Amendment 0002.pdf
PDF 992 KB Posted
- Attached to
- Mount Morris Dam Visitor Center Road
- Solicitation number
- W912P421B0007
About this file
This solicitation seeks a firm fixed-price construction contract to improve the Mount Morris Dam Visitor Center road. The selected contractor will be awarded the contract to complete the road construction project. Bids are due no later than April 23, 2021 and must be submitted electronically through the Army's File Sharing Service, DOD SAFE. Award will be made to the lowest priced responsive and responsible bidder. The work includes all labor, materials, equipment, and supervision to construct the new visitor center road at Mount Morris Dam in accordance with the specifications. The Department of the Army Corps of Engineers Engineering District Buffalo will administer the contract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Copy of Abstract IGE adjusted_MMD VC.xls | XLS spreadsheet | |
| Amendment1.pdf | ||
| Fullsolicitation.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
The Purpose of this amendment is to Post Questions and answers update Wage Determination and clarify Bid Opening date of 23 April 2021 in Box 13A. 13A supercedes all other dates.
1. CONTRACT ID CODE PAGE OF PAGES
1 5
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code)
X 9B. DATED (SEE ITEM 11)
10-Mar-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
X W912P421B0007
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
08-Apr-2021
CODE
U.S. ARMY ENGINEER DISTRICT, BUFFALO
1776 NIAGARA STREET
BUFFALO NY 14207-3199
W912P4 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 21 13 - INSTRUCTIONS TO BIDDERS
The following have been modified:
INSTRUCTIONS
INSTRUCTION TO BIDDERS
INSTRUCTIONS
Bids: ALL RESPONSES TO THIS ANNOUNCEMENT SHALL BE SUBMITTED E LECTRONICALLY. Hand carried delivery or USPS/UPS/FEDEX delivery of hard copies and or CD-ROMs are not authorized. Facsimile submission is not authorized.
Electronic Proposal Submission is required through the Army’s Electronic File Sharing Service, DOD SAFE (https://safe.apps.mil). The DOD SAFE Application is used to send large files to individuals that would normally be too large to send via email.
There are no user accounts for SAFE. Authentication is handled via email. Anyone has access to DOD SAFE, and the application is available for use by anyone. The SAFE “Getting Started Guide” has information on how to utilize the system (https://safe.apps.mil/about.php).
As this is a public bid opening, a call in number will be provided. Please call in on at the time the bids are due.
1-844-800-2712
CODE 199-784-0308
1. Instructions for uploading are as follows:
a. Send an email to the Contracting Officer and Contract Specialist to receive the link to drop off your bid. This will need to be completed WITHIN five (5) days of the proposal due date, but no later than one day prior to the proposal due date.
1. Walter Kamad, Contracting Officer at Walter.Kamad@usace.army.mil
2. Kenneth Mackkay, Contract Specialist at kenneth.e.mackay@usace.army.mil
b. You will receive an email with the link to submit your drop-off.
c. Short Note to the Recipients: Click the Add Files or Drag and Drop your files. For file description, enter W912P421B0007-FIRMNAME.
d. Click Upload button to send documents.
e. Guest users will need to check their email to verify their email address before the recipients will be notified. No additional action is required by CAC users.
File Size Limitations: Offerors are advised to follow the DOD SAFE instructions for uploading files. DOD SAFE supports delivery up to 8GB. If needed, Offerors are advised to break the files down into smaller sections in order to upload it to the system.
In such cases, please divide the sections as logically as possible and be sure to clearly name the files as specified below.
File Naming Convention: To ensure your submission is received and processed appropriately, it is important that interested parties CAREFULLY ensure their electronic files adhere to the following naming convention:
• W912P421B0007-FIRMNAME-Bid
• W912P421B0007-FIRMNAME-Amendments
W912P421B0007-FIRMNAME-Bid Bonds
Each file name shall begin with the solicitation number followed by the firm’s name and a brief file description. Please see examples above.
File Organization: Although hard copies are not accepted, each file shall be clearly indexed, and logically assembled. Font size shall be 10 or larger.
