5.2.1 Payment

1.5.2.2 Measurement

1.5.2.3 Unit of Measure

1.5.3 Soil Fill

1.5.3.1 Payment

1.5.3.2 Measurement

1.5.3.3 Unit of Measure

1.5.4 Topsoil

1.5.4.1 Payment

1.5.4.2 Measurement

1.5.4.3 Unit of Measure

1.5.5 Geogrid

1.5.5.1 Payment

1.5.5.2 Measurement

1.5.5.3 Unit of Measure

1.5.6 Geotextiles

1.5.6.1 Payment

1.5.6.2 Measurement

1.5.6.3 Unit of Measure

1.5.7 Permanent NWSG Seeding

1.5.7.1 Payment

1.5.7.2 Measurement

1.5.7.3 Unit of Measure

1.5.8 Shrub/Tree Planting

SECTION 01 20 00 Page 1

1.5.8.1 Payment

1.5.8.2 Measurement

1.5.8.3 Unit of Measure

1.5.9 Erosion Control Blankets

1.5.9.1 Payment

1.5.9.2 Measurement

1.5.9.3 Unit of Measure

1.5.10 Coir Blankets

1.5.10.1 Payment

1.5.10.2 Measurement

1.5.10.3 Unit of Measure

1.5.11 Live Stake Fascine

1.5.11.1 Payment

1.5.11.2 Measurement

1.5.11.3 Unit of Measure

1.5.12 Gravel, Choke Stone

1.5.12.1 Payment

1.5.12.2 Measurement

1.5.12.3 Unit of Measure

1.5.13 400LB Gradation Riprap

1.5.13.1 Payment

1.5.13.2 Measurement

1.5.13.3 Unit of Measure

1.5.14 3,000LB Gradation Riprap

1.5.14.1 Payment

1.5.14.2 Measurement

1.5.14.3 Unit of Measure

1.6 Additional Provisions for Barge Loads

1.7 Determination of Excess Stone

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 20 00 Page 2

SECTION 01 20 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" classification.

Submittals not having a "G" classification are for information only.

Submit the following in accordance with Section 01 33 00 SUBMITTAL

PROCEDURES:

SD-03 Product Data

Weight Certificates

1.2 CONTRACT COST BREAKDOWN

The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.

1.3 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT

1.3.1 Submission of Invoices

Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.

1.4 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

SECTION 01 20 00 Page 3

1.4.1 Performance and Payment Bonds

1.4.1.1 Payment

Payment will be made for costs associated with performance and payment bonds. In accordance with Contract Clause 52.228-1 BID GUARANTEE and Contract Clause 52.228-15 (Dev) PERFORMANCE AND PAYMENT BONDS - CONSTRUCTION, the premiums for payment and performance bonds shall be included in the contract price. Payment for the premiums for performance and payment bonds will be made at the contract price per Job for "Performance & Payment Bonds." Payments made under this provision shall not exceed the amount included for "Performance & Payment Bonds," which payment shall take into consideration any discounts or rebates to the Contractor from the Surety.

1.4.1.2 Unit of Measure

Unit of measure: job.

1.4.2 Mobilization/Demobilization

1.4.2.1 Payment

Payment will be made for costs associated with mobilization and demobilization, as defined in Special Contract Requirement PAYMENT FOR

MOBILIZATION AND DEMOBILIZATION.

1.4.2.2 Unit of Measure

Unit of measure: job.

1.4.3 Survey of Force Main Utility

1.4.3.1 Payment

Payment will be made for the contractor's successful providing of survey data of the 18" force main noted in the contract drawings in accordance with the requirements provided in Section 01 00 00 GENERAL REQUIREMENTS.

1.4.3.2 Unit of Measure

Unit of measure: job.

1.5 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for each of the unit price items.

1.5.1 Hand Clearing

1.5.1.1 Payment

Payment will be made for clearing satisfactorily performed and properly disposed of in accordance with the contract drawings and specified in

SECTION 01 20 00 Page 4

Section 31 11 00 CLEARING, AND GRUBBING. Payment will be made at the contract unit price per square yard. This price shall include consideration for all required equipment, materials and associated work, and disposal of all associated materials.

