5MAR24 Fabrication Schedule.pdf

PDF 442 KB Posted

Attached to
Fabrication Quality Assurance (QA) Inspection Services
Solicitation number
W912P424Q0003
Issued by

About this file

This document appears to be a project schedule for the fabrication of a hydraulic steel structure, specifically the Black Rock Lock Upper Miter Gate under Contract W911WN22D0005. The key details include:

The project has a total duration of 870.3 days, with a planned start date of September 27, 2022 and a planned completion date of March 12, 2026. Major milestones include award/notice to proceed on September 27, 2022, a one-year project extension on February 14, 2023, and various drawing issue and review dates for the left and right leaf miter gates. The schedule outlines the detailed tasks and durations for project development, engineering, procurement, fabrication, assembly, painting, shipping, and field work. Long lead items include the pintle assembly, miter blocks, and anchorage link components. The fabrication phase is expected to take 277.3 days, with key activities such as burn/prep/cut, welding, drilling, and painting.

In addition, there is a related federal contract opportunity for Quality Assurance (QA) inspection services on the fabricated and coated hydraulic steel structures and other metal components under Solicitation W912P424Q0003. The QA services are being procured by the U.S. Army Corps of Engineers, Engineering District Buffalo.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ID Task

Mode

Task Name Duration Start Finish Actual Start Actual Finish % Complete

0 12324-C Black Rock Lock Upper Miter Gate - W911WN22D0005 870.3 days Tue 9/27/22 Thu 3/12/26 Tue 9/27/22 NA 25%

1 Milestones 870.3 days Tue 9/27/22 Thu 3/12/26 Tue 9/27/22 NA 0%

2 Award - NTP 0 days Tue 9/27/22 Tue 9/27/22 Tue 9/27/22 NA 99%

3 Project Delay - One Year Extension by USACE 0 days Tue 2/14/23 Tue 2/14/23 Tue 2/14/23 Tue 2/14/23 100%

4 Project Development 6 wks Tue 10/18/22 Fri 12/2/22 Tue 10/18/22 NA 0%

5 Long Lead Drawing Issue for Review 0 days Wed 5/17/23 Wed 5/17/23 NA NA 0%

6 Long Lead Drawing Issue for Fabrication 0 days Fri 6/23/23 Fri 6/23/23 NA NA 0%

7 Left Leaf Drawing Issue for Review 0 days Wed 12/20/23 Wed 12/20/23 NA NA 0%

8 Left Leaf Drawing Issue for Fabrication 0 days Wed 1/31/24 Wed 1/31/24 NA NA 0%

9 Right Leaf Drawing Issue for Review 0 days Wed 1/31/24 Wed 1/31/24 NA NA 0%

10 Right Leaf Drawing Issue for Fabrication 0 days Thu 3/21/24 Thu 3/21/24 NA NA 0%

11 Project Hold - Field Discovery Project Delay (1 Year Contract Extension) 0 days Mon 2/13/23 Mon 2/13/23 NA NA 0%

12 Prefabrication Conference 0 days Thu 3/21/24 Thu 3/21/24 NA NA 0%

13 Witness Points 0 days Tue 9/27/22 Tue 9/27/22 NA NA 0%

14 Witness Point 1 - Initial QA Inspection 0 days Tue 9/27/22 Tue 9/27/22 NA NA 0%

15 Witness Point 2 - Intermediate QA Inspection 0 days Tue 9/27/22 Tue 9/27/22 NA NA 0%

16 Witness Point 3 - Final QA Inspection 0 days Tue 9/27/22 Tue 9/27/22 NA NA 0%

17 Delivery 1 0 days Wed 2/25/26 Wed 2/25/26 NA NA 0%

18 Project Complete 0 days Thu 3/12/26 Thu 3/12/26 NA NA 0%

19 Invoices 460 days Wed 1/25/23 Mon 11/18/24 NA NA 0%

25 Pre-fab Documentation / Submittals 83 days Tue 12/6/22 Tue 4/4/23 Tue 12/6/22 NA 48%

26 Certs 13.9 days Tue 12/6/22 Tue 12/27/22 Tue 12/6/22 Tue 12/27/22 100%

27 Weld Procedures 30 days Tue 2/21/23 Tue 4/4/23 NA NA 0%

28 Welder Qualifications 13.9 days Tue 12/6/22 Tue 12/27/22 Tue 12/6/22 Tue 12/27/22 100%

29 Engineering 303 days Tue 1/10/23 Thu 3/21/24 Tue 1/10/23 NA 84%

30 Develop ABOM 14 days Tue 1/10/23 Mon 1/30/23 NA NA 0%

31 Left Hand Leaf (As Shown) 284 days Mon 2/6/23 Thu 3/21/24 Mon 2/6/23 NA 87%

32 RFI Period 284 days Mon 2/6/23 Thu 3/21/24 Mon 2/6/23 NA 87%

33 RFI-001 - Recoat window for VZ-108d Primer 29.9 days Mon 2/6/23 Fri 3/17/23 Mon 2/6/23 Fri 3/17/23 100%

34 RFI-002 - Toughness requirements for fracture critical components 36.9 days Mon 2/6/23 Tue 3/28/23 Mon 2/6/23 Tue 3/28/23 100%

