US Army Corps Of Engineers

Nashville District

Caisson Slot Fillers

Wheeler, Wilson and Nickajack Locks Various Locations, Tennessee River

Technical Specifications 100%

July 2017

THIS PAGE INTENTIONALLY LEFT BLANK

FOR DUPLEX PRINTING

Caisson slot fillers Wheeler, Wilson and Nickajack Locks W912P5-17-T-0051 Tennessee River

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 00 00 GENERAL REQUIREMENTS

01 11 00 SUMMARY OF WORK

01 22 00 PRICE AND PAYMENT PROCEDURES

01 33 00 SUBMITTAL PROCEDURES - SUPPLY

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 95 00 FORMS AND ATTACHMENTS

DIVISION 05 - METALS

05 50 14 STRUCTURAL METAL FABRICATIONS

DIVISION 09 - FINISHES

09 97 02 PAINTING: HYDRAULIC STRUCTURES

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

1.2 LOCATION AND ACCESS

1.2.1 Location

1.2.2 Access to Site

1.3 SUBMITTALS

1.4 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS

CONTRACTS

1.5 PROJECT SCHEDULE

1.5.1 Initial Project Schedule Submission

1.6 MEASUREMENT AND PAYMENT

1.7 SECURITY REQUIREMENTS

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 00 00 Page 1

SECTION 01 00 00

GENERAL REQUIREMENTS

PART 1 GENERAL

1.1 GENERAL

This section comprises an explanation of the general contract requirements needed to accomplish the work. All work specified herein shall be accomplished in accordance with the procedures prescribed in the specifications and drawings.

1.2 LOCATION AND ACCESS

1.2.1 Location

Wilson Lock Wheeler Lock - Option Nickajack Auxillary Lock - Option

1.2.2 Access to Site

Access to the site to deliver the finished project needs to be coordinated with the task manager

1.3 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. The following shall be submitted in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Initial Project Schedule; G

1.4 VETERANS EMPLOYMENT EMPHASIS FOR U.S. ARMY CORPS OF ENGINEERS CONTRACTS

In addition to complying with the requirements outlined in FAR Part 22.13, FAR Clause 52.222-35, FAR Clause 52.222-37, DFARS 222.13 and Department of Labor regulations, U.S. Army Corps of Engineers (USACE) contractors and subcontractors at all tiers are encouraged to promote the training and employment of U.S. veterans while performing under a USACE contract. While no set-aside, evaluation preference, or incentive applies to the solicitation or performance under the resultant contract, USACE contractors are encouraged to seek out highly qualified veterans to perform services under this contract. The following resources are available to assist USACE contractors in their outreach efforts:

U.S. Department of Labor Veterans employment: www.vets.gov/

Federal veteran employment information: www.fedshirevets.gov/index.aspx

SECTION 01 00 00 Page 2

Veterans’ Employment and Training Service (VETS): http://www.dol.gov/vets/

Veterans Opportunity to Work (VOW) Program: http://benefits.va.gov/vow/

U.S. Army Warrior Transition Command Employment Index:

wtc.army.mil/modules/employers/index.html

Hiring Our Heroes initiative: www.uschamberfoundation.org/hiring-our-heroes

Guide to Hiring Veterans:

www.whitehouse.gov/sites/default/files/docs/white_house_business_council_-_ guide_to_hiring_veterans_0.pdf

1.5 PROJECT SCHEDULE

The Contractor shall provide project schedule submittals as described below:

1.5.1 Initial Project Schedule Submission

The Initial Project Schedule shall be submitted for approval within 30 calendar days after Award. The schedule shall provide a reasonable sequence of activities that represent work through the entire project and shall be at a reasonable level of detail.

1.6 MEASUREMENT AND PAYMENT

No separate payment will be made for the work covered under this section.

The costs thereof shall be included in the item to which the work pertains.

1.7 SECURITY REQUIREMENTS

All contractors and all associated sub-contractors shall comply with applicable District and local security policies and procedures (provided by the Government representative). The contractor shall provide any/all requested information required for background checks, background investigations and/or to meet installation/facility access requirements to be accomplished by the District Security Office. Refer to the next paragraph for background investigation requirements. Contractor workforce must comply with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

Background Investigation Requirements: Since this is a delivery and/or supply only, there are no investigation requirements. However, if the Contractor(s) enter a restricted area they shall be escorted by USACE personnel.

