144489-FY25 Conneaut Dredge Plans and Specs - Certified Final RTA (11March25).pdf
PDF 15 MB Posted
- Attached to
- FY25 Maintenance Dredge - Conneaut Harbor, OH
- Solicitation number
- W912P425BA015
About this file
This document is a Certified Final Request for Technical Assistance (RTA) for the FY25 Conneaut Harbor Dredging project located in Conneaut, Ohio. The solicitation covers maintenance dredging of federal navigation channels in Conneaut Harbor, with an estimated total of approximately 100,000 cubic yards of sediment to be dredged annually over 2024-2026 (300,000 cubic yards total). The project involves removing sediment from the Outer Harbor Channel, Inner Harbor Channel, and Municipal Access Channel to maintain authorized navigation depths, with an allowance for up to one additional foot of dredging tolerance.
The procurement will be a 100% Small Business Set-Aside competitive procurement for a Firm-Fixed-Price contract, with an estimated project value between $1,000,000 and $5,000,000. Coarse-grain material from the Municipal Access Channel may be placed in an authorized nearshore placement area approximately 1,500 feet east of the Conneaut Harbor East Breakwater Extension. The dredging is scheduled to occur within an environmental window between July 1 and September 14, with specific restrictions on dredging depths near underwater structures and requirements for sediment placement and handling. Contractors will need to be registered in the System for Award Management (SAM) database and comply with various environmental and safety regulations outlined in the detailed specification sections.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Abstract of Offers_Conneaut Dredging.pdf | ||
| WD IL20250018_published 03 JAN 2025.pdf | ||
| Solicitation - W912P425BA015.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
CERTIFIED FINAL - RTA
W912P425BA015
CONNEAUT, OHIO
CONNEAUT HARBOR
DREDGING
FY25
PLANS AND SPECIFICATIONS
11 MARCH 2025
FY25 CONNEAUT HARBOR DREDGING CERTIFIED FINAL - RTA
PROJECT TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
01 20 00 PRICE AND PAYMENT PROCEDURES
01 32 16 SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
01 33 00 SUBMITTAL PROCEDURES
01 35 13 SPECIAL PROJECT PROCEDURES
01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 QUALITY CONTROL
01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)
01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
35 20 23 DREDGING
35 20 23.13 NATIONAL DREDGING QUALITY MANAGEMENT PROGRAM - SCOW
MONITORING AND ULLAGE PROFILE
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 1000 03/11/25
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
1.2 CONTRACT COST BREAKDOWN
1.3 CONTRACT MODIFICATIONS
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 Submission of Invoices
1.4.2 Final Invoice
1.5 SINGLE JOB PAYMENT ITEMS
1.5.1 Mobilization and Demobilization
1.5.1.1 Payment
1.5.1.2 Unit of Measure
1.6 UNIT PRICE PAYMENT ITEMS
1.6.1 Dredging
1.6.1.1 Payment
1.6.1.2 Quantity Determination
1.6.1.3 Unit of Measure
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section Table of Contents --
SECTION 01 20 00 Page 1001
SECTION 01 20 00
PRICE AND PAYMENT PROCEDURES
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EP 1110-1-8 (2021) Engineering and Design -- Construction Equipment Ownership and Operating Expense Schedule
EM 1110-2-1003 (2013) Engineering and Design:
HYDROGRAPHIC SURVEYING
1.2 CONTRACT COST BREAKDOWN
The Contractor must furnish within 30 days after the date of Notice to Proceed, and prior to the submission of its first partial payment estimate, a breakdown of its single job pay item or items which will be reviewed by the Contracting Officer as to propriety of distribution of the total cost to the various accounts. Any unbalanced items as between early and late payment items or other discrepancies will be revised by the Contracting Officer to agree with a reasonable cost of the work included in the various items. This Contract cost breakdown will then be utilized as the basis for progress payments to the Contractor.
1.3 CONTRACT MODIFICATIONS
In conjunction with the Contract Clause DFARS 252.236-7000 Modification Proposals-Price Breakdown, and where actual ownership and operating costs of construction equipment cannot be determined from Contractor accounting records, base equipment use rates upon the applicable provisions of the
EP 1110-1-8 .
1.4 CONTRACTOR'S INVOICE AND CONTRACT PERFORMANCE STATEMENT
1.4.1 Submission of Invoices
a. Monthly invoices and supporting forms for work performed through the anniversary award date of the Contract must be submitted to the Contracting Officer within 5 calendar days of the date of invoice. For example, if Contract award date is the 7th of the month, the date of each monthly invoice must be the 7th and the invoice must be submitted by the 12th of the month.
1.4.2 Final Invoice
a. A final invoice must be accompanied by the certification required by DFARS 252.247.7023 Transportation of Supplies by Sea, and the Contractor's Final Release. If the Contractor is incorporated, the
SECTION 01 20 00 Page 1002
Final Release must contain the corporate seal. An officer of the corporation must sign and the corporate secretary must certify the Final Release.
b. The original Contractor's Final Release Form and required certification of Transportation of Supplies by Sea must be provided directly to the respective Contracting Officer prior to submission of the final invoice.
c. Final invoices not accompanied by the Contractor's Final Release and required certification of Transportation of Supplies by Sea will be considered incomplete and will be returned to the Contractor.
1.5 SINGLE JOB PAYMENT ITEMS
Payment items for the work of this contract for which contract job payments will be made are listed in the BIDDING SCHEDULE and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job or unit price payment item, are included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for which separate payment is not otherwise provided.