35 RFI-003 - Toughness requirements for A668 Class D FCM 29.9 days Mon 2/6/23 Fri 3/17/23 Mon 2/6/23 Fri 3/17/23 100%

36 RFI-004 - Diagonal hex nut grease fitting hole 11.9 days Mon 2/6/23 Tue 2/21/23 Mon 2/6/23 Tue 2/21/23 100%

37 RFI-005 - Quoin seal fluorocarbon 11.9 days Mon 2/6/23 Tue 2/21/23 Mon 2/6/23 Tue 2/21/23 100%

38 RFI-006 - Seal backing bar 11.9 days Mon 2/6/23 Tue 2/21/23 Mon 2/6/23 Tue 2/21/23 100%

39 RFI-007 - Pintle ball material 11.9 days Mon 2/6/23 Tue 2/21/23 Mon 2/6/23 Tue 2/21/23 100%

40 RFI-008 - Shim material 29.9 days Mon 2/6/23 Fri 3/17/23 Mon 2/6/23 Fri 3/17/23 100%

41 RFI-009 - Pintle socket setscrew holes 30.9 days Mon 2/6/23 Mon 3/20/23 Mon 2/6/23 Mon 3/20/23 100%

42 RFI-010 - Fasteners for miter and quoin blocks 30.9 days Mon 2/6/23 Mon 3/20/23 Mon 2/6/23 Mon 3/20/23 100%

43 RFI-011 - Pintle Details 25.9 days Mon 2/13/23 Mon 3/20/23 Mon 2/13/23 Mon 3/20/23 100%

44 RFI-012 - Pintle Bushing Details 25.9 days Mon 2/13/23 Mon 3/20/23 Mon 2/13/23 Mon 3/20/23 100%

45 RFI-013 - Pintle Socket Details 25.9 days Mon 2/13/23 Mon 3/20/23 Mon 2/13/23 Mon 3/20/23 100%

46 RFI-014 - Pintle Socket, Pintle Plate and Thrust Plate Details 25.9 days Mon 2/13/23 Mon 3/20/23 Mon 2/13/23 Mon 3/20/23 100%

47 RFI-015 - Pintle Plate Bends and Hole Locations 25.9 days Mon 2/13/23 Mon 3/20/23 Mon 2/13/23 Mon 3/20/23 100%

48 RFI-016 - S-565-E5 Wedge Slot Width Clarification 11.9 days Mon 4/10/23 Tue 4/25/23 Mon 4/10/23 Tue 4/25/23 100%

49 RFI-017 - Class B Slip Critical 10.9 days Mon 4/10/23 Mon 4/24/23 Mon 4/10/23 Mon 4/24/23 100%

50 RFI-018 - Location of S-564-A5 in assembly 10.9 days Mon 4/10/23 Mon 4/24/23 Mon 4/10/23 Mon 4/24/23 100%

51 RFI-019 - Location of S-564-A7 weld access holes 10.9 days Mon 4/10/23 Mon 4/24/23 Mon 4/10/23 Mon 4/24/23 100%

52 RFI-020 - Top girder geometry 10.9 days Mon 4/10/23 Mon 4/24/23 Mon 4/10/23 Mon 4/24/23 100%

53 RFI-021 - Anchorage Link Wedges 11.9 days Mon 4/10/23 Tue 4/25/23 Mon 4/10/23 Tue 4/25/23 100%

54 RFI-020 - Fasteners for Miter and Quoin Blocks 13.9 days Thu 4/20/23 Tue 5/9/23 Thu 4/20/23 Tue 5/9/23 100%

55 RFI-023 - Pintle Socket Setscrew Holes 14.9 days Wed 4/19/23 Tue 5/9/23 Wed 4/19/23 Tue 5/9/23 100%

56 RFI-024 - Direct Tension Indicator Washers or Flat Washers 26.9 days Thu 6/22/23 Mon 7/31/23 Thu 6/22/23 Mon 7/31/23 100%

57 RFI-025 - Upstream and Downstream Bracket Bolt Size and Interference 21.9 days Thu 6/29/23 Mon 7/31/23 Thu 6/29/23 Mon 7/31/23 100%