Contractors and/or potential contractors wishing to attend a pre-bid meeting held at or in LRN restricted/controlled areas (such as a Power Plant or Navigation Lock) shall submit a Nashville District (LRN) Security Access Form to the Nashville District Point of Contact (LRN POC) five (5) days prior to the site visit or meeting. If submitting the document in less than five days, the Offer or/Bidder may not receive approval for participation. The LRN POC will notify the Contractor if the request is approval or denied. Any pre-bid meeting which will cover

SECTION 01 00 00 Page 3 anything other than public domain information shall be limited to US Citizens, except under unique circumstances. The Security Access Form and guidance is available at http://www.lrn.usace.army.mil/BusinessWithUs/Contracting/Contract Security Requirements.

Media Free of Viruses, etc: The contractor shall ensure all media, electronic files, etc., it provides to the government shall be free of viruses, Trojan horses, bots, worms, malware, defects, or any other harmful item of a destructive nature.

Release of Information: The contractor shall not make available to the news media or publicly disclose any data generated or reviewed under this contract. Any inquiry received by the contractor for information concerning work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act of 1975, Public Law 93-502, 5 U.S.C., Section 552. The determination of whether records will be released will remain with the Government. The contractor shall assist the COR in compiling information or records for submission upon request by the government. Reports and data generated under this contract shall become the property of the Government and distribution to any other source by the contractor, unless authorized is prohibited.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 00 00 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL

1.2 SUBMITTALS

1.3 FABRICATION SCHEDULE

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

1.4.2 Location

1.5 INSPECTION AND ACCEPTANCE OF WORK

1.5.1 GENERAL

1.5.2 ACCESS TO WORK

1.6 DELIVERY OF FABRICAITONS

1.7 NON-DISCLOSURE OF GOVERNEMENT INFORMATION

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 GENERAL

This section of the Specifications provides general information and requirements. See Section 05 50 14 STRUCTURAL METAL FABRICATIONS for a detailed description of the scope of this project.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Pre-Fabrication Submittals

Delivery/Shipping Plan; G

A plan describing in detail the proposed delivery methods of the fabrications shall be submitted for approval. The plan shall be submitted at least 60 calendar days prior to the proposed delivery of any item.

Fabrication Schedule; G

A schedule outlining the fabrication and delivery dates shall be submitted for approval. The schedule shall be submitted within 30 days of issuance of Notice to Proceed (NTP) and monthly thereafter.

1.3 FABRICATION SCHEDULE

A fabrication and delivery schedule shall be submitted within 30 calendar days of issuance Notice to Proceed (NTP) and monthly thereafter. Schedule shall reflect major milestones for the contract, i.e. material procurement, fabrication of embedded metals, fabrication of slot fillers, painting, delivery, etc. Completed work shall be clearly identified on the schedule updates.

1.4 WORK COVERED BY CONTRACT DOCUMENTS

1.4.1 Project Description

The work includes construction of the floating caisson recess slot fillers and incidental related work. Steel frames will be constructed and then filled with concrete.

1.4.2 Location

The work is located at the Wilson L&D with option to award work at Nickajack L&D and Wheeler L&D, as indicated in Section 1.6. The exact

SECTION 01 11 00 Page 2 location where fabricated items will be delivered to will be directed by the Lock Master.

1.5 INSPECTION AND ACCEPTANCE OF WORK

1.5.1 GENERAL

Not withstanding other provisions of this contract, all materials and work to be performed under this contract shall be inspected and accepted by the Contracting Officer or his authorized representative(s). The Contracting Officer or his authorized representative shall be the individual(s) solely authorized to reject materials, disapprove or approve any work in progress, or order or direct any revision or change to the plans and specifications as presently shown and stated.

1.5.2 ACCESS TO WORK

The Contractor shall provide safe access to the fabrication facility and any other areas where work on this contract is performed to permit inspection by the Government.

1.6 DELIVERY OF FABRICAITONS

Fabricated components for Nickajack Main shall be delivered to 3490 TVA Rd.

Jasper, TN 37347.

