Abstract IGE adjusted_Sodus FY22.xls

XLS spreadsheet 61 KB Posted

Attached to
Little Sodus West Pier Repair
Solicitation number
W912P422B0007
Issued by

About this file

This document contains bid responses for a federal solicitation to repair the Little Sodus West Pier. The U.S. Army Corps of Engineers, Buffalo District issued solicitation number W912P422B0007 seeking a firm-fixed price contract for encapsulating approximately 600 linear feet of an existing timber crib and sheet pile pier with new sheet pile walls and a concrete cap. Bids were received from nine contractors providing unit pricing for line items such as mobilization, record drawings, removals, granular fill, sheet pile installation, concrete caps, and ladders. Pricing ranged from $2.4 million to $6.5 million to complete the work, which includes clearing areas for new sheet piles, removing disconnected existing materials, installing new sheet piles connected by wales and tiebacks, backfilling with granular fill, and pouring a new concrete cap with safety ladders and stairs. The solicitation is for a full and open competition with award going to the lowest priced technically acceptable offer.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidder 1-3

W912P4-22-B-0007response to this solicitation.
Issuing OfficeTyrone Palaganase
Department Of The ArmyContracting Officer
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
CRANE HOGANDean MarineDYMLES
FY 22 Little SodusA. HIRED LABORSPENCERPORT, NYMt. Clemens, MILOCKPORT, NY
Fairport, NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of Bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 761,675.28$ 95,000.00$ 477,836.27$ 616,000.00
2Record (As-built) Draw1JA$ 58,825.64$ 4,400.00$ 25,089.13$ 7,000.00
3Removals Land Side of Pier1JA$ 55,710.58$ 60,000.00$ 33,449.43$ 108,000.00
4Removal of Existing Sheet Pile184LF$ 660.45$ 121,522.80$ 300.00$ 55,200.00$ 947.97$ 174,426.00$ 386.80$ 71,171.20
5Removal of Existing Concrete Cap600TN$ 180.70$ 108,420.00$ 71.00$ 42,600.00$ 212.06$ 127,236.00$ 41.40$ 24,840.00
6Granular Fill Stone2,000TN$ 68.90$ 137,800.00$ 60.00$ 120,000.00$ 57.35$ 114,700.00$ 76.25$ 152,500.00
7Steel Sheet Pile Installation20200SF$ 113.25$ 2,287,650.00$ 78.58$ 1,587,316.00$ 76.75$ 1,550,350.00$ 82.80$ 1,672,560.00
8Cast in place Con Cap665CY$ 1,637.10$ 1,088,671.50$ 620.00$ 412,300.00$ 862.33$ 573,449.00$ 1,140.00$ 758,100.00
9Steel Ladders6EA$ 9,505.80$ 57,034.80$ 3,000.00$ 18,000.00$ 3,089.61$ 18,538.00$ 7,625.00$ 45,750.00
Total Estimated Amount 1-9$ 4,677,310.60$ 2,394,816.00$ 3,095,073.00$ 3,455,921.20
10Removal of Existing Sheet Pile30LF$ 442.15$ 13,267.50$ 300.00$ 9,000.00$ 581.42$ 17,443.00$ 259.00$ 7,770.00
11Misc Granular Fill Stone50TN$ 51.95$ 2,597.50$ 70.00$ 3,500.00$ 57.35$ 2,868.00$ 88.85$ 4,442.50
12Removal of Existing Sheet Pile15LF$ 442.15$ 6,632.25$ 300.00$ 4,500.00$ 1,744.26$ 26,164.00$ 287.30$ 4,309.50
13Removal of Existing Con Cap100TN$ 181.40$ 18,140.00$ 90.00$ 9,000.00$ 389.83$ 38,983.00$ 6,035.00$ 6,050.00
14Removals Land Side Pier1JA$ 41,177.45$ 29,400.00$ 33,449.43$ 63,800.00
15Granular Fill Stone490TN$ 57.40$ 28,126.00$ 60.00$ 29,400.00$ 57.35$ 28,102.00$ 83.75$ 41,037.50
16Steel Sheet Pile Installation11,200SF$ 103.60$ 1,160,320.00$ 54.80$ 613,760.00$ 77.72$ 870,464.00$ 78.60$ 880,320.00
17Cast in Place Con Cap368CY$ 1,567.50$ 576,840.00$ 620.00$ 228,160.00$ 925.11$ 340,440.00$ 1,170.00$ 430,560.00
Total Estimated Amount 14-17$ 1,806,463.45$ 880,320.00$ 1,272,455.00$ 1,415,717.50
Total Estimated Amount 1-17$ 6,524,408.30$ 3,301,136.00$ 4,452,986.00$ 4,894,210.70
*May contain rounding Errors