1.5.1 Mobilization and Demobilization
1.5.1.1 Payment
Payment will be made for costs associated with mobilization and demobilization.
1.5.1.2 Unit of Measure
Unit of measure: job (JA).
1.6 UNIT PRICE PAYMENT ITEMS
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the BIDDING SCHEDULE and described below. The unit price and payment made for each item listed constitutes full compensation for furnishing all plant, labor, materials, and equipment, and performing any associated Contractor quality control, environmental protection, safety requirements, tests and reports, and for performing all work required for each of the unit price items.
1.6.1 Dredging
1.6.1.1 Payment
(a) Payment will be made for all costs associated with the dredging operations. The Contract Unit Price per Cubic Yard of Dredging includes the cost of removal, conveyance and placement of all materials, including Other Removed Materials, within the areas shown on the drawings, and specified herein. The contract unit price also includes all sediment placement costs or fees that will be charged by the sediment placement facility operator. Contact:
SECTION 01 20 00 Page 1003
Nicholas Sanford City Manager City of Conneaut 294 Main Street, Conneaut Ohio 44030 Phone: (440) 593-7401 e-mail: manager@conneautoh.org
(b) Do not leave the project site until the full quantity of material as awareded has been dredged from the limits established by the Contracting Officer unless otherwise approved by the Contracting Officer.
1.6.1.2 Quantity Determination
a. In-place payment quantities will be measured and computed by the Government using channel limits, or other dredging limits established by the Contracting Officer, and stationing as computed by the Government.
b. The material to be paid for will be measured by computing the in-place quantity (cubic yards) available within the maximum pay prism,(as stated in paragraph "Specific Areas and Periods" of Section 35 20 23 "MAINTENANCE DREDGING") as determined from the "before" soundings, less the quantity remaining within the maximum pay prism as determined from the "after" soundings, less any deductions that may be required for misplaced material, described in paragraph "Misplaced Materials" of Section 35 20 23
"MAINTENANCE DREDGING".
c. The "before" and "after" dredging surveys and associated quantity computations will be performed to reflect the total quantity of sediment dredged.
d. No payment will be made for material dredged in excess of the total quantity in each dredging area and contract line item, as specified in the contract and/or as established by the Contracting Officer pursuant to Section 35 20 23 DREDGING paragraph entitled "Specific Areas and Periods" and "FINAL EXAMINATION AND ACCEPTANCE."
e. Surveys:
(1) Before and After dredge surveys will be performed by the Government for purposes of acceptance and determination of quantities dredged. The Government will conduct surveys in accordance with EM 1110-2-1003 , "Engineering and Design: HYDROGRAPHIC SURVEYING", using one of the following methods: (1) multibeam, (2) single beam, or
(3) lead line, whichever is deemed appropriate by the Government for the harbor/channel being dredged.
(2) The surveying method utilized will be determined solely by the Government and is entirely at it's discretion. Upon request, the Contractor will be advised of the surveying method to be used prior to the commencement of dredging.
(3) The "after" sounding survey will be made within 14 calendar days after each acceptance section has been completed.
f. The method used to calculate quantities will be software from HYPACK, Inc., either the standard HYPACK method or the TIN method as determined prior to taking the "before" soundings.
g. Acceptance Sections - Length and notifications (as applicable):
SECTION 01 20 00 Page 1004
(1) Unless specifically designated in the Section 01 35 13 "SPECIAL PROJECT REQUIREMENTS", paragraph "Acceptance Section Lengths", acceptance section lengths for hydraulic dredges with a cutterhead and mechanical dredges will be a minimum of 2,500 feet. Acceptance lengths for hopper dredges will be a minimum of 5,000 feet.
(2) Acceptance section lengths will be determined by the Contracting Officer prior to the commencement of dredging.
(3) Examination for acceptance will not be performed until all dredging required under this contract, within 500 feet of the acceptance section, has been completed, or to a point where, in the judgment of the Contracting Officer, further dredging in the contract area will not cause shoaling or damage to the acceptance section.
(4) Notify the Contracting Officer 7 business days prior to completion of each specified acceptance section to allow adequate time for the scheduling of a survey crew to perform examination soundings. Written notification may be required at the discretion of the Contracting Officer. If completion of the acceptance section is not proceeding as anticipated, notify the Contracting Officer at least 2 business days prior to the anticipated completion date so that the Government survey crew is not dispatched to perform the examination soundings and so that a revised date can be established.
h. It is the responsibility of the Contractor to compute and verify dredge limits and quantities before the commencement of dredging. The Contractor will be furnished drawings depicting both the "before" and "after" dredging soundings along with computer printouts of the soundings, if done by an electronic measuring system, or copies of the original field notes if done by conventional methods.
i. Nothing in this paragraph will be construed as prohibiting the removal of excepted material by special means at the prices agreed and approved in accordance with applicable provisions of the contract.
1.6.1.3 Unit of Measure
Unit of measure: cubic yard (CY).
PART 2 PRODUCTS - NOT USED
PART 3 EXECUTION - NOT USED
-- End of Section --
SECTION 01 20 00 Page 1005
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 ACCEPTANCE
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
1.4 UPDATED SCHEDULES
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 32 16 Page 1006
SECTION 01 32 16
SMALL PROJECT CONSTRUCTION PROGRESS SCHEDULES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation.
Submit the following in accordance with Section 01 33 00 SUBMITTAL
PROCEDURES:
SD-01 Preconstruction Submittals
Construction Schedule; G, AO
1.2 ACCEPTANCE
a. Prior to the start of work, prepare and submit to the Contracting Officer for acceptance a construction schedule in the form of a Bar Chart Schedule.
b. The acceptance of a Baseline Construction Schedule is a condition precedent to:
(1) The Contractor starting work on the contract.