Fabricated components for Wilson Main shall be delivered to The Tennessee River Operations Center (TROC), 704 S Wilson Dam Road, Florence, AL 35630-2010.

Fabricated components for Wheeler Main shall be delivered to the 100 Highway 101, Rogersville, AL 35652-9348.

All other fabrications shall be delivered to the Tennessee River Operations Center (TROC), 704 S Wilson Dam Road, Florence, AL.

The Government will inspect, accept (or reject), and unload all deliveries. Government personnel and equipment will be used in all unloading and storing operations. All fabrications shall be delivered by truck to allow unloading by the Government.

The contractor is required to submit a Delivery/Shipping Plan for approval by the Contracting Officer. The plan shall describe in detail the proposed methods of delivery of the fabricated items. The plan shall address equipment, machinery and site limitations identified in the specifications and discussed at a pre-delivery meeting between the Contractor and the Contracting Officer. Additional Delivery/Shipping Plan requirements are described in Section 05 50 14 STRUCTURAL METAL FABRICATIONS. The plan shall be submitted at least 60 calendar days prior to proposed delivery of any item. The plan shall include, but not be limited to the following:

a. Type and size of truck and/or trailer to be used for delivery.

b. Location and description of intermediate assembly or handling areas (if any) between the fabrication location and the delivery location.

c. Cranes and other lifting and positioning equipment that will be required.

SECTION 01 11 00 Page 3

d. Packaging of components.

e. Blocking.

1.7 NON-DISCLOSURE OF GOVERNEMENT INFORMATION

Neither the Contractor, nor Contractor personnel, shall divulge or release data or information developed or obtained under performance of this work statement, except to authorized Government personnel or upon written approval of the Contracting Officer. The Contractor shall not use, disclose, or reproduce proprietary data which bears a restrictive legend, other than as specified in this work statement.

Neither the Contractor nor the Contractor's employees shall disclose or cause to be disseminated, any information concerning the operations of the activity which could result in, or increase the likelihood of, the possibility of a breach of the activities, security or interrupt the continuity of its operation.

All inquiries received by the Contractor for information concerning work performed under this contract shall be referred to the Government for evaluation under the Freedom of Information Act of 1975, Public Law 93-502, 5 U.S.C., Section 552. The determination of whether records will be released will remain with the Government. The Contractor shall assist the COR in compiling information or records for submission upon request by the Government.

The Contractor shall not release any information (including photographs, files, public announcements, statements, denials, or confirmations) on any portion of the subject matter of this contract or any phase of any program hereunder without the prior written approval of the COR. All documentation showing individuals, names or other personal information will be controlled and protected. The provisions of the Privacy Act of 1974, Public Law 93-579, 5 U.S.C., Section 552a, shall apply.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

SECTION 01 11 00 Page 4

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

1.1.1 Slot Fillers - Nickajack Lock & Dam

1.1.1.1 Payment

1.1.1.2 Unit of Measure

1.1.2 Slot Fillers - Wheeler Lock & Dam

1.1.2.1 Payment

1.1.2.2 Unit of Measure

1.1.3 Slot Fillers - Wilson Lock & Dam

1.1.3.1 Payment

1.1.3.2 Unit of Measure

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 22 00 Page 1

SECTION 01 22 00

PRICE AND PAYMENT PROCEDURES

PART 1 GENERAL

1.1 SINGLE JOB PAYMENT ITEMS

Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.

1.1.1 Slot Fillers - Nickajack Lock & Dam

1.1.1.1 Payment

Payment will be made for costs associated with fabricating and delivering embedded metals and related appurtenances will be made at the contract price bid per Job for the following bid items:

1.1.1.2 Unit of Measure

Unit of measure: job.

Nickajack Slot Fillers

These prices will include consideration for all materials, concrete, embedded metals, painting, labor, delivery, and equipment; and all other related appurtenances; as required in the contract drawings and Section 05 50 14 STRUCTURAL METAL FABRICATIONS. This price includes consideration for all required paint as specified in Section 09 97 02 PAINTING:

HYDRAULIC STRUCTURES.

1.1.2 Slot Fillers - Wheeler Lock & Dam

1.1.2.1 Payment

Payment will be made for costs associated with fabricating and delivering embedded metals and related appurtenances will be made at the contract price bid per Job for the following bid items:

1.1.2.2 Unit of Measure

Unit of measure: job.

