This document provides details for a federal contract opportunity for arc flash mitigation work at the J. Percy Priest Powerplant. The contract will be awarded through an Invitation for Bid as a firm fixed price construction contract between $250,000 and $500,000 to furnish supervision, engineering, labor, materials and equipment to perform field verification of existing equipment, removal and replacement of two motor control centers and associated cabling, provision of temporary power, and other work. The performance period is 365 days after notice to proceed. The pre-solicitation was released on or around August 10, 2020 with a site visit tentatively scheduled for August 18, 2020, and the NAICS code is 238210 with a small business size standard of $16.5 million. The anticipated type of set-aside is total small business and award will be to the lowest priced responsive and responsible bidder.

View the file

Other files for this federal contract opportunity

Other files attached to J. Percy Priest Arc Flash Mitigation, newest first.
File Type Posted
FINAL TSpecs JPP Arc Flash Mitigation.pdf PDF
Foreign National Site Visit Request Form .pdf PDF
W912P520B0011 Solicitation.pdf PDF
US Citizen Site Visit Request Form.pdf PDF
Draft TPlans_JPP Arc Flash Mitigation_BCOES_23JUL2020.pdf PDF
04_JPP Arc Flash Mitigation Scope Work.pdf PDF
Draft TSpecs_JPP Arc Flash Mitigation_BCOES_24JUL2020.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STEELE.LOUIS.A.1536319952 Digitally signed by STEELE.LOUIS.A.1536319952 Date: 2020.08.05 15:50:12 -05'00'

LEE.GERALD.O.1230628315 Digitally signed by LEE.GERALD.O.1230628315 Date: 2020.08.06 10:00:30 -05'00'

BAULSIR.ROBERT.W.III.1258321525 Digitally signed by BAULSIR.ROBERT.W.III.1258321525 Date: 2020.08.10 08:07:39 -05'00'

FOR R

EFERENCE O

NLY

h3ecxlas Callout Contractor Lay Down Area

NLY

h3ecxlas Polygonal Line h3ecxlas Text Box Contractor Lay Down Area.

h3ecxlas Line

H3ECXLAS

Polygonal Line

H3ECXLAS

Text Box There is an open cut in the laydown area. The Government has steel plates in place to allow traffic over the open cut. These plates may be temporarily relocated by the Contactor as needed to provide vehicular access to the power house bay. Traffic shall not cross the open cut except across the steel plates.

H3ECXLAS

Line

H3ECXLAS

Line

H3ECXLAS

Line

H3ECXLAS

Line

H3ECXLAS

Text Box Approximate Location of Overhead Power Lines

H3ECXLAS

Line

NLY

h3ecxlas Polygon h3ecxlas Text Box Hatch can be used to access the Motor Control Center on the lower Level.

h3ecxlas Line

NLY

Cover Sheet2
A02. FINAL TPlans_JPP Arc Flash Mitigation_RTA FINAL_05AUG2020
Cover Sheet
REFERENCE DGNS
q5-79^7
q5-79^11
q5-79^103.2
q5-79^104.2
q5-79^704.2
q5-79^750.18
q5-79^757.6
q5-79^764.4
q5-79^800.3
q5-79^801.8
q5-79^802.4

File details come from the government source that posted it. Updated .