58 RFI-026 - Weld Interference 30 days Mon 7/31/23 Tue 9/12/23 Mon 7/31/23 NA 0%

59 RFI-027 - Weld Interference 27.9 days Mon 7/31/23 Thu 9/7/23 Mon 7/31/23 Thu 9/7/23 100%

60 RFI-028 - Missing Weld Information 27.9 days Mon 7/31/23 Thu 9/7/23 Mon 7/31/23 Thu 9/7/23 100%

61 RFI-029 - Bolt Hole Interference 27.9 days Mon 7/31/23 Thu 9/7/23 Mon 7/31/23 Thu 9/7/23 100%

62 RFI-030 - Pintle Socket and Bushing Assembly 27.9 days Mon 7/31/23 Thu 9/7/23 Mon 7/31/23 Thu 9/7/23 100%

63 RFI-031 - Pintle Plate and Pintle Socket Interference 1.9 days Fri 8/4/23 Mon 8/7/23 Fri 8/4/23 Mon 8/7/23 100%

64 RFI-032 - Bolt Interferences 18.9 days Fri 8/11/23 Thu 9/7/23 Fri 8/11/23 Thu 9/7/23 100%

65 RFI-033 - Quoin Seal Length 18.9 days Fri 8/11/23 Thu 9/7/23 Fri 8/11/23 Thu 9/7/23 100%

66 RFI-034 - Miter Seal, Bottom Girder Interference 18.9 days Fri 8/11/23 Thu 9/7/23 Fri 8/11/23 Thu 9/7/23 100%

67 RFI-035 - Diagonal Layout 40.9 days Fri 8/18/23 Mon 10/16/23 Fri 8/18/23 Mon 10/16/23 100%

68 RFI-036 - Diagonal Intersection 33.9 days Tue 8/29/23 Mon 10/16/23 Tue 8/29/23 Mon 10/16/23 100%

69 RFI-037 - Control Dimension Conflict 29.9 days Tue 9/5/23 Mon 10/16/23 Tue 9/5/23 Mon 10/16/23 100%

70 RFI-038 - Control Dimension Conflict 28.9 days Wed 9/6/23 Mon 10/16/23 Wed 9/6/23 Mon 10/16/23 100%

71 RFI-039 - Anchorage Link, Miter Block, Quoin Block Elevations 27.9 days Thu 9/7/23 Mon 10/16/23 Thu 9/7/23 Mon 10/16/23 100%

72 RFI-040 - Upstream Bracket/Top Girder Weld Interference 26.9 days Fri 9/8/23 Mon 10/16/23 Fri 9/8/23 Mon 10/16/23 100%

73 RFI-041 - Weld Interference 25.9 days Tue 9/19/23 Tue 10/24/23 Tue 9/19/23 Tue 10/24/23 100%

74 RFI-042 - Weld Interference 10.9 days Mon 10/2/23 Mon 10/16/23 Mon 10/2/23 Mon 10/16/23 100%

75 RFI-043 - Top Girder Geometry 10.9 days Mon 10/2/23 Mon 10/16/23 Mon 10/2/23 Mon 10/16/23 100%

76 RFI-044 - Gudgeon/Pintle Offset 32.9 days Mon 10/2/23 Wed 11/15/23 Mon 10/2/23 Wed 11/15/23 100%

77 RFI-045 - Control Dimension 2 10.9 days Mon 10/2/23 Mon 10/16/23 Mon 10/2/23 Mon 10/16/23 100%

78 RFI-046 - Upstream Bracket Welds 30 days Thu 10/19/23 Mon 12/4/23 Thu 10/19/23 NA 0%

79 RFI-047 - S-563-E1 Seal Geometry 30 days Thu 10/26/23 Mon 12/11/23 Thu 10/26/23 NA 0%

80 RFI-048 - Gudgeon Pin Length 30 days Wed 11/15/23 Wed 1/3/24 Wed 11/15/23 NA 0%

81 RFI-049 - Walkway Holes 30 days Thu 2/8/24 Thu 3/21/24 Thu 2/8/24 NA 0%

82 RFI-050 Fender Excess Clearance 12.9 days Tue 2/13/24 Thu 2/29/24 Tue 2/13/24 Thu 2/29/24 100%

83 RFI-051 Hydraulic Tensioner Sleeve Material Availability 4.9 days Wed 2/21/24 Tue 2/27/24 Wed 2/21/24 Tue 2/27/24 100%