Upload Completion & Deadline: Interested parties shall submit responses no later than the date specified on the solicitation document. The time & date of bid receipt will be the upload completion / delivery time & date recorded within DOD SAFE site. Do not assume that electronic submission will occur instantaneously. Large files (e.g. 10MB or more) will take some time to upload. Offerors should time their upload effort with prudence by not waiting until the last few minutes—this will allow for unexpected delays in the transmittal process. Bidders are encouraged to keep a copy of the upload confirmation for their record. Submissions after the deadline will be considered late and will be processed in accordance with FAR 14.304.
Electronic Files: Files shall be in their native format (i.e. doc, xls, ppt, etc.), or if in pdf format, shall be in searchable text. Text and graphics portfolios of the electronic copies shall be in a format readable by Microsoft Office or Adobe applications. Data submitted in a spreadsheet format shall be readable by MS Excel (all cells and formulas should be unlocked).
2. INTENT
The intent of this solicitation is to award one (1) firm fixed-price construction contract for the FY21 MMD VC Road requirement.
3. BASIS OF SELECTION OF AWARD
A. Award shall be made to the lowest priced bidder who is found to be responsive and responsible.
See FAR Subpart 9.1, Responsible Prospective Contractors and FAR Provision 52.214-19, Contract Award—Sealed Bidding— Construction, for more information.
B. In accordance with FAR Provision 52.217-5, the Government intends to evaluate bids for award purposes by adding the total price for all options to the total price for the basic requirement.
4. SITE VISIT
A. A Formal site vist is planned at Mt. Morris Dam on Tuesday 23 March 2021 at 10:00am ET. If you are not able to join please call in at
Telephone Number : 1-844-800-2712
CODE 199-784-0308
5. REGISTRATION IN SAM
A. The System for Award Management (SAM) is the Government’s online database of federal contractors.
Contractors self-register in SAM at the website www.sam.gov. Registration is free to all users.
B. In accordance with FAR Provision 52.204-7 SYSTEM FOR AWARD MANAGEMENT, a bidder must be registered in SAM when submitting an offer and must continue to be registered until time of award, during performance, and through final payment of any contract.
C. Bidders who are not currently registered in SAM with the NAICS Code that is indicated in Block 10, at the front of this Solicitation, are encouraged to start the registration process as soon as possible to ensure that it is complete prior to submission of any bid.
D. See FAR Provision 52.204-7 for more information.
6. REQUESTS FOR INFORMATION
A. Questions/Inquiries. All questions pertaining to this requirement shall be submitted in writing no later than, 6 April 2021, 10 A.M. Eastern Time. The offeror shall put the solicitation number located in Block 1 of the SF 1442 followed by QUESTIONS in the subject line of the email. All questions received after the above date and time WILL NOT BE ANSWERED.
B. Questions shall be submitted too:
a. Walt Kamad, Contracting Officer at Walt. Kamad@usace.army.mil
b. Kenneth Mackay, Contract Specialist at kenneth.e.mackay@usace.army.mil
c. Once all inquiries are compiled and addressed, the questions and answers will be generated as an amendment and posted to the beta.sam.gov website for all interested parties to view/acknowledge to be sent in with their submission prior to the closing date. If additional time is needed for submission, this extension will be executed on the same amendment as the questions and answers amendment.
7. SUBMISSION OF BIDS
A. All Bidders are reminded to complete and submit with your bid all FAR and DFARS Provisions related to Representations and Certifications.
B. Bidders shall complete and submit any additional full text certifications that are included in the solicitation. An offeror may also complete the certifications at https:// www.sam.gov in lieu of completing the representations and certifications in this solicitation provided that all the FAR and DFARS certifications contained in the solicitation have been completed on line.
C. All Bidders shall be registered at https://www.sam.gov with the NAICS code that is shown on the front page of the solicitation prior to contract award.
D. Remember to fill in and sign the Standard Form 1442, from the front of the Solicitation, before submitting your bid.
E. Bids must be received electronically at the DoD safe address reflected in the Section 00 21 13, Instructions paragraph of this solicitation, by the date and time indicated on page 1, Block 13.