Bidder 4-6

W912P4-22-B-0007response to this solicitation.
Issuing OfficeTyrone Palaganase
Department Of The ArmyContracting Officer
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
GLDMKOVILICMARION HILL
FY 22 Little SodusA. HIRED LABORMUSKEGON, MIFRANKLIN, ILNEW BRIGHTON PA
Fairport, NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of Bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 761,675.28$ 771,859.00$ 500,000.00$ 359,200.00
2Record (As-built) Draw1JA$ 58,825.64$ 27,500.00$ 50,000.00$ 35,673.00
3Removals Land Side of Pier1JA$ 55,710.58$ 158,000.00$ 250,000.00$ 197,652.00
4Removal of Existing Sheet Pile184LF$ 660.45$ 121,522.80$ 725.00$ 133,400.00$ 1,000.00$ 184,000.00$ 2,523.00$ 464,232.00
5Removal of Existing Concrete Cap600TN$ 180.70$ 108,420.00$ 124.00$ 74,400.00$ 250.00$ 150,000.00$ 348.00$ 208,800.00
6Granular Fill Stone2,000TN$ 68.90$ 137,800.00$ 54.00$ 108,000.00$ 200.00$ 400,000.00$ 146.00$ 292,000.00
7Steel Sheet Pile Installation20200SF$ 113.25$ 2,287,650.00$ 111.00$ 2,242,200.00$ 135.00$ 2,727.00$ 130.00$ 2,626,000.00
8Cast in place Con Cap665CY$ 1,637.10$ 1,088,671.50$ 1,185.00$ 788,025.00$ 1,000.00$ 665,000.00$ 1,641.00$ 155,850.00
9Steel Ladders6EA$ 9,505.80$ 57,034.80$ 6,168.00$ 37,008.00$ 10,000.00$ 60,000.00$ 25,975.00$ 155,848.00
Total Estimated Amount 1-9$ 4,677,310.60$ 4,340,392.00$ 4,986,000.00$ 5,430,675.00
10Removal of Existing Sheet Pile30LF$ 442.15$ 13,267.50$ 741.00$ 22,230.00$ 1,000.00$ 30,000.00$ 2,523.00$ 75,690.00
11Misc Granular Fill Stone50TN$ 51.95$ 2,597.50$ 54.00$ 2,700.00$ 100.00$ 5,000.00$ 146.00$ 7,300.00
12Removal of Existing Sheet Pile15LF$ 442.15$ 6,632.25$ 1,451.00$ 21,765.00$ 1,000.00$ 15,000.00$ 2,523.00$ 37,845.00
13Removal of Existing Con Cap100TN$ 181.40$ 18,140.00$ 181.00$ 18,100.00$ 250.00$ 25,000.00$ 348.00$ 34,800.00
14Removals Land Side Pier1JA$ 41,177.45$ 56,280.00$ 125,000.00$ 118,932.00
15Granular Fill Stone490TN$ 57.40$ 28,126.00$ 54.00$ 26,460.00$ 100.00$ 49,000.00$ 146.00$ 71,540.00
16Steel Sheet Pile Installation11,200SF$ 103.60$ 1,160,320.00$ 104.00$ 1,164,800.00$ 125.00$ 1,400,000.00$ 130.00$ 1,456,000.00
17Cast in Place Con Cap368CY$ 1,567.50$ 576,840.00$ 986.00$ 362,848.00$ 850.00$ 312,800.00$ 1,641.00$ 603,888.00
Total Estimated Amount 14-17$ 1,806,463.45$ 1,610,388.00$ 1,886,800.00$ 2,250,360.00
Total Estimated Amount 1-17$ 6,524,408.30$ 6,015,575.00$ 6,947,800.00$ 7,836,670.00
*May contain rounding Errors