Wheeler Slot Fillers

SECTION 01 22 00 Page 2

These prices will include consideration for all materials, concrete, embedded metals, painting, labor, delivery, and equipment; and all other related appurtenances; as required in the contract drawings and Section 05 50 14 STRUCTURAL METAL FABRICATIONS. This price includes consideration for all required paint as specified in Section 09 97 02 PAINTING:

HYDRAULIC STRUCTURES.

1.1.3 Slot Fillers - Wilson Lock & Dam

1.1.3.1 Payment

Payment will be made for costs associated with fabricating and delivering embedded metals and related appurtenances will be made at the contract price bid per Job for the following bid items:

1.1.3.2 Unit of Measure

Unit of measure: job.

Wilson Slot Fillers

These prices will include consideration for all materials, concrete, embedded metals, painting, labor, delivery, and equipment; and all other related appurtenances; as required in the contract drawings and Section 05 50 14 STRUCTURAL METAL FABRICATIONS. This price includes consideration for all required paint as specified in Section 09 97 02 PAINTING:

HYDRAULIC STRUCTURES.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 22 00 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES - SUPPLY

PART 1 GENERAL

1.1 SCOPE

1.2 SUMMARY

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

1.3.2 Approving Authority

1.3.3 Work

1.4 SUBMITTALS

1.5 SUBMITTAL CLASSIFICATION

1.5.1 Government Approved (G)

1.5.2 For Information Only

1.6 PREPARATION

1.6.1 Transmittal Form

1.6.2 Terms and Conditions

1.6.3 Electronic File Format

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of Copies SD-02 Shop Drawings

1.7.1.1 Number of Copies of SD-03 Product Data and SD-08

Manufacturer's Instructions

1.7.1.2 Number of Copies SD-05 Design Data and SD-07 Certificates

1.7.1.3 Number of Copies SD-06 Test Reports and SD-09

Manufacturer's Field Reports

1.7.1.4 Number of Copies of SD-10 Operation and Maintenance Data

1.8 INFORMATION ONLY SUBMITTALS

1.9 SUBMITTAL REGISTER

1.9.1 Use of Submittal Register

1.9.2 Contractor Use of Submittal Register

1.9.3 Approving Authority Use of Submittal Register

1.9.4 Copies Delivered to the Government

1.10 VARIATIONS

1.10.1 Considering Variations

1.10.2 Proposing Variations

1.10.3 Warranting that Variations are Compatible

1.10.4 Review Schedule Extension

1.11 SCHEDULING

1.11.1 Government Reviewed Design

1.12 GOVERNMENT APPROVING AUTHORITY

1.12.1 Review Notations

1.13 DISAPPROVED OR REJECTED SUBMITTALS

1.14 APPROVED/ACCEPTED SUBMITTALS

1.15 APPROVED SAMPLES

1.16 WITHHOLDING OF PAYMENT

PART 2 PRODUCTS

SECTION 01 33 00 Page 1

PART 3 EXECUTION

ATTACHMENTS:

Appendix A - Submittal Register

Appendix B ENG Form 4025-R

SECTION 01 33 00 Page 2

SECTION 01 33 00

SUBMITTAL PROCEDURES - SUPPLY

PART 1 GENERAL

1.1 SCOPE

The scope of this Section covers the submittal procedures required by this contract. All required submittals shall be provided in both hard copy and electronic format (PDF). Electronic submittals shall be sent to the Contracting Officer or designated representative via E-Mail to the extent possible.

1.2 SUMMARY

The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections.

Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.

Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.

Contractor's Quality Control (CQC) System Manager and the Designer of Record, if applicable, to check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited

to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications;

warranties; and other such required submittals.

Submittals requiring Government approval are to be scheduled and made prior to the acquisition of the material or equipment covered thereby. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Material Safety Data Sheets (MSDS) and in compliance with existing laws and regulations.

A submittal register showing items of equipment and materials for when submittals are required by the specifications is provided as "Appendix A - Submittal Register".

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

Submittals requirements are specified in the technical sections.