8. BID OPENING
A public Bid Opening will be conducted via teleconference, on 23 April 2021 at 12pm ET. at the date and time indicated for receipt of bids/offers in Box 13 of the Standard Form 1442 at the front of this solicitation. The Bid Opening will be broadcast via live audio telephone conference.
Interested parties may access the conference by calling one of the following numbers and entering the access code when prompted. Callers may log into the conference up to 5 minutes before the stated time.
W912P421R0007
AUDIO CONFERENCE ACCESS INFORMATION:
USA Toll-Free: 888-675-2535 USA Caller Paid/International Toll:
215-446-0145 ACCESS
CODE: 477-6889
SECURITY CODE: 1234
9. FACSIMILE BIDS/OFFERS NOT ACCEPTED
Facsimile bids/offers, modifications thereto, or cancellations of bid/offers will not be accepted.
10. AMENDMENTS
Acknowledgement of each amendment by the Bidder must be made in the space provided on the SF 1442, or by returning a signed copy of the amendment by the time set for receipt of bids. Explanations or instructions given in a form other than an amendment to the solicitation shall not be binding. Questions (on a non-attribution basis) and answers shall be furnished to all prospective Bidders via the website. For security reasons all potential Bidders, plan rooms and printing companies are required to register in SAM at www.sam.gov.
NOTE: Failure to comply with the above instructions may result in an offeror not being eligible for ard.
(End of Summary of Changes)
4/8/2021 beta.SAM.gov | Search https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 1/15
"General Decision Number: NY20210030 04/02/2021
Superseded General Decision Number: NY20200030
State: New York
Construction Types: Building, Heavy and Highway
County: Livingston County in New York.
BUILDING CONSTRUCTION PROJECTS (does not include residential construction consisting of single family homes and apartments up to and including 4 stories), HEAVY AND HIGHWAY CONSTRUCTION
PROJECTS
Note: Under Executive Order (EO) 13658, an hourly minimum wage of $10.95 for calendar year 2021 applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2015. If this contract is covered by the EO, the contractor must pay all workers in any classification listed on this wage determination at least $10.95 per hour (or the applicable wage rate listed on this wage determination, if it is higher) for all hours spent performing on the contract in calendar year 2021. If this contract is covered by the EO and a classification considered necessary for performance of work on the contract does not appear on this wage determination, the contractor must pay workers in that classification at least the wage rate determined through the conformance process set forth in 29 CFR 5.5(a)(1)(ii) (or the EO minimum wage rate,if it is higher than the conformed wage rate). The EO minimum wage rate will be adjusted annually. Please note that this EO applies to the above-mentioned types of contracts entered into by the federal government that are subject to the Davis-Bacon Act itself, but it does not apply to contracts subject only to the Davis-Bacon Related Acts, including those set forth at 29 CFR 5.1(a)(2)-(60). Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Modification Number Publication Date 0 01/01/2021 1 03/12/2021 2 04/02/2021
ASBE0026-003 06/01/2020
Rates Fringes
ASBESTOS WORKER/HEAT & FROST
INSULATOR
(Includes the application of all insulating materials, protective coverings, coatings, and finishes to all types of mechanical systems. Also, the application of firestooping material openings and penetrations in walls, floors, ceilings, curtain walls and all lead abatement).....$ 32.26 24.11 https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 2/15
HAZARDOUS MATERIAL HANDLER
Duties limited to Preparation; wetting;
stripping; removal;
scrapping; vacuuming;
bagging; and disposing of all insulation materials, whether they contain asbestos or not, from mechanical systems..........$ 32.26 24.11
BOIL0007-001 01/01/2017
Rates Fringes
BOILERMAKER......................$ 33.00 28.15
BRNY0003-009 07/01/2020
ROCHESTER CHAPTER
Rates Fringes
BUILDING CONSTRUCTION
BRICKLAYERS, STONE MASONS,
PLASTERERS, CEMENT MASONS,
POINTER, CLEANER AND
CAULKERS....................$ 30.41 23.39
MARBLE, TILE & TERRAZZO
WORKERS.....................$ 29.94 18.71
MARBLE, TILE AND TERRAZZO
FINISHERS...................$ 24.98 15.70
CEMENT MASON/CONCRETE FINISHER
HEAVY/HIGHWAY CONSTRUCTION
CEMENT MASONS..............$ 31.58 21.90
CARP0276-007 07/01/2020
Rates Fringes
Carpenters (HEAVY & HIGHWAY
CONSTRUCTION)....................$ 32.18 23.35
Carpenters, including Drywall Hanging (BUILDING CONSTRUCTION
Entire County, excluding the Towns of Phelps, Seneca and Geneva)..........................$ 30.05 22.19
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day.