(2) Processing Contractor's invoice(s) for construction activities/items of work.
(3) Review of any schedule updates.
c. Submittal of the Baseline Schedule, and subsequent schedule updates, is understood to be the Contractor's certification that the submitted schedule meets all of the requirements of the Contract Documents, represents the Contractor's plan on how the work will be accomplished, and accurately reflects the work that has been accomplished and how it was sequenced (as-built logic).
(1) Include work schedules in the plan, and notify the Contracting Officer at least 48 hours in advance of changes in work schedules.
Include in the plan provisions for the coordination of construction activities indicated in the specifications and shown on the contract drawings. Construction practices for placement quality of materials will follow those marine procedures normally found acceptable by the U.S. Army Corps of Engineers.
(2) Clearly indicate the intended segment length in the construction schedule.
1.3 SCHEDULE FORMAT
1.3.1 Bar Chart Schedule
Produce a Bar Chart to show, as a minimum, work activities, submittals, Government review periods, material and equipment delivery, utility
SECTION 01 32 16 Page 1007 outages, on-site construction, inspection, testing, and closeout activities. Make the Bar Chart time scaled and generated using an electronic spreadsheet program.
1.4 UPDATED SCHEDULES
Update the Construction schedule at monthly intervals or when the schedule has been revised. Keep the updated schedule current, reflecting actual activity progress and plan for completing the remaining work. Submit copies of purchase orders and confirmation of delivery dates as directed.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
-- End of Section --
SECTION 01 32 16 Page 1008
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 1.1 SUMMARY
1.1.1 1.1.1 Submittal Information
1.1.2 1.1.2 Project Type
1.1.3 1.1.3 Submission of Submittals
1.2 1.2 DEFINITIONS
1.2.1 1.2.1 Submittal Descriptions (SD)
1.2.2 1.2.2 Approving Authority
1.2.3 1.2.3 Work
1.3 1.3 SUBMITTALS
1.4 1.4 SUBMITTAL CLASSIFICATION
1.4.1 1.4.1 Government Approved (G)
1.4.2 1.4.2 For Information Only
1.5 1.5 PREPARATION
1.5.1 1.5.1 Transmittal Form
1.5.2 1.5.2 Electronic File Format
1.6 1.6 INFORMATION ONLY SUBMITTALS
1.7 1.7 PROJECT SUBMITTAL REGISTER
1.7.1 1.7.1 Submittal Management
1.7.2 1.7.2 Preconstruction Use of Submittal Register
1.7.3 1.7.3 Contractor Use of Submittal Register
1.7.4 1.7.4 Approving Authority Use of Submittal Register
1.7.5 1.7.5 Action Codes
1.7.5.1 1.7.5.1 Government Review Action Codes
1.7.6 1.7.6 Delivery of Copies
1.8 1.8 VARIATIONS
1.8.1 1.8.1 Considering Variations
1.8.2 1.8.2 Proposing Variations
1.8.3 1.8.3 Warranting that Variations are Compatible
1.8.4 1.8.4 Review Schedule Extension
1.9 1.9 SCHEDULING
1.10 1.10 GOVERNMENT APPROVING AUTHORITY
1.10.1 1.10.1 Review Notations
1.11 1.11 DISAPPROVED SUBMITTALS
1.12 1.12 APPROVED SUBMITTALS
1.13 1.13 WITHHOLDING OF PAYMENT
1.14 1.14 CERTIFICATION OF SUBMITTAL DATA
PART 2 PRODUCTS
PART 3 EXECUTION
ATTACHMENTS:
Submittal Register
SECTION 01 33 00 Page 1009
-- End of Section Table of Contents --
SECTION 01 33 00 Page 1010
SECTION 01 33 00
SUBMITTAL PROCEDURES
PART 1 GENERAL
1.1 SUMMARY
1.1.1 Submittal Information
a. The Contracting Officer may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective sections. Each submittal is to be complete and in sufficient detail to allow ready determination of compliance with contract requirements.
b. Units of weights and measures used on all submittals are to be the same as those used in the contract drawings.
1.1.2 Project Type
The Contractor's Quality Control (CQC) System Manager are to check and approve all items before submittal and stamp, sign, and date indicating action taken. Proposed deviations from the contract requirements are to be clearly identified. Include within submittals items such as:
Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list); certifications; warranties; and other such required submittals.
1.1.3 Submission of Submittals
Schedule and provide submittals requiring Government approval before acquiring the material or equipment. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.
1.2 DEFINITIONS
1.2.1 Submittal Descriptions (SD)
Submittal requirements are specified in the technical sections. Examples and descriptions of submittals identified by the Submittal Description (SD) numbers and titles follow:
SD-01 Preconstruction Submittals
Submittals that are required prior to or at the start of construction (work) or the next major phase of the construction on a multiphase contract.
Preconstruction Submittals include schedules and a tabular list of locations, features, and other pertinent information regarding products, materials, equipment, or components to be used in the work.
SECTION 01 33 00 Page 1011
Certificates Of Insurance
Surety Bonds
List Of Proposed Subcontractors
List Of Proposed Products
Baseline Network Analysis Schedule (NAS)
Submittal Register
Schedule Of Prices Or Earned Value Report
Accident Prevention Plan
Work Plan
Quality Control (QC) plan
Environmental Protection Plan
Contractor Accident Prevention Checklist
Contractor Activity Hazard Analysis
SD-06 Test Reports
Report signed by authorized official of testing laboratory that a material, product or system identical to the material, product or system to be provided has been tested in accord with specified requirements. Unless specified in another section, testing must have been within three years of date of contract award for the project.