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Preconstruction Submittals

SECTION 01 33 00 Page 3

Submittals which are required prior to start of construction (work).or the start of the next major phase of the construction on a multi-phase contract, includes schedules, tabular list of data, or tabular list including location, features, or other pertinent information regarding products, materials, equipment, or components to be used in the work.

Certificates of insurance

Surety bonds

List of proposed Subcontractors

List of proposed products

Construction progress schedule

Submittal register

Schedule of prices

Work plan

Quality Control(QC) plan

SD-02 Shop Drawings

Drawings, diagrams and schedules specifically prepared to illustrate some portion of the work.

Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance and other characteristics of materials, systems or equipment for some portion of the work.

Samples of warranty language when the contract requires extended product warranties.

SD-04 Samples

Fabricated or unfabricated physical examples of materials, equipment or workmanship that illustrate functional and aesthetic characteristics of a material or product and establish standards by which the work can be judged.

Color samples from the manufacturer's standard line (or custom color samples if specified) to be used in selecting or approving colors for the project.

Field samples and mock-ups constructed on the project site establish standards by which the ensuring work can be judged. Includes

SECTION 01 33 00 Page 4 assemblies or portions of assemblies which are to be incorporated into the project and those which will be removed at conclusion of the work.

SD-06 Test Reports

Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.

Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

Investigation reports.

Daily logs and checklists.

Final acceptance test and operational test procedure.

SD-07 Certificates

Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.

Document required of Contractor, or of a manufacturer, supplier, installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.

Confined space entry permits.

1.3.2 Approving Authority

Office or designated person authorized to approve submittal.

1.3.3 Work

As used in this section, on- and off-site construction required by contract documents, including labor necessary to produce submittals, except those SD-01 Pre-Construction Submittals noted above, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction.

1.4 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in

SECTION 01 33 00 Page 5 accordance with this section.

SD-01 Preconstruction Submittals

Submittal Register; G

1.5 SUBMITTAL CLASSIFICATION

Submittals are classified as follows:

1.5.1 Government Approved (G)

Government approval is required for extensions of design, critical materials, deviations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Contracting Officer.

Government approval is required for any deviations from the Solicitation or Accepted Proposal and other items as designated by the Contracting Officer. Within the terms of the Contract Clause SPECIFICATIONS AND DRAWINGS FOR CONSTRUCTION, they are considered to be "shop drawings."

1.5.2 For Information Only

Submittals not requiring Government approval will be for information only.

For Design-build construction all submittals not requiring Designer of Record or Government approval will be for information only. They are not considered to be "shop drawings" within the terms of the Contract Clause referred to above.

1.6 PREPARATION

1.6.1 Transmittal Form

Use the attached sample transmittal form in Appendix B ENG Form 4025-R for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted. Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.

1.6.2 Terms and Conditions

Data contained on these electronic files must not be used for any purpose other than as a convenience in the preparation of construction data for the referenced project. Any other use or reuse shall be at the sole risk of the Contractor and without liability or legal exposure to the Government.

The Contractor must make no claim and waives to the fullest extent permitted by law, any claim or cause of action of any nature against the Government, its agents or sub consultants that may arise out of or in connection with the use of these electronic files. The Contractor must, to the fullest extent permitted by law, indemnify and hold the Government harmless against all damages, liabilities or costs, including reasonable attorney's fees and defense costs, arising out of or resulting from the use of these electronic files.

These electronic Source Drawing files are not construction documents.

Differences may exist between the Source Drawing files and the

SECTION 01 33 00 Page 6 corresponding construction documents. The Government makes no representation regarding the accuracy or completeness of the electronic Source Drawing files, nor does it make representation to the compatibility of these files with the Contractor hardware or software. In the event that a conflict arises between the signed and sealed construction documents prepared by the Government and the furnished Source Drawing files, the signed and sealed construction documents govern. The Contractor is responsible for determining if any conflict exists. Use of these Source Drawing files does not relieve the Contractor of duty to fully comply with the contract documents, including and without limitation, the need to check, confirm and coordinate the work of all contractors for the project.

If the Contractor uses, duplicates or modifies these electronic Source Drawing files for use in producing construction data related to this contract, remove all previous indicia of ownership (seals, logos, signatures, initials and dates).