CARP1163-001 07/01/2014
Rates Fringes
Carpenters:
BUILDING CONSTRUCTION
Piledrivers................$ 29.00 18.89
HEAVY & HIGHWAY
CONSTRUCTION
Piledrivers................$ 24.47 13.91 https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 3/15
Diver (Dry Day)............$ 26.48 14.36 Diver (Wet Day)............$ 61.25 14.36 Diver Tender...............$ 24.72 16.95 Piledrivers................$ 29.00 18.89
ELEC0086-002 06/01/2020
Rates Fringes
ELECTRICIAN......................$ 34.70 5.25%+24.11
ELEC1249-003 05/04/2020
Rates Fringes
ELECTRICIAN (LINE
CONSTRUCTION: LIGHTING AND
TRAFFIC SIGNAL Including any and all Fiber Optic Cable necessary for Traffic Signal Systems, Traffic Monitoring systems and Road Weather information systems) Flagman.....................$ 27.72 6.75%+33.90 Groundman (Truck Driver)....$ 36.96 6.75%+33.90 Groundman Truck Driver (tractor trailer unit)......$ 39.27 6.75%+33.90 Lineman & Technician........$ 46.20 6.75%+33.90 Mechanic....................$ 36.96 6.75%+33.90
FOOTNOTE:
a. New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, plus President's Day, Good Friday, Decoration Day, Election Day for the President of the United States and Election Day for the Governor of the State of New York, provided the employee works the day before or the day after the holiday.
ELEC1249-004 05/04/2020
Rates Fringes
ELECTRICIAN (Line Construction) Overhead and underground distribution and maintenance work and all overhead and underground transmission line work including any and all fiber optic ground wire, fiber optic shield wire or any other like product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities :
Flagman....................$ 32.10 6.75%+33.90 Groundman digging machine operator...................$ 48.15 6.75%+33.90 Groundman truck driver (tractor trailer unit).....$ 45.48 6.75%+33.90 https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 4/15
Groundman Truck driver.....$ 42.80 6.75%+33.90 Lineman and Technician.....$ 53.50 6.75%+33.90 Mechanic...................$ 42.80 6.75%+33.90 Substation:
Cable Splicer..............$ 58.85 6.75%+33.90 Flagman....................$ 32.10 6.75%+33.90 Ground man truck driver....$ 42.80 6.75%+33.90 Groundman digging machine operator...................$ 48.15 6.75%+33.90 Groundman truck driver (tractor trailer unit).....$ 45.48 6.75%+33.90 Lineman & Technician.......$ 53.50 6.75%+33.90 Mechanic...................$ 42.80 6.75%+33.90 Switching structures;
railroad catenary installation and maintenance, third rail type underground fluid or gas filled transmission conduit and cable installations (including any and all fiber optic ground product by any other name manufactured for the dual purpose of ground fault protection and fiber optic capabilities), pipetype cable installation and maintenance jobs or projects, and maintenance bonding of rails; Pipetype cable installation Cable Splicer..............$ 60.30 6.75%+33.90 Flagman....................$ 32.89 6.75%+33.90 Groundman Digging Machine Operator...................$ 49.34 6.75%+33.90 Groundman Truck Driver (tractor-trailer unit).....$ 46.60 6.75%+33.90 Groundman Truck Driver.....$ 43.86 6.75%+33.90 Lineman & Technician.......$ 54.82 6.75%+33.90 Mechanic...................$ 43.86 6.75%+33.90
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Presidents' Day, Memorial Day, Good Friday, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, and Election Day for the President of the United States and Election Day for the Governor of New York State, provided the employee works two days before or two days after the holiday.