1.5.1.2 Measurement

Measurement for payment will be made to the nearest square yard of satisfactorily cleared area.

1.5.1.3 Unit of Measure

Unit of measure: square yard.

1.5.2 Toe Trench Excavation

1.5.2.1 Payment

Payment will be made for costs associated with excavation for the toe trench in accordance with the contract drawings and as specified in Section 31 23 00.00 20 EXCAVATION AND FILL, which includes performing required excavation and other operations incidental thereto including spreading of excess excavated material in the riprap.

1.5.2.2 Measurement

The total quantity of excavated material for which payment will be made will be the calculated quantity based on average end area calculations as determined by Pre-Construction survey and Post-Construction survey. No allowance will be made for overdepth excavation or for the removal of any material outside the required slope lines unless authorized. Post construction grades within +/- one-tenth of a foot of the design surface shall be payable. Post construction grades beyond those limits will result in an adjustment to the payable quantity. Areas shown to be more than one-tenth of a foot below design grade will be deducted from the payable quantity. Areas shown to be more than one-tenth of a foot above design grade will require re-work at no additional cost to the Government." For additional survey requirements for measurement of quantities, refer to Section 01 00 00 GENERAL REQUIREMENTS.

1.5.2.3 Unit of Measure

Unit of measure: cubic yard.

1.5.3 Soil Fill

1.5.3.1 Payment

Payment will be made for soil fill placement satisfactorily performed and in accordance with the contract drawings and specified in Section 31 23 00.00 20 EXCAVATION AND FILL. Payment will be made at the contract unit price per cubic yard. This price shall include consideration for all required equipment, materials and associated work of all associated materials.

1.5.3.2 Measurement

The total quantity of soil fill material for which payment will be made will be the calculated quantity based on average end area calculations as

SECTION 01 20 00 Page 5 determined by Pre-Construction survey and Post-Construction survey. No allowance will be made for over filling or for filling outside the required slope lines unless authorized.

1.5.3.3 Unit of Measure

Unit of measure: cubic yard.

1.5.4 Topsoil

1.5.4.1 Payment

Payment will be made for topsoil placement satisfactorily performed and in accordance with the contract drawings and specified in Section 31 32 39

BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE STABILIZATION AND

Section 31 23 00.00 20 EXCAVATION AND FILL. Payment will be made at the contract unit price per cubic yard. This price shall include consideration for all required equipment, materials and associated work of all associated materials.

1.5.4.2 Measurement

The total quantity of topsoil material for which payment will be measured for payment in place to the nearest cubic yard of satisfactorily placed material. No allowance will be made for over filling or for filling outside the required slope lines unless authorized.

1.5.4.3 Unit of Measure

Unit of measure: cubic yard.

1.5.5 Geogrid

1.5.5.1 Payment

Payment will be made for costs associated with procuring and installing Geogrid as shown in the contract drawings and in accordance with Section 31 32 19.13 GEOGRID SOIL STABILIZATION. Payment will be made at the contract unit price per square yard of placement and will constitute full compensation to the Contractor for providing all required equipment, materials and associated work necessary for the complete and satisfactory installation of the geogrid.

1.5.5.2 Measurement

Installed Geogrid will be measured for payment in place to the nearest square yard of protected area. The following items are included in the unit price for Geogrid and will not be counted a second time in the process of determining the extent of geogrid placed: Material and associated equipment and operation used in laps, seams, or extra length;

securing pins and associated material, equipment, and operations. No payment will be made for geogrid replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.5.5.3 Unit of Measure

Unit of measure: square yard.

SECTION 01 20 00 Page 6

1.5.6 Geotextiles

1.5.6.1 Payment

Payment will be made for costs associated with procuring and installing Geotextile Fabric as shown in the contract drawings and in accordance with Section 31 05 19.13 GEOTEXTILES FOR EARTHWORK. Payment will be made at the contract unit price per square yard and will constitute full compensation to the Contractor for providing all required equipment, materials and associated work necessary for the complete and satisfactory installation of the geotextiles.