Report that includes findings of a test required to be performed on an actual portion of the work or prototype prepared for the project before shipment to job site.
Report that includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.
Investigation reports
Daily logs and checklists
Final acceptance test and operational test procedure
SD-07 Certificates
Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system or material attesting that the product, system, or material meets specification requirements. Must be dated after award of project contract and clearly name the project.
Document required of Contractor, or of a manufacturer, supplier, SECTION 01 33 00 Page 1012 installer or Subcontractor through Contractor. The document purpose is to further promote the orderly progression of a portion of the work by documenting procedures, acceptability of methods, or personnel qualifications.
Confined space entry permits
Text of posted operating instructions
SD-11 Closeout Submittals
Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.
Submittals required for Guiding Principle Validation (GPV) or Third Party Certification (TPC).
Special requirements necessary to properly close out a construction contract. For example, Record Drawings and as-built drawings. Also, submittal requirements necessary to properly close out a major phase of construction on a multi-phase contract.
1.2.2 Approving Authority
Office or designated person authorized to approve the submittal.
1.2.3 Work
As used in this section, on-site and off-site construction required by contract documents, including labor necessary to produce submittals, construction, materials, products, equipment, and systems incorporated or to be incorporated in such construction. In exception, excludes work to produce SD-01 submittals.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" classification. Submit the following in accordance with this section
SD-01 Preconstruction Submittals
Submittal Register; G, AO
1.4 SUBMITTAL CLASSIFICATION
1.4.1 Government Approved (G)
Government approval is required for extensions of design, critical materials, variations, equipment whose compatibility with the entire system must be checked, and other items as designated by the Government.
1.4.2 For Information Only
Submittals not requiring Government approval will be for information only.
1.5 PREPARATION
1.5.1 Transmittal Form
SECTION 01 33 00 Page 1013
Use the attached sample transmittal form (ENG Form 4025, found in the Attachments panel of this pdf file) for submitting both Government approved and information only submittals in accordance with the instructions on the reverse side of the form. These forms will be furnished to the Contractor. Properly complete this form by filling out all the heading blank spaces and identifying each item submitted.
Exercise special care to ensure proper listing of the specification paragraph and sheet number of the contract drawings pertinent to the data submitted for each item.
1.5.2 Electronic File Format
a. Provide submittals in electronic format, with the exception of material samples required for SD-04 Samples items. RMS will be used to update, store and exchange submittals. Produce electronic files of sufficient quality that all information is legible. Use PDF as the electronic format, unless otherwise specified or directed by the Contracting Officer.
Generate PDF files from original documents with bookmarks so that the text included in the PDF file is searchable and can be copied. If documents are scanned, optical character resolution (OCR) routines are required. Index and bookmark files exceeding 30 pages to allow efficient navigation of the file. When required, include a valid electronic signature or a scan of a signature in the electronic file.
b. Provide electronic documents through an electronic file sharing system such as the DoD SAFE Web Application when document size is too large to save in RMS CM. Instructions are located at the following website:
https://safe.apps.mil/ .
1.6 INFORMATION ONLY SUBMITTALS
Submittals without a "G" designation must be certified by the QC manager and submitted to the Contracting Officer for information-only. Approval of the Contracting Officer is not required on information only submittals. The Contracting Officer will mark "receipt acknowledged" on submittals for information and will return only the transmittal cover sheet to the Contractor. Normally, submittals for information only will not be returned. However, the Government reserves the right to return unsatisfactory submittals and require the Contractor to resubmit any item found not to comply with the contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the Contracting Officer from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.
1.7 PROJECT SUBMITTAL REGISTER
A sample Project Submittal Register follows this section.
1.7.1 Submittal Management
a. Prepare and maintain a submittal register, as the work progresses. Do not change data that is output in columns (c), (d), (e), and (f) as delivered by Government; retain data that is output in columns (a), (g), (h), and (i) as approved. As an attachment, provide a submittal register
SECTION 01 33 00 Page 1014 showing items of equipment and materials for which submittals are required by the specifications. This list may not be all-inclusive and additional submittals may be required. Maintain a submittal register for the project in accordance with Section 01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE(RMS CM). The Government will provide the initial submittal register in electronic format.
Column (c): Lists specification section in which submittal is required.
Column (d): Lists each submittal description (SD Number. and type, e.g., SD-02 Shop Drawings) required in each specification section.
Column (e): Lists one principal paragraph in each specification section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting the project requirements.
b. Thereafter, the Contractor is to track all submittals by maintaining a complete list, including completion of all data columns and all dates on which submittals are received by and returned by the Government.
1.7.2 Preconstruction Use of Submittal Register
Submit the submittal register. Include the QC plan and the project schedule. Verify that all submittals required for the project are listed and add missing submittals. Coordinate and complete the following fields on the register submitted with the QC plan and the project schedule:
Column (a) Activity Number: Activity number from the project schedule.
Column (g) Contractor Submit Date: Scheduled date for the approving authority to receive submittals.
Column (h) Contractor Approval Date: Date that Contractor needs approval of submittal.
Column (i) Contractor Material: Date that Contractor needs material delivered to Contractor control.
1.7.3 Contractor Use of Submittal Register
Update the following fields in the Government-furnished submittal register program or equivalent fields in the program used by the Contractor with each submittal throughout the contract.