* ELEC1249-008 01/03/2021
Rates Fringes
ELECTRICIAN (Line Construction)
TELEPHONE, CATV
FIBEROPTICS CABLE AND
EQUIPMENT
Cable splicer..............$ 34.78 3%+5.14 Groundman..................$ 17.50 3%+5.14 Installer Repairman-https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 5/15
Teledata Lineman/Technician- Equipment Operator.........$ 33.01 3%+5.14 Tree Trimmer................$ 27.36 3%+9.98
a. New Year's Day, President's Day, Good Friday, Decoration Day, Independence Day, Labor Day, Veteran's Day, Thanksgiving Day, Day after Thanksgiving, Christmas Day.
ELEV0027-001 01/01/2020
Rates Fringes
ELEVATOR MECHANIC................$ 50.71 34.765+a+b
FOOTNOTE:
a.Vacation: 6%/under 5 years based on regular hourly rate for all hours worked. 8%/over 5 years based on regular hourly rate for all hours worked.
b. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Veterans' Day; Thanksgiving Day; the Friday after Thanksgiving Day; and Christmas Day.
ENGI0832-001 07/01/2018
Rates Fringes
Operating Engineer:
EXCAVATING AND PAVING
GROUP 1....................$ 31.45 27.55+a GROUP 2....................$ 30.98 27.55+a GROUP 3....................$ 30.29 27.55+a GROUP 4....................$ 26.80 27.55+a MASTER MECHANIC............$ 33.45 27.55+a
HEAVY AND HIGHWAY
GROUP 1....................$ 41.51 28.25+a GROUP 2....................$ 40.80 28.25+a GROUP 3....................$ 37.94 28.25+a GROUP 4....................$ 45.51 28.25+a GROUP 5....................$ 44.51 28.25+a GROUP 6....................$ 43.51 28.25+a GROUP 7....................$ 42.94 28.25+a
TUNNEL AND SHAFT
GROUP 1....................$ 44.24 28.35+a GROUP 2....................$ 43.02 28.35+a GROUP 3....................$ 40.23 28.35+a GROUP 4....................$ 37.22 28.35+a MASTER MECHANIC............$ 46.65 28.35+a
For EXCAVATION AND PAVING:
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day; Memorial Day; Independence Day; Labor Day; Thanksgiving Day; Christmas Day, regardless of the day of the week on which the holiday may fall, provided the employee works either on the work day immediately preceding the holiday or on the scheduled work day immediately following the holiday.
EXCAVATION AND PAVING CLASSIFICATIONS
GROUP 1: Asphalt paver; automatic fine grader; backhoe https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 6/15
(except tractor mounted, rubber tired); blacktop plant (automated); cableway; caisson auger; central mix concrete plant (automated); cherry picker- over 5 ton capacity;
crane; cranes and derricks (steel erection); dragline; dual drum paver; front end loader (4 cu. yd. and over);
hoist,(Tow or 3 drum); pile driver; power grader with elevation loader attachment; quarry master (or equivalent);
shovel; slip form paver; tractor drawn belt-type loader;
truck crane tunnel shovel; excavator, all purpose hydraulically operated
GROUP 2: Backhoe (tractor mounted, rubber tired); bituminous spreader and mixer; blacktop plant (non automated); boring machine; cage hoist; central mix plant (non automated) and all concrete batching plants; cherry picker, 5 tons and under; compressor (4 or less) exceeding 2000 CFM combined capacity; concrete paver over 16s; concrete pump; crusher;
drill rigs (tractor mounted); front end loader (under 4 cu.