1.5.6.2 Measurement

Installed Geotextile Fabric will be measured for payment in place to the nearest square yard of protected area. The following items are included in the unit price for Geotextiles and will not be counted a second time in the process of determining the extent of geotextile placed: Material and associated equipment and operation used in laps, seams, or extra length;

securing pins and associated material, equipment, and operations. No payment will be made for geotextiles replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.5.6.3 Unit of Measure

Unit of measure: square yard.

1.5.7 Permanent NWSG Seeding

1.5.7.1 Payment

Payment will cover all costs associated with seeding, incorporating, protecting, and maintaining the areas indicated and designated for seeding. This price shall constitute full compensation for furnishing all plants, labor, equipment, materials,and performing all operations necessary for placing and maintaining seed as specified in Section 31 32 39 BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE STABILIZATION. No payment for "NWSG seeding" will be made until acceptance by the Contracting Officer or his/her representative.

1.5.7.2 Measurement

Measurement for payment will be made to the nearest square yard of satisfactorily seeded area. Damage to areas as a result of incidental construction that falls outside the reasonable limits shall be repaired by the contractor at his/her own expense.

1.5.7.3 Unit of Measure

Unit of measure: square yard.

1.5.8 Shrub/Tree Planting

1.5.8.1 Payment

Payment will cover all costs associated with seeding,topsoiling, incorporating, protecting, and maintaining the areas indicated and designated for seeding. This price shall constitute full compensation for

SECTION 01 20 00 Page 7 furnishing all plants and topsoil, labor, equipment, materials,and performing all operations necessary for placing and maintaining seed as specified in Section 31 32 39 BIOENGINEERING PRACTICES FOR STREAM BANK AND SHORELINE STABILIZATION. No payment for Shrub/Tree Planting will be made until acceptance by the Contracting Officer or his/her representative.

1.5.8.2 Measurement

Measurement for payment will be made for each satisfactorily planted shrub/tree. Damage to areas/items as a result of incidental construction after placement shall be repaired by the contractor at his/her own expense.

1.5.8.3 Unit of Measure

Unit of measure: each.

1.5.9 Erosion Control Blankets

1.5.9.1 Payment

Payment will be made for costs associated with procuring and installing Erosion Control Blankets as shown in the contract drawings and in accordance with Section 31 32 39 BIOENGINEERING PRACTICES FOR STREAMBANK AND SHORELINE STABILIZATION. Payment will be made at the contract unit price per square yard of placement and will constitute full compensation to the Contractor for providing all required equipment, materials and associated work necessary for the complete and satisfactory installation of the erosion control blankets.

1.5.9.2 Measurement

Installed Erosion Control Blankets will be measured for payment in place to the nearest square yard of protected area. The following items are included in the unit price for Erosion Control Blankets and will not be counted a second time in the process of determining the extent of Erosion Control Blankets placed: Material and associated equipment and operation used in laps, seams, or extra length; securing pins and associated material, equipment, and operations. No payment will be made for blankets replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.5.9.3 Unit of Measure

Unit of measure: square yard.

1.5.10 Coir Blankets

1.5.10.1 Payment

Payment will be made for costs associated with procuring and installing Coir Blankets for the designated sections in the contract package and in accordance with Section 31 32 39 BIOENGINEERING PRACTICES FOR STREAMBANK AND SHORELINE STABILIZATION. Payment will be made at the contract unit price per square yard of placement and will constitute full compensation to the Contractor for providing all required equipment, materials and associated work necessary for the complete and satisfactory installation of the erosion control blankets.

SECTION 01 20 00 Page 8

1.5.10.2 Measurement

Installed Coir Blankets will be measured for payment in place to the nearest square yard of protected area. The following items are included in the unit price for Coir Blankets and will not be counted a second time in the process of determining the extent of Coir Blankets placed:

Material and associated equipment and operation used in laps, seams, or extra length; securing pins and associated material, equipment, and operations. No payment will be made for blankets replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.5.10.3 Unit of Measure

Unit of measure: square yard.