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (j) Action Code (k): Date of action used to record Contractor's review when forwarding submittals to QC.
Column (l) Date submittal transmitted.
Column (q) Date approval was received.
SECTION 01 33 00 Page 1015
1.7.4 Approving Authority Use of Submittal Register
Update the following fields:
Column (b) Transmittal Number: List of consecutive, Contractor-assigned numbers.
Column (l) Date submittal was received.
Column (m) through (p) Dates of review actions.
Column (q) Date of return to Contractor.
1.7.5 Action Codes
1.7.5.1 Government Review Action Codes
"A" - "Approved as submitted"; "Completed"
"B" - "Approved, except as noted on drawings"; "Completed"
"C" - "Approved, except as noted on drawings; resubmission required"; "Resubmit"
"D" - "Returned by separate correspondence"; "Completed"
"E" - "Disapproved (See attached)"; "Resubmit"
"F" - "Receipt acknowledged"; "Completed"
"G" - "Other (Specify)"; "Resubmit"
"K" - "Government concurs with Interim Design"; "Completed"
"R" - "Acceptable for Release for Construction"; "Completed"
"X" - "Receipt acknowledged, does not comply with contract requirements"; "Resubmit"
1.7.6 Delivery of Copies
Submit an updated electronic copy of the submittal register to the Contracting Officer with each invoice request. Provide an updated Submittal Register monthly regardless of whether an invoice is submitted.
1.8 VARIATIONS
Variations from contract requirements require Contracting Officer approval and will be considered where advantageous to the Government.
1.8.1 Considering Variations
a. Discussion of variations with the Contracting Officer before submission will help ensure that functional and quality requirements are met and minimize rejections and resubmittals. When contemplating a variation that results in lower cost, consider submission of the variation as a Value Engineering Change Proposal (VECP).
SECTION 01 33 00 Page 1016
b. Specifically point out variations from contract requirements in transmittal letters. Failure to point out variations may cause the Government to require rejection and removal of such work at no additional cost to the Government.
1.8.2 Proposing Variations
a. When proposing variation, deliver a written request to the Contracting Officer, with documentation of the nature and features of the variation and why the variation is desirable and beneficial to Government. Include the DOR's written analysis and approval. If lower cost is a benefit, also include an estimate of the cost savings. In addition to documentation required for variation, include the submittals required for the item.
Clearly mark the proposed variation in all documentation.
b. Check the column "variation" of ENG Form 4025 for submittals that include variations proposed by the Contractor. Set forth in writing the reason for any variations and note such variations on the submittal. The Government reserves the right to rescind inadvertent approval of submittals containing unnoted variations.
1.8.3 Warranting that Variations are Compatible
When delivering a variation for approval, the Contractor warrants that this contract has been reviewed to establish that the variation, if incorporated, will be compatible with other elements of work.
1.8.4 Review Schedule Extension
In addition to the normal submittal review period, a period of 14 calendar days will be allowed for the Government to consider submittals with variations.
1.9 SCHEDULING
a. Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Submit pertinent certifications at the same time. No delay damages or time extensions will be allowed for time lost in late submittals.
(1) Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. The Contractor is responsible for additional time required for Government reviews resulting from required resubmittals. The review period for each resubmittal is the same as for the initial submittal.
(2) Submittals required by the contract documents are listed on the submittal register. If a submittal is listed in the submittal register but does not pertain to the contract work, the Contractor is to include the submittal in the register and annotate it "N/A" with a brief explanation. Approval by the Contracting Officer does not relieve the Contractor of supplying submittals required by the contract documents but that have been omitted from the register or marked "N/A."
(3) Resubmit the submittal register and annotate it monthly with actual submission and approval dates. When all items on the register have been fully approved, no further resubmittal is required.
SECTION 01 33 00 Page 1017
(b) Contracting Officer review will be completed within 30 calendar days after the date of submission.
1.10 GOVERNMENT APPROVING AUTHORITY
a. When the approving authority is the Contracting Officer, the Government will:
(1) Note the date on which the submittal was received.
(2) Review submittals for approval within the scheduling period specified and only for conformance with project design concepts and compliance with contract documents.
(3) Identify returned submittals with one of the actions defined in paragraph REVIEW NOTATIONS and with comments and markings appropriate for the action indicated.
b. Upon completion of review of submittals requiring Government approval, stamp and date submittals. Two copies of the submittal will be retained by the Contracting Officer and one copy of the submittal will be returned to the Contractor.
1.10.1 Review Notations
Submittals will be returned to the Contractor with the following notations:
a. Submittals marked "approved" or "accepted" authorize proceeding with the work covered.
b. Submittals marked "approved as noted" or "approved, except as noted, resubmittal not required," authorize proceeding with the work covered provided that the Contractor takes no exception to the corrections.
c. Submittals marked "not approved," "disapproved," or "revise and resubmit" indicate incomplete submittal or noncompliance with the contract requirements or design concept. Resubmit with appropriate changes. Do not proceed with work for this item until the resubmittal is approved.
d. Submittals marked "not reviewed" indicate that the submittal has been previously reviewed and approved, is not required, does not have evidence of being reviewed and approved by Contractor, or is not complete. A submittal marked "not reviewed" will be returned with an explanation of the reason it is not reviewed. Resubmit submittals returned for lack of review by Contractor or for being incomplete, with appropriate action, coordination, or change.
e. Submittals marked "receipt acknowledged" indicate that submittals have been received by the Government. This applies only to "information-only submittals" as previously defined.