yds); hi- pressure boiler (15 lbs and over); hoist (one drum); Kolman plant loader and similar type loaders;
maintenance engineer; maintenance grease man; mechanical slurry machine; mixer for stabilized base self propelled;
monorail machine; plant engineer; power broom; power grader; pump crete; ready mix concrete plant; road widener;
roller (all above sub-grade); side boom; tractor scraper;
tractor with dozer and or pusher; trencher; winch
GROUP 3: Compressors (4 not to exceed 2000 CFM combined capacity; or 3 or less with more than 1200 CFM but not to exceed 2000 CFM); compressors (any size but subject to other provisions for compressors); dust collectors;
generators; welding machines (4 of any type or combination); concrete pavement spreaders and finishers;
conveyor; drill (core); drill (well); electric pump used in conjunction with well point systems; farm tractor with accessories; fine grade machine; fork lift; gunite machine;
hammers-hydraulic-self propelled; locomotive; post hole digger and post driver; pumps (regardless of motive power, not more than 4 in number not to exceed 20"" in total capacity); submersible electric pumps when used in lieu of well points, tractor with towed accessories; vibratory compactor; vibro tamp; well point
GROUP 4: Compressor (any size, but subject to other provisions for compressors); dust collectors; generators;
welding machines (3 or less of any type or combination);
concrete mixer (16s and under), concrete saw-self propelled; fireman; form tamper; mulching machine; power heaterman; pumps regardless of motive power no more than 3 in number not to exceed 12"" in total capacity; revinius widener; steam cleaner; tractor
GROUP 5: Master Mechanic
For HEAVY AND HIGHWAY CONSTRUCTION:
FOOTNOTE:
b. PAID HOLIDAYS: New Years Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day provided the employee works the working day before and the working day after the holiday
POWER EQUIPMENT OPERATOR CLASSIFICATIONS (HEAVY/HIGHWAY):
https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 7/15
GROUP 1: Asphalt Curb Machine, Self Propelled, Slipform, Automated Concrete Spreader (CMI Type), Automatic Fine Grader, Backhoe (Except Tractor Mounted, Rubber Tired), Backhoe Excavator Full Swing (CAT 212 or similar type), Back Filling Machine, Belt Placer (CMI Type), Blacktop Plant (Automated), Boom truck , Cableway, Caisson Auger, Central Mix Concrete Plant (Automated), Concrete Curb Machine, Self Propelled, Slipform, Concrete Pump, Crane, Cherry Picker, Derricks (steel erection), Dragline, Overhead Crane (Gantry or Straddle type), Pile Driver, Truck Crane, Directional Drilling Machine, Dredge, Dual Drum Paver, Excavator (All Purpose Hydraulically Operated) (Gradall or Similar), Front End Loader ( 4 cu. yd. and Over), Head Tower (Sauerman or Equal), Hoist (Two or Three Drum), Holland Loader, Maintenance Engineer, Mine Hoist, Mucking Machine or Mole Pavement Breaker(SP) Wertgen; PB-4 and similar type, Power Grader, Profiler (over 105 H.P.)