1.5.11 Live Stake Fascine

1.5.11.1 Payment

Payment will be made for costs associated with procuring and installing the live stake fascine for the designated area in the contract package and in accordance with Section 31 32 39 BIOENGINEERING PRACTICES FOR STREAMBANK AND SHORELINE STABILIZATION. Payment will be made at the contract unit price per linear foot of placement and will constitute full compensation to the Contractor for providing all required equipment, materials and associated work necessary for the complete and satisfactory installation of the erosion control blankets.

1.5.11.2 Measurement

Installed live stake fascine will be measured for payment in place to the nearest linear foot of protected area. The following items are included in the unit price for live stake fascine and will not be counted a second time in the process of determining the extent of fascine placed: Material and associated equipment and operation required and incidental to placement; securing pins and associated material, equipment, and operations. No payment will be made for fascine replaced because of waste, contamination, damage, repair, or due to Contractor fault or negligence.

1.5.11.3 Unit of Measure

Unit of measure: linear foot.

1.5.12 Gravel, Choke Stone

1.5.12.1 Payment

Payment for gravel or crushed stone acceptably placed to fill riprap voids under soil fill will be made at the applicable contract unit prices for "Gravel, Choke Stone" procured and installed as shown in the contract drawings and in accordance with Section 35 31 19 STONE, CHANNEL, SHORELINE PROTECTION FOR STRUCTURES. Price and payment shall include all costs of furnishing, hauling, placing and maintaining the material until placement of the soil cover is completed and accepted. No payment will be made for excess thickness of material

SECTION 01 20 00 Page 9

1.5.12.2 Measurement

Gravel, choke stone at an adequate gradation and adequately installed will be measured for payment in place to the nearest ton.

1.5.12.3 Unit of Measure

Unit of measure: ton.

1.5.13 400LB Gradation Riprap

1.5.13.1 Payment

Payment for riprap acceptably placed will be made at the applicable contract unit price for "400LB Gradation Riprap". Price and payment shall constitute full compensation for furnishing, hauling, handling, placing, and maintaining the riprap until final acceptance by the Government in accordance with the contract drawings and Section 35 31 19 STONE, CHANNEL, SHORELINE PROTECTION FOR STRUCTURES. No payment will be made for excess riprap left in place. Existing stone placed in lieu of new stone from off-site sources will be excluded from measurement and payment.

1.5.13.2 Measurement

Riprap at an adequate gradation and adequately installed will be measured for payment in place to the nearest ton.

1.5.13.3 Unit of Measure

Unit of measure: ton.

1.5.14 3,000LB Gradation Riprap

1.5.14.1 Payment

Payment for riprap acceptably placed will be made at the applicable contract unit price for "3,000LB Gradation Riprap". Price and payment shall constitute full compensation for furnishing, hauling, handling, placing, and maintaining the riprap until final acceptance by the Government in accordance with the contract drawings and Section 35 31 19 STONE, CHANNEL, SHORELINE PROTECTION FOR STRUCTURES. No payment will be made for excess riprap left in place. Existing stone placed in lieu of new stone from off-site sources will be excluded from measurement and payment.

1.5.14.2 Measurement

Riprap at an adequate gradation and adequately installed will be measured for payment in place to the nearest ton.

1.5.14.3 Unit of Measure

Unit of measure: ton.

1.6 Additional Provisions for Barge Loads

Upon approval by the Contracting Officer, stone delivered by barge may be measured for payment, in the presence of the Contracting Officer, by weight determined by barge displacement. Furnish the Contracting Officer a barge displacement table not less than 10 work days prior to unloading the

SECTION 01 20 00 Page 10 stone from any barge. Each table submitted shall show the name and/or number of the barge owner, the name of the fabricator, and the certification and date of certification of the person or firm preparing the table. Furnish with the barge displacement tables a drawing or sketch of each barge, dimensioned in sufficient detail to permit checking of the tables. The drawings shall show, as a minimum, the length, width, depth of the barge, and dimensions of the rake or rakes. Each such table shall have its accuracy certified by a person or firm, other than the Contractor, customarily performing this service. Each table submitted shall contain, in parallel columns, the freeboard of the barge in feet and tenths from zero to the full depth of the barge and the corresponding gross displacement to the nearest ton. Each barge shall be suitably marked with three displacement gaging locations on each side near each end of the barge and two amidship on opposite sides.