Abstract of Offers_Conneaut Dredging.pdf

PDF 278 KB Posted

Attached to
FY25 Maintenance Dredge - Conneaut Harbor, OH
Solicitation number
W912P425BA015
Issued by

About this file

This document is an Abstract of Offers for a Conneaut Dredging construction project issued by the US Army Engineer District in Buffalo, NY. The solicitation (W912P425BA015) covers base work and optional dredging services, with Walsh Service Solutions, LLC as the primary offeror. The base work includes mobilization/demobilization and dredging 50,000 cubic yards of material at a government-furnished upland placement site, with a base total estimated at $2,996,107.48. An optional additional 20,000 cubic yards of dredging is priced at $879,400.00, bringing the total base and options to $3,875,507.48. The government estimate and Walsh Service Solutions' bid are slightly different, with Walsh's offer being approximately $115,440.92 higher than the government estimate. The solicitation requires a bid bond of 20% of the bid and was opened on 29-Apr-25, with the project date issued on 26-Mar-25.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Issuing Office

Item Est. Unit Estimated Unit Estimated Unit Estimated Unit Estimated Unit Estimated Unit Estimated No. Description of Offered Item Quantity Unit Price Amount Price Amout Price Amout Price Amout Price Amout Price Amout

01 BASE WORK

1 MOBILIZATION / DEMOBILIZATION 1 JA 223,607.48$ $223,607.48 $231,848.40 $231,848.40 $0.00 $0.00

Dredging with placement in Government furnished Upland Placement Site 50000 CY 55.45$ $2,772,500.00 55.33$ $2,766,500.00 $0.00 $0.00

TOTAL BASE $2,996,107.48 $2,998,348.40 $0.00 $0.00

A OPTIONS

Dredging with placement in Governmentfurnished Upland Placement Site 20000 CY 43.97$ $879,400.00 $49.63 $992,600.00 $0.00 $0.00

TOTAL OPTIONS $879,400.00 $992,600.00 $0.00 $0.00

BASE + OPTIONS TOTAL $3,875,507.48 $3,990,948.40 $0.00 $0.00 $0.00 $0.00

Date Received 29-Apr-25 SAM Unique Identity ID: MLCNYDBEJK23

Amendment(s) Acknolwedged ? NA Bid Bond Provided ? Yes

W912P4 US Army Engineer District, Buffalo 478 Main Street Buffalo, NY 14202

Date Signed

W912P425BA015 I CERTIFY that I have opened, read, and recorded on this abstract all offers received in response to this solicitation.

ABSTRACT OF OFFERS - CONSTRUCTION

NO. 1 NO. 2 NO. 3

Date Issued: Date Opened

Solicitation Number 26-Mar-25 29-Apr-25

O F F E R S

Project Title GOVERNMENT ESTIMATE OFFEROR OFFEROR OFFEROR

Bid bond - 20% of bid

Conneaut Dredging A. HIRED LABOR Walsh Service Solutions, LLC

NO. 4

XX

C. REASONABLE CONTRACT

(including profit)

B. REASONABLE CONTRACT BID SECURITY (type & amount) BID SECURITY (type & amount) BID SECURITY (type & amount) (without profit) Bid bond - 20% of Bid Bid bond - 20% of bid

BID SECURITY (type & amount) Bid bond - 20% of bid

NO. 5

OFFEROR

BID SECURITY (type & amount) Bid bond - 20% of bid

OFFEROR

2025-04-30T09:22:47-0400
ERNEST.JEFFREY.G.1016090294