1.6.3 Electronic File Format

Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. Compile the submittal file as a single, complete document, to include the Transmittal Form described within. Name the electronic submittal file specifically according to its contents, coordinate the file naming convention with the Contracting Officer. Electronic files must be of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer. Generate PDF files from original documents with bookmarks so that the text included in the PDF file is both searchable and can be copied. If documents are scanned, Optical Character Resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, the electronic file must include a valid electronic signature, or scan of a signature.

Email electronic submittal documents fewer than 10MB to an email address as directed by the Contracting Officer. Provide electronic documents over 10MB on an optical disc, or through an electronic file sharing system such as the AMRDEC SAFE Web Application located at the following website:

https://safe.amrdec.army.mil/safe/.

Provide hard copies of submittals when requested by the Contracting Officer. Additional hard copies of any submittal may be requested at the discretion of the Contracting Officer, at no additional cost to the Government.

1.7 QUANTITY OF SUBMITTALS

1.7.1 Number of Copies SD-02 Shop Drawings

a. Submit one electric (PDF Format), and two sets of hard copites of submittals of shop drawings requiring review and approval only by the QC organization and one electronic (PDF format) and two hard copies of shop drawings requiring review and approval by Contracting Officer.

1.7.1.1 Number of Copies of SD-03 Product Data and SD-08 Manufacturer's Instructions

Submit in compliance with quantity requirements specified for shop drawings.

SECTION 01 33 00 Page 7

1.7.1.2 Number of Copies SD-05 Design Data and SD-07 Certificates

Submit in compliance with quantity requirements specified for shop drawings.

1.7.1.3 Number of Copies SD-06 Test Reports and SD-09 Manufacturer's Field Reports

Submit in compliance with quantity and quality requirements specified for shop drawings other than field test results that will be submitted with QC reports.

1.7.1.4 Number of Copies of SD-10 Operation and Maintenance Data

Submit one electronic (PDF format) and two hard copies of O&M Data to the Contracting Officer for review and approval.

Number of Copies of SD-01 Pre-Fabrication Submittals and SD-11 Closeout Submittals

Unless otherwise specified, submit one electronic (PDF format) and two hard sets of administrative submittals.

1.8 INFORMATION ONLY SUBMITTALS

Normally submittals for information only will not be returned. Approval of the Contracting Officer is not required on information only submittals.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work;

and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe. For design-build construction the Government will retain 1 copy of information only submittals.

1.9 SUBMITTAL REGISTER

Prepare and maintain submittal register, as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and

(i) as approved. A submittal register showing items of equipment and materials for which submittals are required by the specifications is provided as an attachment. This list may not be all inclusive and additional submittals may be required. The Government will provide the initial submittal register with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists specification section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each specification section.

Column (e): Lists one principal paragraph in specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

SECTION 01 33 00 Page 8

Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

The Designer of Record develops a complete list of submittals during design and identify required submittals in the specifications, and use the list to prepare the Submittal Register. The list may not be all inclusive and additional submittals may be required by other parts of the contract.

Complete the submittal register and submit it to the Contracting Officer for approval within 30 calendar days after Notice to Proceed. The approved submittal register will serve as a scheduling document for submittals and will be used to control submittal actions throughout the contract period.

Coordinate the submit dates and need dates with dates in the Contractor prepared progress schedule. Submit monthly or until all submittals have been satisfactorily completed, updates to the submittal register showing the Contractor action codes and actual dates with Government action codes.

Revise the submittal register when the progress schedule is revised and submit both for approval.

1.9.1 Use of Submittal Register

Submit submittal register. Submit with QC plan and project schedule.

Verify that all submittals required for project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:

Column (g) Contractor Submit Date: Scheduled date for approving authority to receive submittals.

Column (h) Contractor Approval Date: Date Contractor needs approval of submittal.

Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.

1.9.2 Contractor Use of Submittal Register

Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor with each submittal throughout contract.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.

Column (l) List date of submittal transmission.

Column (q) List date approval received.

1.9.3 Approving Authority Use of Submittal Register

Update the following fields in the Government-furnished submittal register program or equivalent fields in program utilized by Contractor.

Column (b) Transmittal Number: Contractor assigned list of consecutive numbers.

SECTION 01 33 00 Page 9

Column (l) List date of submittal receipt.

Column (m) through (p) List Date related to review actions.

Column (q) List date returned to Contractor.