84 Shop Drawings 213 days Wed 5/17/23 Thu 3/21/24 Wed 5/17/23 NA 76%

85 Long Lead Items 26.9 days Wed 5/17/23 Fri 6/23/23 Wed 5/17/23 Fri 6/23/23 100%

86 Submit 0.9 days Wed 5/17/23 Wed 5/17/23 Wed 5/17/23 Wed 5/17/23 100%

87 Customer Approval 0.9 days Mon 5/22/23 Mon 5/22/23 Mon 5/22/23 Mon 5/22/23 100%

88 Redlines - Submit 1.9 days Tue 5/23/23 Wed 5/24/23 Tue 5/23/23 Wed 5/24/23 100%

89 Customer Approval for Redlines 18.9 days Wed 5/24/23 Tue 6/20/23 Wed 5/24/23 Tue 6/20/23 100%

90 Release Drawings 0.9 days Fri 6/23/23 Fri 6/23/23 Fri 6/23/23 Fri 6/23/23 100%

91 Left Hand Leaf (As Shown) 181 days Fri 6/23/23 Wed 3/13/24 Fri 6/23/23 NA 84%

92 Model/Assembly 67.9 days Fri 6/23/23 Thu 9/28/23 Fri 6/23/23 Thu 9/28/23 100%

93 Detail Drawings 27.9 days Fri 9/29/23 Tue 11/7/23 Fri 9/29/23 Tue 11/7/23 100%

94 Checking 12 days Tue 11/7/23 Mon 11/27/23 Tue 11/7/23 Mon 11/27/23 100%

95 Redlines 16.9 days Tue 11/28/23 Wed 12/20/23 Tue 11/28/23 Wed 12/20/23 100%

96 Submit 0 days Wed 12/20/23 Wed 12/20/23 Wed 12/20/23 Wed 12/20/23 100%

97 Customer Approval 12 days Wed 12/20/23 Wed 1/10/24 Wed 12/20/23 Wed 1/10/24 100%

98 Redlines - Approved 14.9 days Thu 1/11/24 Wed 1/31/24 Thu 1/11/24 Wed 1/31/24 100%

99 Submit Revised Drawings for Approval 0.9 days Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 100%

100 Customer Approval 30 days Wed 1/31/24 Wed 3/13/24 Wed 1/31/24 NA 0%

101 Release Drawings 0 days Wed 1/31/24 Wed 1/31/24 NA NA 0%

102 Right Hand Leaf (Opposite Hand) 62 days Thu 12/21/23 Thu 3/21/24 Thu 12/21/23 NA 44%

103 Model/Assembly 9.9 days Thu 12/21/23 Mon 1/8/24 Thu 12/21/23 Mon 1/8/24 100%

104 Detail Drawings 9.9 days Tue 1/9/24 Mon 1/22/24 Tue 1/9/24 Mon 1/22/24 100%

105 Checking 5.9 days Tue 1/23/24 Tue 1/30/24 Tue 1/23/24 Tue 1/30/24 100%

106 Redlines 0.9 days Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 100%

107 Submit 0.9 days Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 Wed 1/31/24 100%

108 Customer Approval 30 days Thu 2/1/24 Thu 3/14/24 Thu 2/1/24 NA 0%

109 Redlines - Approved 5 days Thu 3/14/24 Thu 3/21/24 NA NA 0%

110 Release Drawings 0 days Thu 3/21/24 Thu 3/21/24 NA NA 0%

111 Procurement 541 days Tue 9/27/22 Mon 11/18/24 Tue 9/27/22 NA 14%

112 ABOM 260 days Tue 8/8/23 Mon 8/19/24 Tue 8/8/23 NA 56%

113 Plate Material 103.9 days Tue 8/8/23 Mon 1/8/24 Tue 8/8/23 Mon 1/8/24 100%

116 Angle Material 80 days Thu 4/25/24 Mon 8/19/24 NA NA 0%

119 Long Lead Items 541 days Tue 9/27/22 Mon 11/18/24 Tue 9/27/22 NA 12%

120 Pintle Assembly 338 days Wed 7/19/23 Mon 11/18/24 Wed 7/19/23 NA 45%

121 12324-1 | S-535-A1 | Pintle | ASTM A668 CL D | Qty. 2 24 wks Thu 3/21/24 Wed 9/11/24 NA NA 0%

122 12324-2 | S-535-A4 | Pintle Bushing | ASTM B148 Copper Alloy | Qty. 2 20 wks Thu 3/21/24 Tue 8/13/24 NA NA 0%

123 12324-3 | S-536-A1 | Pintle Socket Casting | ASTM A148 GR. 90-60 | Qty. 2 27.98 wks Wed 7/19/23 Wed 2/7/24 Wed 7/19/23 Wed 2/7/24 100%

124 12324-5 | S-537-A1 | Pintle Base Casting | ASTM A148 GR. 90-60 | Qty. 2 29.78 wks Wed 7/19/23 Tue 2/20/24 Wed 7/19/23 Tue 2/20/24 100%

125 12324-4 | S-537-E6 | 3/4 x 2 | Set Screw | Qty. 16 26 wks Wed 5/15/24 Mon 11/18/24 NA NA 0%

126 Miter Blocks 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

127 S-547-A5 | Left Miter Block | ASTM A668 CL D | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

128 S-547-D5 | Right Miter Block | ASTM A668 CL D | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

129 S-548-A5 | Quoin Block | ASTM A668 CL D | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

130 S-548-D5 | Quoin Block | ASTM A668 CL D | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

131 S-565-F8 | Anchorage Link Assembly 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

132 S-565-E1 | Anchorage Link Rod Eye | ASTM A668 CL K | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

133 S-565-E5 | Anchorage Link Plate | ASTM A668 CL K | Qty. 4 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

134 S-565-A1 | Anchorage Link Rod Eye | ASTM A668 CL K | Qty. 2 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

135 S-565-A5 | Anchorage Link Hook Plate | ASTM A668 CL K | Qty. 4 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

136 S-561-E1 | Gudgeon Hood | Qty. 2 196 days Tue 8/8/23 Fri 5/17/24 Tue 8/8/23 NA 74%

137 S-561-A9 | Gudgeon Pin | AISI 4140 | Qty. 2 8 wks Thu 3/21/24 Fri 5/17/24 NA NA 0%

138 12324-7 | S-561-D1 | Bushing | ASTM B148 Copper Alloy No. C95400 | Qty. 2 11.58 wks Tue 8/8/23 Fri 10/27/23 Tue 8/8/23 Fri 10/27/23 100%

139 12324-8 | S-561-D3 | Top/Bottom Bushing | ASTM B148 Copper Alloy No. C95400 | Qty. 4 11.58 wks Tue 8/8/23 Fri 10/27/23 Tue 8/8/23 Fri 10/27/23 100%

140 S-545-E1 | Left Miter Guide | Qty. 2 186 days Tue 8/8/23 Fri 5/3/24 Tue 8/8/23 NA 49%

141 S-545-A7 | Miter Guide Pin | SAE A151 4140 HT | Qty. 1 6 wks Thu 3/21/24 Fri 5/3/24 NA NA 0%

142 S-545-A9 | Miter Guide Roller | SAE A151 1045 HR | Qty. 1 6 wks Thu 3/21/24 Fri 5/3/24 NA NA 0%

143 12324-6 | S-545-D7 | Miter Guide Bushing | ASTM B148 Copper Alloy No. C95400 | Qty. 1 57.9 days Tue 8/8/23 Fri 10/27/23 Tue 8/8/23 Fri 10/27/23 100%