Quad 9, Quarry Master (or equivalent), Scraper, Fireman, Fork Lift, Form Tamper, Grout Pump, Gunite Machine, Hammers (Hydraulic self-propelled), Hydra-Spiker, ride-on, Hydraulic Pump (jacking system), Hydro-Blaster (Water), Mulching Machine, Oiler, Parapet Concrete or Pavement, Shovel, Side Boom, Slip Form Paver, Tractor Drawn, BeltType Loader, Truck or Trailer Mounted Log , Chipper (Self Feeder), Tug Operator (Manned Rented Equipment Excluded), Tunnel Shovel
GROUP 2: Asphalt Paver, Backhoe (Tractor Mounted, Rubber Tired), Bituminous Recycler Machine, Bituminous Spreader and Mixer, Blacktop Plant (NonAutomated), Blast or Rotary Drill (Truck or Tractor Mounted), Boring Machine, Cage Hoist, Central Mix Plant (NonAutomated) and All Concrete Batching Plants, Cherry Picker (5 tons capacity and under), Concrete Paver (Over 16S), Crawler Drill, Self-contained, Crusher, Diesel Power Unit, Drill Rigs, Tractor Mounted, Front End Loader (Under 4 cu. yd.), Greaseman/Lubrication Engineer, HiPressure Boiler (15 lbs. and over), Hoist (One Drum), Hydro-Axe, Kolman Plant Loader and Similar Type Loaders, L.C.M. Work Boat Operator, Locomotive Mixer (for stabilized base selfpropelled), Monorail Machine, Plant Engineer, Profiler (105 H.P. and under), Grinder, Post Hole Digger and Post Driver, Power Broom (towed), Power Heaterman, Power Sweeper, Revinius Widener, Roller (Grade and Fill), Scarifier, ride-on, Shell Winder, Skid steer loader (Bobcat or similar), Span-Saw, ride-on, Steam Cleaner, Pug Mill, Pump Crete Ready Mix Concrete Plant Refrigeration Equipment (for soil stabilization)Road Widener, Roller (all above subgrade), Sea Mule, Self-contained Ride-on Rock Drill, Excluding Air-Track Type Drill, Skidder, Tractor with Dozer and/or Pusher, Trencher.
Tugger Hoist, Vermeer saw (ride on, any size or type), Winch, Winch Cat
GROUP 3: A Frame Winch Hoist on Truck , Articulated Heavy Hauler, Aggregate Plant, Asphalt or Concrete Grooving, Machine (ride on), Ballast Regulator, Ride-on Boiler (used in conjunction with production), Bituminous Heater, self-propelled, Boat (powered), Cement and Bin Operator, Compressors, Dust Collectors, Generators, Pumps, Welding Machines, Light Plants, Heaters (hands-off equipment), Concrete Pavement Spreader and Finisher, Concrete Paver or Mixer (16S and under), Concrete Saw (self-propelled), Conveyor, Deck Hand, Directional Drill Machine Locator, Drill, (Core), Drill, (Well,) Farm Tractor with accessories, Fine Grade Machine, Tamper, ride-on, Tie https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 8/15
Extractor, ride-on, Tie Handler, ride-on, Tie Inserter, ride-on, Tie Spacer, ride-on, Tire Repair, Track Liner, ride-on, Tractor, Tractor (with towed accessories), Vibratory Compactor, Vibro Tamp, Well Point
GROUP 4: Tower Cranes
GROUP 5: Cranes 50 tons and over
GROUP 6: Cranes 49 tons and below
GROUP 7: Master Mechanic
For TUNNEL AND SHAFT:
FOOTNOTE:
b. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, Christmas Day, regardless of the day of the week on which the Holiday may fall, provided the employee works the working day before and the working day after the holiday
TUNNEL AND SHAFT CLASSIFICATIONS
GROUP 1: Automated concrete spreader (CMI or equivalent);
automated fine grade machine (cmi); backhoe; belt placer (cmi or similar); blacktop spreader (automated); cableway;
caisson auger; central mix plant (automated); cherry picker (5 tons); concrete curb machine (self-propelled slipform);
concrete pump; crane; crane shaft; crane underground;
cranes and derricks (steel erection); dragline; dredge;
dual drum paver; excavator (all purpose-hydraulicly operated gradall or similar); fork lift (factory rated 15' and over); front end loader (4cu yd and over); head tower (sauerman or equal); hoist; shaft; hoist (two or three drum); holland loader; maintenance engineer (shaft and tunnel); mine hoist; mining machine (mole and similar types); mucking machine or mose; overhead crane (gantry or straddle type); pile driver; power grader; Quad 9, quarry master (or equivalent); scraper; shovel; side boom; slip form paver; tripper/maintenance engineer (shaft and tunnel); tractor drawn belt-type loader; truck crane; truck or trailer mounted log chipper (self feeder); tug operator (manned rented equipment excluded); tunnel shovel
