This document contains bid responses to Solicitation Number W912P421B0007 for road improvements at the Mount Morris Dam Visitor Center. Five contractors submitted bids for the base scope of work including mobilization, record drawings, removals, paving, median replacement, and catch basin installation. Estimated costs ranged from $114,475 to $208,455.53. The solicitation also included three option items for asphalt patching, trench drain installation, and parking lot improvements. Total estimated costs accounting for both base work and options ranged from $174,275 to $305,458.26. Keeler Construction provided the apparent low bid at $174,275. The bid responses include the type of bid security provided by each contractor and their acknowledgment of any addenda to the solicitation. The work is to be completed for the U.S. Army Corps of Engineers Buffalo District.

View the file

Other files

File Type Posted
Amendment 0002.pdf PDF
Amendment1.pdf PDF
Fullsolicitation.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Bidder 1-5

W912P4-21-B-0007response to this solicitation.
Issuing OfficeDate Signed
Department Of The Army
US Army Engineer District, BuffaloO F F E R S
1776 Niagara Street
Buffalo, NY 14207-3199NO. 1NO. 2NO. 3
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROROFFEROR
Keeler ConstructionArmitage ArchitectureConstruction Solutions Group
FY 21 MMD VC RoadA. HIRED LABORAlbion, NYBuffalo, NYSt. Louis
MM, New YorkB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 62,375.21$ 3,000.00$ 7,070.49$ 36,810.00
2Record As built Draw1JA$ 15,171.25$ 5,000.00$ 13,530.90$ 1,810.00
3Removals - Near 402245LF$ 30.36$ 7,438.20$ 45.00$ 11,025.00$ 137.85$ 33,773.53$ 56.11$ 13,746.95
4Paving245LF$ 332.42$ 81,442.90$ 210.00$ 51,450.00$ 485.92$ 119,050.96$ 323.99$ 79,377.55
5Median Replacement1JA$ 16,650.32$ 23,000.00$ 24,728.95$ 32,580.00
6Catch Basin and Pipe Install1JA$ 14,409.82$ 21,000.00$ 10,300.70$ 2,150.00
Total Estimated Amount (Items 1-6)$ 197,487.70$ 114,475.00$ 208,455.53$ 166,474.50
7(Option A) Asphalt Patching1JA$ 757.44$ 3,200.00$ 5,469.73$ 9,050.00
8(Option B) Trench Drain1JA$ 20,415.21$ 24,000.00$ 54,590.27$ 39,000.00
9(Option C) Parking Lot Improvements8,150SF$ 2.65$ 21,597.50$ 4.00$ 32,600.00$ 4.53$ 36,942.72$ 4.50$ 36,675.00
Total Estimated Amount All Options (Items 7-9)$ 42,770.15$ 59,800.00$ 97,002.73$ 85,025.00
Total Estimated Amount All Items (Items 1-9)$ 240,257.85$ 174,275.00$ 305,458.26$ 251,199.50
Apparent Low
O F F E R S
NO. 4NO. 5
Project TitleGOVERNMENT ESTIMATEOFFEROROFFEROR
DmylesLaubacker
FY 21 MMD VC RoadA. HIRED LABORNiagara Falls, NYNiagara Falls, NY
MM, New YorkB. REASONABLE CONTRACTBID SECURITY (type & amount)BID SECURITY (type & amount)BID SECURITY (type & amount)
XX(without profit)Bid bond - 20% of BidBid bond - 20% of bidBid bond - 20% of bid
NUMBER OF ADDENDA ISSUED:C. REASONABLE CONTRACTADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGEDADDENDA ACKNOWLEDGED
(including profit)
ItemEst.UnitEstimatedUnitEstimatedUnitEstimatedUnitEstimated
No.Description of Offered ItemQuantityUnitPriceAmountPriceAmoutPriceAmoutPriceAmout
Bidding Schedule
Schedule A
1Mobilization and Demobilization1JA$ 62,375.21$ 11,573.00$ 7,000.00
2Record As built Draw1JA$ 15,171.25$ 3,560.00$ 3,500.00
3Removals - Near 402245LF$ 30.36$ 7,438.20$ 75.30$ 18,448.50$ 100.00$ 24,500.00
4Paving245LF$ 332.42$ 81,442.90$ 249.90$ 61,225.50$ 391.00$ 95,795.00
5Median Replacement1JA$ 16,650.32$ 15,735.00$ 16,700.00
6Catch Basin and Pipe Install1JA$ 14,409.82$ 18,976.00$ 14,245.00
Total Estimated Amount (Items 1-6)$ 197,487.70$ 129,518.00$ 161,740.00
7(Option A) Asphalt Patching1JA$ 757.44$ 1,910.00$ 3,575.00
8(Option B) Trench Drain1JA$ 20,415.21$ 39,780.00$ 29,385.00
9(Option C) Parking Lot Improvements8,150SF$ 2.65$ 21,597.50$ 2.60$ 21,190.00$ 3.50$ 28,525.00
Total Estimated Amount All Options (Items 7-9)$ 42,770.15$ 62,880.00$ 61,485.00
Total Estimated Amount All Items (Items 1-9)$ 240,257.85$ 192,398.00$ 223,225.00