144 S-547-D1 | Right Miter Block 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

145 S-547-D5 | Miter Block | ASTM A668 Gr. D | Qty. 1 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

146 S-547-A1 | Left Miter Block 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

147 S-547-A5 | Miter Block | ASTM A668 Gr. D | Qty. 1 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

148 S-548-D1 | Quoin Block 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

149 S-548-D5 | Block | ASTM A668 Gr. D | Qty. 1 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

150 S-548-A1 | Quoin Block 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

151 S-548-A5 | Block | ASTM A668 Gr. D | Qty. 1 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

152 S-560-E8 | Operating Strut Pin | A151 4140 HT | Qty. 1 8 wks Thu 3/21/24 Fri 5/17/24 NA NA 0%

153 S-520-A1 Diagonal Assembly 90 days Thu 3/21/24 Tue 7/30/24 NA NA 0%

154 S-520-A9 | Diagonals | ASTM A668 CL D | Qty. 4 18 wks Thu 3/21/24 Tue 7/30/24 NA NA 0%

155 S-520-A3 | Plate | AISI 4140 HT | Qty. 8 4 wks Thu 3/21/24 Fri 4/19/24 NA NA 0%

156 S-521-E3 | Plate | ASTM A572 Gr. 50 | Qty. 4 4 wks Thu 3/21/24 Fri 4/19/24 NA NA 0%

157 S-521-E5 | Diagonal Nut | ASTM A572 Gr. 42 | Qty. 4 4 wks Thu 3/21/24 Fri 4/19/24 NA NA 0%

158 S-521-A3 | Diagonal Lock | AISI 4140 HT | Qty. 4 4 wks Thu 3/21/24 Fri 4/19/24 NA NA 0%

159 S-560-E1 | Operating Strut Pin | AISI 4140 HT | Qty. 2 4 wks Thu 3/21/24 Fri 4/19/24 NA NA 0%

160 Seals 493 days Tue 9/27/22 Wed 9/11/24 NA NA 0%

161 S-563-E1 | Seal | Natural 103 From Seals Unlimited Mold No. 3677-A | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