Bidder 7-9

W912P4-22-B-0007response to this solicitation.
Issuing OfficeTyrone Palaganase
Department Of The ArmyContracting Officer
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
SLATE HILLWDMALONEWINN CORP
FY 22 Little SodusA. HIRED LABORWARNERS, NYHANIBAL, NYLOCKPORT, NY
Fairport, NYB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of Bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 761,675.28$ 175,000.00$ 204,000.00$ 150,000.00
2Record (As-built) Draw1JA$ 58,825.64$ 37,000.00$ 13,300.00$ 10,000.00
3Removals Land Side of Pier1JA$ 55,710.58$ 56,000.00$ 27,000.00$ 25,000.00
4Removal of Existing Sheet Pile184LF$ 660.45$ 121,522.80$ 200.00$ 36,800.00$ 785.00$ 144,440.00$ 450.00$ 82,800.00
5Removal of Existing Concrete Cap600TN$ 180.70$ 108,420.00$ 82.00$ 49,200.00$ 55.00$ 33,000.00$ 50.00$ 30,000.00
6Granular Fill Stone2,000TN$ 68.90$ 137,800.00$ 50.00$ 100,000.00$ 43.00$ 86,000.00$ 37.00$ 74,000.00
7Steel Sheet Pile Installation20200SF$ 113.25$ 2,287,650.00$ 68.00$ 1,373,600.00$ 72.85$ 1,471,570.00$ 70.00$ 1,414,000.00
8Cast in place Con Cap665CY$ 1,637.10$ 1,088,671.50$ 920.00$ 611,800.00$ 624.00$ 414,960.00$ 815.00$ 541,975.00
9Steel Ladders6EA$ 9,505.80$ 57,034.80$ 5,000.00$ 30,000.00$ 5,395.00$ 32,370.00$ 3,000.00$ 18,000.00
Total Estimated Amount 1-9$ 4,677,310.60$ 2,469,400.00$ 2,426,640.00$ 2,345,775.00
10Removal of Existing Sheet Pile30LF$ 442.15$ 13,267.50$ 200.00$ 6,000.00$ 700.00$ 21,000.00$ 450.00$ 13,500.00
11Misc Granular Fill Stone50TN$ 51.95$ 2,597.50$ 50.00$ 2,500.00$ 43.00$ 2,150.00$ 37.00$ 1,850.00
12Removal of Existing Sheet Pile15LF$ 442.15$ 6,632.25$ 200.00$ 3,000.00$ 500.00$ 7,500.00$ 450.00$ 6,750.00
13Removal of Existing Con Cap100TN$ 181.40$ 18,140.00$ 82.00$ 8,200.00$ 55.00$ 5,500.00$ 50.00$ 5,000.00
14Removals Land Side Pier1JA$ 41,177.45$ 22,000.00$ 13,000.00$ 20,000.00
15Granular Fill Stone490TN$ 57.40$ 28,126.00$ 50.00$ 24,500.00$ 43.00$ 21,070.00$ 37.00$ 18,130.00
16Steel Sheet Pile Installation11,200SF$ 103.60$ 1,160,320.00$ 63.00$ 705,600.00$ 70.00$ 784,000.00$ 69.00$ 772,800.00
17Cast in Place Con Cap368CY$ 1,567.50$ 576,840.00$ 920.00$ 338,560.00$ 628.00$ 231,104.00$ 815.00$ 299,920.00
Total Estimated Amount 14-17$ 1,806,463.45$ 1,090,000.00$ 1,049,174.00$ 1,110,850.00
Total Estimated Amount 1-17$ 6,524,408.30$ 3,579,760.00$ 3,511,964.00$ 3,483,725.00
*May contain rounding Errors

File details come from the government source that posted it. Updated .