1.9.4 Copies Delivered to the Government

Deliver one copy of submittal register updated by Contractor to Government with each invoice request.

1.10 VARIATIONS

Variations from contract requirements require both Designer of Record (DOR) and Government approval pursuant to contract Clause FAR 52.236-21 and will be considered where advantageous to Government.

1.10.1 Considering Variations

Discussion with Contracting Officer prior to submission, after consulting with the DOR, will help ensure functional and quality requirements are met and minimize rejections and re-submittals. When contemplating a variation which results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).

Specifically point out variations from contract requirements in transmittal letters. Failure to point out deviations may result in the Government requiring rejection and removal of such work at no additional cost to the Government.

1.10.2 Proposing Variations

When proposing variation, deliver written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government, including the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.

Clearly mark the proposed variation in all documentation.

Check the column "variation" of ENG Form 4025 for submittals which include proposed deviations requested by the Contractor. Set forth in writing the reason for any deviations and annotate such deviations on the submittal.

The Government reserves the right to rescind inadvertent approval of submittals containing unnoted deviations.

1.10.3 Warranting that Variations are Compatible

When delivering a variation for approval, Contractor, including its Designer(s) of Record, warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.

1.10.4 Review Schedule Extension

In addition to normal submittal review period, a period of 10 business days will be allowed for consideration by the Government of submittals with variations.

SECTION 01 33 00 Page 10

1.11 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Include certifications to be submitted with the pertinent drawings at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the contract documents will be listed on the register. If a submittal is called for but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but which have been omitted from the register or marked "N/A."

c. Re-submit register and annotate monthly by the Contractor with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register."

1.11.1 Government Reviewed Design

The Government will review design submittals for conformance with the technical requirements of the solicitation. Government review is required for deviation from the completed design. Review will be only for conformance with the contract requirements. Included are only those construction submittals for which the Designer of Record design documents do not include enough detail to ascertain contract compliance. The Government may, but is not required, to review extensions of design such as structural steel or reinforcement shop drawings.

1.12 GOVERNMENT APPROVING AUTHORITY

When approving authority is Contracting Officer, the Government will:

a. Note date on which submittal was received.

b. Review submittals for approval within scheduling period specified and only for conformance with project design concepts and compliance with contract documents.

c. Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with markings appropriate for action indicated.

Upon completion of review of submittals requiring Government approval, stamp and date submittals. One copy of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor. If the Government performs a conformance review of other Designer of Record approved submittals, the submittals will be so

SECTION 01 33 00 Page 11 identified and returned, as described above.

1.12.1 Review Notations

Contracting Officer review will be completed within 30 calendar days after date of submission. Submittals will be returned to the Contractor with the following notations:

a. Submittals marked "approved" or "accepted" authorize the Contractor to proceed with the work covered.

b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize the Contractor to proceed with the work covered provided he takes no exception to the corrections.

c. Submittals marked "not approved" or "disapproved," or "revise and resubmit," indicate noncompliance with the contract requirements or design concept, or that submittal is incomplete. Resubmit with appropriate changes. No work shall proceed for this item until resubmittal is approved.

d. Submittals marked "not reviewed" will indicate submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.

1.13 DISAPPROVED OR REJECTED SUBMITTALS

Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications; notice as required under the FAR 52.212-4(C) clause entitled CHANGES, is to be given to the Contracting Officer. Contractor is responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

If changes are necessary to submittals, make such revisions and submission of the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.14 APPROVED/ACCEPTED SUBMITTALS

The Contracting Officer's approval or acceptance of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing and other information are satisfactory. Design, general method of construction, materials, detailing and other information appear to meet the Solicitation and Accepted Proposal.

Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this contract is responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work design, dimensions, all design extensions, such as the design of adequate connections and details, SECTION 01 33 00 Page 12 etc., and the satisfactory construction of all work.

After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.

1.15 APPROVED SAMPLES

Approval of a sample is only for the characteristics or use named in such approval and is not be construed to change or modify any contract requirements. Before submitting samples, the Contractor to assure that the materials or equipment will be available in quantities required in the project. No change or substitution will be permitted after a sample has been approved.