162 S-527-A1 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

163 S-527-A3 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

164 S-527-A5 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

165 S-527-A7 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

166 S-527-A9 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

167 S-527-F1 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Thu 3/21/24 Wed 9/11/24 NA NA 0%

168 S-527-F6 | Left Leaf Miter Post Seal | 103 from SU | Qty. 2 6 mons Tue 9/27/22 Tue 3/21/23 NA NA 0%

169 Fenders 130 days Thu 3/21/24 Wed 9/25/24 NA NA 0%

170 S-555-E1 | Fender | UHMW | Qty. 4 26 wks Thu 3/21/24 Wed 9/25/24 NA NA 0%

171 S-555-C1 | Fender | UHMW | Qty. 4 26 wks Thu 3/21/24 Wed 9/25/24 NA NA 0%

172 S-555-A1 | Fender | UHMW | Qty. 4 26 wks Thu 3/21/24 Wed 9/25/24 NA NA 0%

173 S-564-A5 | Rubber | ASTM D4020 UHMW-PE | Qty. 8 26 wks Thu 3/21/24 Wed 9/25/24 NA NA 0%

174 Butterfly Valves 130 days Thu 3/21/24 Wed 9/25/24 NA NA 0%

175 M-501-E5 | Butterfly Valve | Qty. 4 (2 per leaf) 26 wks Thu 3/21/24 Wed 9/25/24 NA NA 0%

176 Subcontracts 140 days Thu 3/21/24 Wed 10/9/24 NA NA 0%

177 Walkways and Handrails 140 days Thu 3/21/24 Wed 10/9/24 NA NA 0%

180 Operations 510.4 days Mon 10/30/23 Thu 11/6/25 NA NA 0%

181 Fabrication 277.3 days Fri 5/17/24 Tue 6/24/25 NA NA 0%

182 Burn/Prep/Cut 151.4 days Fri 5/17/24 Wed 12/25/24 NA NA 0%

183 Vertical Beams 98 days Fri 5/17/24 Mon 10/7/24 NA NA 0%

184 S-515-A8 Vertical Beam 98 days Fri 5/17/24 Mon 10/7/24 NA NA 0%

190 S-515-A5 Vertical Beam 48 days Mon 6/17/24 Fri 8/23/24 NA NA 0%

196 S-515-A3 Vertical Beam 4 days Fri 5/17/24 Thu 5/23/24 NA NA 0%

200 S-515-A1 Vertical Beam 6 days Fri 5/17/24 Tue 5/28/24 NA NA 0%

204 S-516-A9 Vertical Beam 6 days Fri 5/17/24 Tue 5/28/24 NA NA 0%

208 S-516-A7 Vertical Beam 6 days Fri 5/17/24 Tue 5/28/24 NA NA 0%

212 S-516-A5 Vertical Beam 6 days Thu 5/23/24 Mon 6/3/24 NA NA 0%

216 S-516-A3 Vertical Beam 6 days Thu 5/23/24 Mon 6/3/24 NA NA 0%

220 S-516-A1 Vertical Beam 6 days Thu 5/23/24 Mon 6/3/24 NA NA 0%

224 Vertical Girders 44 days Mon 8/19/24 Mon 10/21/24 NA NA 0%

240 Intercostals 7 days Mon 10/21/24 Wed 10/30/24 NA NA 0%

244 S-530-A1 | Quoin Post Assembly 3.8 days Wed 10/30/24 Mon 11/4/24 NA NA 0%

255 S-525-A1 | Miter Post Assembly 36 days Tue 9/17/24 Wed 11/6/24 NA NA 0%

265 S-501-E1 | Top Girder 3.2 days Mon 11/4/24 Thu 11/7/24 NA NA 0%

273 S-505-E1 | Bottom Girder 3 days Thu 11/7/24 Tue 11/12/24 NA NA 0%

279 Skin Plates 3.2 days Tue 11/12/24 Mon 11/18/24 NA NA 0%

287 S-561-E1 | Gudgeon Hood 1.9 days Thu 11/14/24 Mon 11/18/24 NA NA 0%

299 S-562-E1 | Lifting Assembly 2 days Fri 11/15/24 Tue 11/19/24 NA NA 0%

307 S-546-D1 | Right Miter Guide 1 day Mon 11/18/24 Tue 11/19/24 NA NA 0%

312 S-545-E1 | Left Miter Guide 0.6 days Tue 11/19/24 Wed 11/20/24 NA NA 0%

316 S-547-D1 | Right Miter Block 1.9 days Wed 11/20/24 Thu 11/21/24 NA NA 0%

322 S-547-A1 | Left Miter Block 0.7 days Fri 11/22/24 Fri 11/22/24 NA NA 0%

325 S-548-D1 | Quoin Block 1.2 days Fri 11/22/24 Mon 11/25/24 NA NA 0%

331 S-548-A1 | Quoin Block 0.4 days Mon 11/25/24 Tue 11/26/24 NA NA 0%

334 S-566-F1 | Sill Bearing Assembly 2.4 days Tue 11/26/24 Mon 12/2/24 NA NA 0%

340 S-564-A7 | Thrust Plate | Qty. 2 3 days Mon 12/2/24 Thu 12/5/24 NA NA 0%

341 S-560-E1 | Operating Strut 2.4 days Thu 12/5/24 Tue 12/10/24 NA NA 0%

347 S-567-A1 | Trash Rack 2.8 days Tue 12/10/24 Thu 12/12/24 NA NA 0%

354 S-502-A1 | Diagonal Assembly 5.4 days Thu 12/12/24 Fri 12/20/24 NA NA 0%

364 Brackets 0.4 days Fri 12/20/24 Fri 12/20/24 NA NA 0%

367 Gusset Plates 0.4 days Fri 12/20/24 Wed 12/25/24 NA NA 0%

370 Filler Plates 0.4 days Wed 12/25/24 Wed 12/25/24 NA NA 0%

373 Fit-Up 213.3 days Thu 5/23/24 Fri 3/28/25 NA NA 0%

374 Vertical Beams 29 days Thu 5/23/24 Fri 7/5/24 NA NA 0%

384 Vertical Girders 10 days Mon 10/21/24 Mon 11/4/24 NA NA 0%

387 Intercostals 75 days Thu 10/24/24 Thu 2/13/25 NA NA 0%

391 S-530-A1 | Quoin Post Assembly 12 days Wed 10/30/24 Fri 11/15/24 NA NA 0%

396 S-525-A1 | Miter Post Assembly 9 days Mon 11/4/24 Fri 11/15/24 NA NA 0%

400 S-501-E1 | Top Girder 5 days Fri 11/15/24 Fri 11/22/24 NA NA 0%

401 S-505-E1 | Bottom Girder 5 days Fri 11/22/24 Tue 12/3/24 NA NA 0%

402 S-561-E1 | Gudgeon Hood 2 days Mon 11/18/24 Wed 11/20/24 NA NA 0%

403 S-562-E1 | Lifting Assembly 2 days Wed 11/20/24 Fri 11/22/24 NA NA 0%

404 S-546-D1 | Right Miter Guide 6 days Fri 11/22/24 Wed 12/4/24 NA NA 0%

405 S-545-E1 | Left Miter Guide 6 days Wed 12/4/24 Thu 12/12/24 NA NA 0%

406 S-547-D1 | Right Miter Block 6 days Thu 12/12/24 Fri 12/20/24 NA NA 0%

407 S-547-A1 | Left Miter Block 6 days Fri 12/20/24 Thu 1/2/25 NA NA 0%

408 S-548-D1 | Quoin Block 5 days Thu 1/2/25 Thu 1/9/25 NA NA 0%

409 S-548-A1 | Quoin Block 5 days Thu 1/9/25 Thu 1/16/25 NA NA 0%

410 S-566-F1 | Sill Bearing Assembly | Qty. 2 21 days Thu 1/16/25 Fri 2/14/25 NA NA 0%

411 S-564-A7 | Thrust Plate | Qty. 2 5 days Fri 2/14/25 Fri 2/21/25 NA NA 0%

412 S-560-E1 | Operating Strut 20 days Fri 2/14/25 Fri 3/14/25 NA NA 0%

9/27

2/14

5/17

6/23

12/20

1/31

1/31

3/21

2/13

3/21

9/27

9/27

9/27

9/27

2/25

3/12

0 - Mike,0 - Trisha

0 - Mike,0 - Trisha

12/20

1/31

3/21

242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 91113151719212325271 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 8101214161820222426281 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 8101214161820222426282 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 91113151719212325271 3 5 7 911131517192123252729

October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

Project: 12324-C Black Rock Lo

Date: Fri 3/1/24

RFP Note: This schedule should be treated as a reference. Dates have not been actualized and only the durations are relevant.