1.11 DISAPPROVED SUBMITTALS
a. Make corrections required by the Contracting Officer. If the Contractor considers any correction or notation on the returned submittals to constitute a change to the contract drawings or specifications, give notice to the Contracting Officer as required under the FAR clause 52.243-4
SECTION 01 33 00 Page 1018
CHANGES. The Contractor is responsible for the dimensions and design of connection details and the construction of work. Failure to point out variations may cause the Government to require rejection and removal of such work at the Contractor's expense.
b. If changes are necessary to submittals, make such revisions and resubmit in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.
1.12 APPROVED SUBMITTALS
a. The Contracting Officer's approval of submittals is not to be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory.
b. Approval or acceptance by the Government for a submittal does not relieve the Contractor of the responsibility for meeting the contract requirements or for any error that may exist, because under the Quality Control (QC) requirements of this contract, the Contractor is responsible for ensuring information contained with in each submittal accurately conforms with the requirements of the contract documents.
c. After submittals have been approved or accepted by the Contracting Officer, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is necessary.
1.13 WITHHOLDING OF PAYMENT
Payment for materials incorporated in the work will not be made if required approvals have not been obtained.
1.14 CERTIFICATION OF SUBMITTAL DATA
Certify the submittal data as follows on Form ENG 4025: "I certify that the above submitted items had been reviewed in detail and are correct and in strict conformance with the contract drawings and specifications except as otherwise stated.
______NAME OF CONTRACTOR ______ SIGNATURE OF CONTRACTOR
PART 2 PRODUCTS
Not Used
PART 3 EXECUTION
Not Used
-- End of Section --
SECTION 01 33 00 Page 1019
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 1 OF 2 PAGES
FY25 CONNEAUT HARBOR DREDGING
01 32 16 SD-01 Preconstruction Submittals
1.2 G AOConstruction Schedule
01 33 00 SD-01 Preconstruction Submittals
1.7 G AOSubmittal Register
01 35 13 SD-01 Preconstruction Submittals
1.2.1Schedule of Work
3.3 G AOPlacement Plan
1.3.11Real Estate Rights
SD-06 Test Reports
1.2.2Contract Accruals
SD-07 Certificates
1.3.9Notifications
1.3.3Notice to Mariners
01 35 26 SD-01 Preconstruction Submittals
1.8 G SOAccident Prevention Plan (APP)
SD-06 Test Reports
1.12.2 G SOAccident Reports
1.12.3LHE Inspection Reports
1.5Monthly Exposure Reports
SD-07 Certificates
1.9 G SOActivity Hazard Analysis (AHA)
1.13Hot Work Permit
1.7.5 G SOCrane Operators/Riggers
1.12.4 G SOStandard Lift Plan (SLP)
1.12.4 G SOCritical Lift Plan (CLP)
1.12.4 G SOCertificate Of Compliance
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SUBMITTAL FORM,Jan 96 PREVIOUS EDITION IS OBSOLETE PAGE 2 OF 2 PAGES
FY25 CONNEAUT HARBOR DREDGING
01 35 26 1.14Confined Space Entry Permit
1.12.5 G SONaval Architectural Analysis
(NAA) / Floating Service Load
Chart (FSLC)
01 45 00 SD-01 Preconstruction Submittals
3.2 G AOContractor Quality Control (CQC)
Plan
3.2 G AOContractor Quality Control Plan
Checklist
01 57 19 SD-01 Preconstruction Submittals
1.5.1 G AORegulatory Notifications
1.6 G AOEnvironmental Protection Plan
SD-11 Closeout Submittals
3.4.1Waste Determination
Documentation
35 20 23 SD-11 Closeout Submittals
3.7Quality Control Survey
35 20 23.13 SD-07 Certificates
1.4 G SAMNational Dredging Quality
Management Program Certification
SUBMITTAL REGISTER
CONTRACT NO.
TITLE AND LOCATION CONTRACTOR
CONTRACTOR:
SCHEDULE DATES
CONTRACTOR
ACTION
APPROVING AUTHORITY
A C T I V I T Y
N O
T R A N S M I T T A L
N O
S P E C
S E C T
DESCRIPTION
ITEM SUBMITTED
P A R A G R A P H
C L A S S I F I C A T I O N
G O V T
O R
A E
R E V W
R SUBMIT
APPROVAL
NEEDED
BY
MATERIAL
NEEDED
BY
A C T I O N
C O D E
DATE
OF
ACTION
DATE FWD
TO APPR
AUTH/
DATE RCD
FROM
CONTR
DATE FWD
TO OTHER
REVIEWER
DATE RCD
FROM OTH
REVIEWER
A C T I O N
C O D E
DATE
OF
ACTION
MAILED
TO
CONTR/
DATE RCD
FRM APPR
AUTH REMARKS
(a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) (m) (n) (o) (p) (q) (r)
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
1.2 PERFORMANCE PERIOD AND RESTRICTIONS
1.2.1 Schedule of Work
1.2.2 Contract Accruals
1.3 PROJECT/SITE CONDITIONS
1.3.1 Condition and Use of Project Site
1.3.2 Physical Conditions
1.3.3 Waterways Navigation, Traffic and Notice to Mariners
1.3.4 General Navigation
1.3.4.1 Hazards to Navigation
1.3.5 Existing Vegetation, Structures, Equipment, Utilities &
Improvements
1.3.6 Condition of Channels
1.3.7 Temporary Lights, Signals and Buoys Required by the Coast Guard
1.3.8 Dredging Vertical Datum and Control
1.3.9 Notifications
1.3.10 Environmental Restrictions
1.3.11 Real Estate Rights
PART 2 PRODUCTS (Not Applicable)
PART 3 EXECUTION
3.1 SUBMITTAL PROCEDURES
3.1.1 Procedures
3.1.2 Deviations
3.2 ORDER OF WORK
3.2.1 See paragraph 1.3.10.
3.2.2 See Section 01 20 00 for coordination requirements between the
Contractor and the sediment placement facility operator.