Match the approved samples for materials and equipment incorporated in the work. If requested, approved samples, including those which may be damaged in testing, will be returned to the Contractor, at his expense, upon completion of the contract. Samples not approved will also be returned to the Contractor at its expense, if so requested.

Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this contract, any further samples of the same brand or make of that material. Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

Samples of various materials or equipment delivered on the site or in place may be taken by the Contracting Officer for testing. Samples failing to meet contract requirements will automatically void previous approvals.

Contractor to replace such materials or equipment to meet contract requirements.

Approval of the Contractor's samples by the Contracting Officer does not relieve the Contractor of his responsibilities under the contract.

1.16 WITHHOLDING OF PAYMENT

Payment for materials incorporated in the work will not be made if required approvals have not been obtained. No payment for materials incorporated in the work will be made if all required Designer of Record or required Government approvals have not been obtained. No payment will be made for any materials incorporated into the work for any conformance review submittals or information only submittals found to contain errors or deviations from the Solicitation or Accepted Proposal.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 33 00 Page 13

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

PART 1 GENERAL

1.1 REFERENCES

1.2 ORDERING INFORMATION

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 42 00 Page 1

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

PART 1 GENERAL

1.1 REFERENCES

Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.

1.2 ORDERING INFORMATION

The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.

AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS

(AASHTO)

444 North Capital Street, NW, Suite 249 Washington, DC 20001 Ph: 202-624-5800 Fax: 202-624-5806 E-Mail: info@aashto.org Internet: http://www.aashto.org

AMERICAN WELDING SOCIETY (AWS)

13301 NW 47 Ave Miami, FL 33054

Ph: 888-WELDING, 305-824-1177, 305-826-6192 Fax: 305-826-6195 E-mail: customer.service@awspubs.com Internet: http://www.aws.org

ASME INTERNATIONAL (ASME)

Two Park Avenue, M/S 10E New York, NY 10016-5990 Ph: 800-843-2763 Fax: 973-882-1717 E-mail: customercare@asme.org Internet: http://www.asme.org

ASTM INTERNATIONAL (ASTM)

100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 877-909-2786 Internet: http://www.astm.org

SECTION 01 42 00 Page 2

SOCIETY FOR PROTECTIVE COATINGS (SSPC)

40 24th Street, 6th Floor Pittsburgh, PA 15222 Ph: 412-281-2331 Fax: 412-281-9992 E-mail: info@sspc.org Internet: http://www.sspc.org

U.S. ARMY CORPS OF ENGINEERS (USACE)

CRD-C DOCUMENTS available on Internet:

http://www.wbdg.org/ccb/browse_cat.php?c=68 Order Other Documents from:

USACE Publications Depot Attn: CEHEC-IM-PD 2803 52nd Avenue Hyattsville, MD 20781-1102 Ph: 301-394-0081 Fax: 301-394-0084 E-mail: pubs-army@usace.army.mil Internet: http://www.publications.usace.army.mil/ or http://www.hnc.usace.army.mil/Missions/Engineering/TECHINFO.aspx

U.S. GENERAL SERVICES ADMINISTRATION (GSA)

General Services Administration 1275 First St. NE Washington, DC 20417 Ph: 202-501-1231 Internet: http://www.gsaelibrary.gsa.gov/ElibMain/home.do Obtain documents from:

Acquisition Streamlining and Standardization Information System

(ASSIST)

Internet: https://assist.dla.mil/online/start/; account registration required

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Not used

SECTION 01 42 00 Page 3

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 95 00

FORMS AND ATTACHMENTS

PART 1 GENERAL

1.1 FORMS AND ATTACHMENTS

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

ATTACHMENTS:

1. ENG Form 4025 Transmittal Form

2. Submittal Register

SECTION 01 95 00 Page 1

SECTION 01 95 00

FORMS AND ATTACHMENTS

PART 1 GENERAL

1.1 FORMS AND ATTACHMENTS

Listed below, and attached at the end of this section, are forms and attachments referred to in other parts of the set of technical specifications.

1. ENG Form 4025 Transmittal Form. See Section 01 33 00 SUBMITTAL

PROCEDURES.

2. Submittal Register. See Section 01 33 00 SUBMITTAL PROCEDURES.

PART 2 PRODUCTS (Not Used)

PART 3 EXECUTION (Not Used)

SECTION 01…