RFP Note: This schedule should be treated as a reference. Dates have not been actualized and only the durations are relevant.

h5tddswd Highlight h5tddswd Highlight

ID Task

Mode

Task Name Duration Start Finish Actual Start Actual Finish % Complete

413 S-567-A1 | Trash Rack 30 days Fri 2/14/25 Fri 3/28/25 NA NA 0%

414 S-502-A1 | Diagonal Assembly 20 days Fri 2/14/25 Fri 3/14/25 NA NA 0%

415 S-540-E1 | Downstream Bracket 20 days Fri 2/14/25 Fri 3/14/25 NA NA 0%

416 S-541-E1 | Upstream Bracket 20 days Fri 2/14/25 Fri 3/14/25 NA NA 0%

417 Welding 240.3 days Wed 5/29/24 Mon 5/12/25 NA NA 0%

418 Vertical Beams 40 days Wed 5/29/24 Thu 7/25/24 NA NA 0%

428 Vertical Girders 21 days Mon 11/4/24 Thu 12/5/24 NA NA 0%

431 Intercostals 60 days Mon 12/2/24 Thu 2/27/25 NA NA 0%

435 S-530-A1 | Quoin Post Assembly 29 days Mon 11/4/24 Tue 12/17/24 NA NA 0%

440 S-525-A1 | Miter Post Assembly 8 days Thu 11/7/24 Tue 11/19/24 NA NA 0%

444 S-501-E1 | Top Girder 20 days Fri 11/22/24 Thu 12/26/24 NA NA 0%

445 S-505-E1 | Bottom Girder 20 days Tue 12/3/24 Fri 1/3/25 NA NA 0%

446 S-561-E1 | Gudgeon Hood 15 days Wed 11/20/24 Fri 12/13/24 NA NA 0%

447 S-562-E1 | Lifting Assembly 16 days Fri 11/22/24 Wed 12/18/24 NA NA 0%

448 S-546-D1 | Right Miter Guide 10 days Wed 12/4/24 Wed 12/18/24 NA NA 0%

449 S-545-E1 | Left Miter Guide 10 days Thu 12/12/24 Mon 12/30/24 NA NA 0%

450 S-547-D1 | Right Miter Block 10 days Fri 12/20/24 Wed 1/8/25 NA NA 0%

451 S-547-A1 | Left Miter Block 10 days Thu 1/2/25 Thu 1/16/25 NA NA 0%

452 S-548-D1 | Quoin Block 10 days Thu 1/9/25 Thu 1/23/25 NA NA 0%

453 S-548-A1 | Quoin Block 10 days Thu 1/16/25 Thu 1/30/25 NA NA 0%

454 S-563-A1 | Sill Bearing Assembly | Qty. 2 20 days Fri 2/14/25 Fri 3/14/25 NA NA 0%

455 S-564-A7 | Thrust Plate | Qty. 2 5 days Fri 2/21/25 Fri 2/28/25 NA NA 0%

456 S-560-E1 | Operating Strut 20 days Fri 3/14/25 Fri 4/11/25 NA NA 0%

457 S-567-A1 | Trash Rack 30 days Fri 3/28/25 Mon 5/12/25 NA NA 0%

458 S-502-A1 | Diagonal Assembly 20 days Fri 3/14/25 Fri 4/11/25 NA NA 0%

459 S-540-E1 | Downstream Bracket 20 days Fri 3/14/25 Fri 4/11/25 NA NA 0%

460 S-541-E1 | Upstream Bracket 20 days Fri 3/14/25 Fri 4/11/25 NA NA 0%

461 Drilling 230.3 days Thu 7/25/24 Tue 6/24/25 NA NA 0%

462 Skin Plates 20 days Thu 12/5/24 Tue 1/7/25 NA NA 0%

463 Vertical Beams 20 days Thu 7/25/24 Thu 8/22/24 NA NA 0%

464 Vertical Girders 25 days Thu 12/5/24 Tue 1/14/25 NA NA 0%

465 Top Girder 25 days Thu 12/26/24 Fri 1/31/25 NA NA 0%

466 Bottom Girder 20 days Fri 1/3/25 Fri 1/31/25 NA NA 0%

467 Miter Post 15 days Fri 1/31/25 Fri 2/21/25 NA NA 0%

468 Quoin Post 15 days Fri 2/21/25 Fri 3/14/25 NA NA 0%

469 Seals 15 days Mon 5/12/25 Tue 6/3/25 NA NA 0%

470 Fenders 15 days Tue 6/3/25 Tue 6/24/25 NA NA 0%

471 Machining 354.1 days Mon 10/30/23 Thu 3/27/25 NA NA 0%

472 S-520-A3 | Diagonal | Qty. 8 5.6 days Fri 4/19/24 Fri 4/26/24 NA NA 0%

475 S-520-A6 | Diagonal Plate | Qty. 8 4 days Mon 6/17/24 Fri 6/21/24 NA NA 0%

478 S-520-A9 | Diagonal Threaded End | Qty. 4 6 days Tue 7/30/24 Wed 8/7/24 NA NA 0%

481 S-520-E3 | Diagonal Connecting Plate | Qty. 8 1 day Fri 3/14/25 Mon 3/17/25 NA NA 0%

483 S-520-E5 | Diagonal Keeper Plate | Qty. 8 0.4 days Fri 3/14/25 Mon 3/17/25 NA NA 0%

485 S-520-E7 | Diagonal Connecting Plate | Qty. 8 1 day Fri 3/14/25 Mon 3/17/25 NA NA 0%

487 S-521-E3 | Diagonal Connecting Plate | Qty. 16 1 day Fri 3/14/25 Mon 3/17/25 NA NA 0%

489 S-521-A3 | Diagonal Lock | Qty. 8 7 days Fri 4/19/24 Tue 4/30/24 NA NA 0%

492 S-522 | Gudgeon Plates | Qty. 2 1.6 days Tue 7/16/24 Wed 7/17/24 NA NA 0%