3.3 DREDGED MATERIAL PLACEMENT
ATTACHMENTS:
Control
-- End of Section Table of Contents --
SECTION 01 35 13 Page 1020
SECTION 01 35 13
SPECIAL PROJECT PROCEDURES
PART 1 GENERAL
1.1 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01, Preconstruction Submittals
Schedule of Work
Placement Plan; G, AO
Real Estate Rights
SD-06, Test Reports
Contract Accruals
SD-07, Certificates
Notifications
Notice to Mariners
1.2 PERFORMANCE PERIOD AND RESTRICTIONS
a. Complete the entire work ready for use not later than the date indicated below. If the option is exercised, additional time will be allowed at the rate indicated below, for any portion of any option exercised, for dredging and placement. See applicable FAR clauses. A period of time between Notice to Proceed and the actual start of dredging will be allocated for submittal review and approval. The time stated for completion includes final clean-up of the premises. Comply with the milestone schedule below.
Rate: 2,500 CY per day
Milestone Maximum Calendar Days After Receipt of Notice to Proceed
Commence Actual Dredging 77 Operations
Complete Base Bid Work 97
Complete Option Bid Work 105 (If entire quantity of options are exercised)
SECTION 01 35 13 Page 1021
b. The Notice to Proceed will be issued on or about 30 May 2025.
c. The environmental window for dredging is 01 July to 14 September.
1.2.1 Schedule of Work
Based upon contract award, submit a complete schedule of work covering the period of time from the Notice of Award through the specified duration of the contract, including all private and Government work, and the plant intended for each project, to the Contracting Officer within 10 calendar days of receipt of the Notice of Award.
1.2.2 Contract Accruals
In conjunction with the schedule submittal requirements specified in FAR 52.236-15 SCHEDULES FOR CONSTRUCTION CONTRACTS, submit a monthly listing of accruals. Accruals are used to provide projections of the incremental costs not yet paid for, but earned. Perform the accrual submittal one week before the end of each month throughout the contract duration.
Provide the accrual information for each line item of the Bidding Schedule.
1.3 PROJECT/SITE CONDITIONS
1.3.1 Condition and Use of Project Site
The drawings indicate depths and elevations. Provide a notification of at least 5 calendar days to the Contracting Officer prior to bringing any dredging equipment or material to the work site. The Contractor is responsible for damages that may be suffered due to Contractor operations. Note FAR 52.236-9 PROTECTION OF EXISTING VEGETATION, STRUCTURES, EQUIPMENT, UTILITIES, AND IMPROVEMENTS.
1.3.2 Physical Conditions
The physical conditions shown on the drawings are indicative of those that prevailed at the time of the site investigations and may be different than those at the time of dredging. Report significant variations that require changes to the plans, specifications, or both to the Contracting Officer immediately.
1.3.3 Waterways Navigation, Traffic and Notice to Mariners
a. General Information: There is a moderate amount of traffic in the harbor consisting of fishing boats, recreational boats, tugs, barges, and all classes of lake vessels varying in length to over 600 feet. To prevent any delays to the shipping industry, no mooring of dredging equipment in any of the turning basins is allowed.
b. Coordination and Notification Requirements
(1) Become acquainted with all information and regulations pertaining to navigation and vessel traffic within the waterways.
(2) Coordinate with the U.S. Coast Guard Offices indicated in the paragraph entitled "Notifications" of this Section to ensure that a "NOTICE TO MARINERS" is issued prior to work activity at the project site.
c. Preparing the "NOTICE TO MARINERS" Request
SECTION 01 35 13 Page 1022
(1) Be as specific as possible, providing detailed information about the dredging operations, including the who, what, when, and where of the activity.
(2) Include geographic coordinates for the dredging area, even if they are approximate, to ensure clarity for the boating public.
(3) Use the email address LocalNoticetoMariners@uscg.mil to submit the request.
(4) A copy of the requisite notice form is attached to this solicitation.
Submit the completed form to the address shown on the form so that it arrives no less than 2 weeks prior to the start of work activity at the project site.
(5) Submit a copy of the completed "NOTICE TO MARINERS" form to the
Government prior to the commencement of work.
d. Navigation and Safety Regulations
(1) The Government will not undertake to keep the waterways free from vessels or other obstructions, except to the extent of such regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917 (see Title 33 U.S.C.A. Sec. 1).
(2) Conduct work in such a manner as to obstruct navigation as little as possible.
(3) In case the Contractor's plant obstructs a channel, making it difficult or endangering the passage of vessels, promptly move any plant on the approach of any vessel, as may be necessary to allow safe passage.
(4) Upon completion of the work, promptly remove the plant, including ranges, buoys, piles, and other marks placed under the contract, in navigable waters or on shore.
1.3.4 General Navigation
a. The site of dredging is considered partially sheltered and subject to wave action. Information and regulations pertaining to navigation may be obtained from the current issue of the "United States Coast Pilot 6".
(1) The "United States Coast Pilot 6" may be obtained electronically from https://nauticalcharts.noaa.gov/publications/coast-pilot/download.php?book=6.