501 S-561-A9 | Gudgeon Pin | Qty. 2 3.6 days Fri 5/17/24 Wed 5/22/24 NA NA 0%

504 S-535-A1 | Pintle | Qty. 2 15 days Wed 9/11/24 Wed 10/2/24 NA NA 0%

507 S-535-A4 | Pintle Bushing | Qty. 2 14 days Tue 8/13/24 Tue 9/3/24 NA NA 0%

510 S-536-A1 | Pintle Socket | Qty. 2 19 days Tue 7/30/24 Fri 8/23/24 NA NA 0%

513 S-537-A1 | Pintle Base | Qty. 2 20 days Mon 8/12/24 Mon 9/9/24 NA NA 0%

516 S-537-E6 | Turned Bolt | Qty. 16 16 hrs Mon 11/18/24 Tue 11/19/24 NA NA 0%

517 S-545-E1 | Left Miter Guide | Qty. 2 131.1 days Mon 10/30/23 Wed 5/8/24 NA NA 0%

527 S-546-D1 | Right Miter Guide | Qty. 2 0.6 days Fri 5/17/24 Fri 5/17/24 NA NA 0%

529 S-547-D1 | Right Miter Block | Qty. 2 3.6 days Fri 5/17/24 Wed 5/22/24 NA NA 0%

533 S-547-A1 | Left Miter Block | Qty. 2 2.2 days Wed 5/22/24 Fri 5/24/24 NA NA 0%

536 S-548-D1 | Quoin Block | Qty. 2 3.8 days Tue 7/30/24 Fri 8/2/24 NA NA 0%

541 S-548-A1 | Quoin Block | Qty. 1 2.8 days Tue 7/30/24 Thu 8/1/24 NA NA 0%

544 S-560-E1 | Operating Strut | Qty. 2 8.4 days Fri 3/14/25 Thu 3/27/25 NA NA 0%

547 S-561-E1 | Gudgeon Hood Assembly | Qty. 2 15 days Fri 12/13/24 Wed 1/8/25 NA NA 0%

552 S-562-E1 | Lifting Assembly | Qty. 2 2 days Wed 12/18/24 Fri 12/20/24 NA NA 0%

554 S-563-A1 | Seal Plates | Qty. 2 2 days Fri 3/14/25 Tue 3/18/25 NA NA 0%

556 S-564-F7 | Plate | Drilling 8 hrs Fri 12/20/24 Wed 12/25/24 NA NA 0%

557 S-565-F8 | Anchorage Link Assembly 24.8 days Tue 7/30/24 Tue 9/3/24 NA NA 0%

563 Paint 95 days Tue 6/24/25 Thu 11/6/25 NA NA 0%

564 Left Leaf Miter Gate Assembly 9.5 wks Tue 6/24/25 Fri 8/29/25 NA NA 0%

565 Right Leaf Miter Gate Assembly 9.5 wks Fri 8/29/25 Thu 11/6/25 NA NA 0%

566 Shipping 74 days Thu 11/6/25 Wed 2/25/26 NA NA 0%

567 Planning Delivery 1 14 days Thu 11/6/25 Wed 11/26/25 NA NA 0%

568 Shipping Delivery 1 60 days Wed 11/26/25 Wed 2/25/26 NA NA 0%

569 Field 5 days Thu 3/21/24 Fri 3/29/24 NA NA 0%

571 Job Documentation 1 day Tue 6/24/25 Wed 6/25/25 NA NA 0%

573 Closeout 11 days Wed 2/25/26 Thu 3/12/26 NA NA 0%

242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 91113151719212325271 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 8101214161820222426281 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 8101214161820222426282 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 911131517192123252729312 4 6 810121416182022242628302 4 6 810121416182022242628301 3 5 7 9111315171921232527291 3 5 7 911131517192123252729312 4 6 810121416182022242628301 3 5 7 91113151719212325271 3 5 7 911131517192123252729

October 2022 November 2022 December 2022 January 2023 February 2023 March 2023 April 2023 May 2023 June 2023 July 2023 August 2023 September 2023 October 2023 November 2023 December 2023 January 2024 February 2024 March 2024 April 2024 May 2024 June 2024 July 2024 August 2024 September 2024 October 2024 November 2024 December 2024 January 2025 February 2025 March 2025 April 2025 May 2025 June 2025 July 2025 August 2025 September 2025 October 2025 November 2025 December 2025 January 2026 February 2026 March 2026

Task Split Milestone Summary Project Summary Inactive Task Inactive Milestone Inactive Summary Manual Task Duration-only Manual Summary Rollup Manual Summary Start-only Finish-only External Tasks External Milestone Deadline Progress Manual Progress

Project: 12324-C Black Rock Lo

Date: Fri 3/1/24

RFP Note: This schedule should be treated as a reference. Dates have not been actualized and only the durations are relevant.

RFP Note: This schedule should be treated as a reference. Dates have not been actualized and only the durations are relevant.