Copy and paste this link into a web browser. Alternately, it may be obtained from the National Ocean Survey, NOAA, Distribution Division-C44, Riverside, Maryland 20840.
1.3.4.1 Hazards to Navigation
Maintain complete control of the movement of floating equipment and material. Loose floating equipment and material are not permitted. Keep in readiness at all times a powered craft capable of moving, securing and disposing of floating equipment which may get loose and become a hazard to navigation.
SECTION 01 35 13 Page 1023
1.3.5 Existing Vegetation, Structures, Equipment, Utilities & Improvements
General locations of applicable existing utilities, vegetation, structures, equipment and improvements, based upon latest information available to the Government have been shown on the drawings. However, it is the responsibility of the Contractor to establish the exact horizontal and vertical location and size of all existing utility lines which are located within the required work area. Confer with the owners of the crossings regarding their exact locations and elevations. Report any utility lines that are not found by the Contractor, but are known to exist at the project site, to the Contracting Officer immediately.
1.3.6 Condition of Channels
Reference drawings showing the depths for the most recent survey are available on the web at http://navigation.usace.army.mil/Survey/Hydro or http://www.lrb.usace.army.mil/Library/MapsandCharts.aspx . For surveys older than those shown on either website, contact the Survey Section at
(716) 879-4429. Previous surveys are for information only, and are not representative of current conditions.
1.3.7 Temporary Lights, Signals and Buoys Required by the Coast Guard
Display all temporary lights, signals and buoys required by the U.S. Coast Guard during the project work. Information regarding required signals, lights, buoys and other requirements may be obtained from the Commander OAN), U.S. Coast Guard, Shore Maintenance Detachment, ATTENTION: Aids to Navigation Branch, 1240 East Ninth Street, Cleveland, Ohio 44199-2060, Telephone (216) 902-6070.
1.3.8 Dredging Vertical Datum and Control
a. The plane of reference is the low water datum, elevation is 569.2 feet above mean level at Rimouski, Quebec (IGLD85) (International Great Lakes Datum 1985).
b. Control can be found as attachments following this section.
c. Upon request, the Government may provide additional control.
d. Verify all control prior to use.
1.3.9 Notifications
Within 5 calendar days of completing the notifications required under this contract, submit to the Contracting Officer, written verification of these notifications, including the date, time and the name of the point of contact with whom correspondence occurred. Send these verifications to:
U.S. Army Corps of Engineers Buffalo District Ohio Area Office 1035 East 9th Street Cleveland, OH 44114 Tel.: (216) 685-1213 Fax: (216) 522-2470
a. Notify the City of Conneaut, as indicated below, at least 3
SECTION 01 35 13 Page 1024 calendar days prior to commencement of dredging, concerning the initiation of dredging.
City of Conneaut Public Water System Administrative Contact: Nicholas Sanford Office Number: 440-593-7401 Emergency Number: 440-593-7437 Email: manager@conneautoh.org
b. Notify the Civil Engineering Unit, Ninth Coast Guard District, 1240 E. Ninth Street, Room 2179, Cleveland, OH 44199-2060, phone (216) 902-6206, at least 3 weeks prior to commencement of construction, concerning the presence of Coast Guard-owned cables and the necessary action and coordination to prevent cable damage.
c. Notify the Ohio Environmental Protection Agency, both the Section 401 Coordinator (P.O. Box 1049, 1800 Watermark Drive, Columbus, OH 43266-0149, Phone (614) 644-3020), and the Northeast District Office (2110 East Aurora Road, Twinsburg, OH 44087, Phone: (330) 963-2100, at least 3 business days prior to commencement of dredging, concerning the initiation of dredging.
d Advise the following U.S. Coast Guard Offices regarding the "Notice to Mariners" requirements of the contract:
U.S. Coast Guard Command Center, Sector Buffalo 1 Fuhrmann Blvd.
Buffalo, New York 14203 Tel: (716) 843-9525/843-9527 Fax: (716) 843-9594
e. Consult with the U.S. Coast Guard Office indicated below for the most recent Federal Register for more specific information and scheduled marine events which may effect the dredging, transportation and placement operations. Additionally the Contractor is advised that contact with the indicated agencies regarding marine events is an ongoing requirement. Schedule dredging/transportation/placement work should be scheduled accordingly.
U.S. Coast Guard Prevention Division Waterways Management Branch 1240 E. 9th Street, #2061 Cleveland, Ohio 44199-2060 Tel: (216) 902-6045
1.3.10 Environmental Restrictions
a. Adhere to all provisions set forth in the 401 Water Quality Certification documents and maintain a copy of this document on the dredging vessel during the entire duration of dredging operations.
b. If mussels, or mussel beds, or both, are encountered at any time during dredging activities, stop work immediately and contact the Ohio Department of Natural resources (ODNR), Division of Wildlife for further evaluation of the project site. The point of contact will be provided at the pre-construction meeting.
SECTION 01 35 13 Page 1025
c. Dredging in the river channel will be performed in maximum 50-foot wide +/- cuts running parallel to the channel centerline.
d. Dredging in the outer harbor (lakeward of Station 25+00) cannot occur until after June 30.
1.3.11 Real Estate Rights
All rights for the use of required real estate are shown on the drawings.
Copies of the real estate agreements for this project are included in the solicitation package, if applicable. No additional real estate rights are required to complete the project.
a. Additional Real Estate Rights Obtained by the…
This is the start of the file's text. The full file is on GovTribe.