GROUP 2: Automated central mix concrete plant; backhoe (topside); backhoe (tractor mounted,rubber tired);
bituminous spreader and mixer; blacktop plant (non automated); blast or rotary drill (truck or tractor mounted); boring machine; cage hoist; central mix plant (non automated) and all concrete batching plants; cherry picker (5 tons capacity and under); compressors (4 or less exceeding 2000 CFM combined capacity); concrete paver (over 16s); concrete pump; crane (topside); crusher; diesel power unit; drill rigs, tractor mounted; front end loader (under 4 cu. yds); grayco epoxy machine; hi-pressure boiler (15 lbs and over); hoist (one drum); hoist (two or three drum) (topside); kolman plant loader and similar type loaders;
L.C.M. work boat operator; locomotive; maintenance engineer (topside); maintenance greaseman; mixer (for stabilized base self-propelled); monorial machine; plant engineer;
personnel hoist; pump crete; ready mix concrete plant;
refrigeration equipment (from soil stabilization); road https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad_… 9/15 widener; roller (all above sub-grade); sea mule; shotcrete machine; shovel (topside); tractor with dozer and/or pusher; trencher; tugger hoist; tunnel locomotive; welder;
winch; winch cat
GROUP 3: ""A"" frame truck; ballast regulator (ride on);
compressors (4 not to exceed 2000 cfm combined capacity; or 3 or less with more than 1200 cfm but not to exceed 2000 cfm); compressors (any size but subject to other provisions for compressors; dust collectors; generators; pumps;
welding machines; light plants (4 of any type or combination); concrete pavement spreaders and finishers;
conveyor; drill (core); drill (well); electric pump used in conjunction with well point system; farm tractor with accessories; fine grade machine; fork lift (under 15 ft);
ground pump over 5 cu. ft (manufacturers rating); gunite machine; hammers (hydraulic self propelled); hydra-spiker (ride on); hydra blaster (water); hydra blaster; motorized form carrier; post hole digger and post driver; power sweeper; roller (grade and fill); scarifer (ride on); span saw (ride on); submersible electric pump (when used in lieu of well points); tamper (ride on); tie extractor (ride on);
tie handler (ride on); tie inserter (rider on); tie spacer (ride on); track liner (ride on); tractor with towed accessories; vibratory compactor; vibro tamp; well point aggregate plant; boiler (used in conjunction with production); cement and bin operator; compressors (3 or less not to exceed 1200 cfm combined capacity); compressors (any size; but subject to other provisions for compressors); dust collectors; generators; pumps; welding machines; light plants (3 or less of any type or combination); concrete paver or mixer (16s and under);
concrete saw (self propelled); fireman; form tamper;
greaseman; hydraulic pump (jacking system); junior engineer; light plants; mulching machine; oiler; parapet concrete or pavement grinder; power broom (towed); power heaterman (when used for production); revinius widener;
shell winder; steam cleaner; tractor
GROUP 4: Crane, friction or lattice type with boom length 200 feet and over
ENGI0832-004 07/01/2018
Rates Fringes
Power equipment operators:
BUILDING CONSTRUCTION
GROUP 1....................$ 33.27 27.90+a GROUP 2....................$ 32.47 27.90+a GROUP 3....................$ 29.77 27.90+a GROUP 4....................$ 25.21 27.90+a GROUP 5....................$ 36.85 27.90+a GROUP 6....................$ 38.32 27.90+a GROUP 7....................$ 39.19 27.90+a GROUP 8....................$ 35.27 27.90+a
FOOTNOTE:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day, and Christmas Day, provided the employee works on the work day immediately preceding the holiday or on the scheduled work day immediately following the holiday.
https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 10/15
BUILDING CONSTRUCTION CLASSIFICATIONS
GROUP 1: Air Tugger, All terrain telescoping material handler, Clamshell, Dragline, Shovel and similar machines over three eighths cu.yd. capacity (Fact. rating);Carrier mounted backhoes that swing 360 degrees Big Generator Plant Hoist (on steel erection) Bridge Crane (all types), Cableway, Caisson auger and similar type machine, Crane, Derrick, Dredge, Excavator all purpose hydraulically operated, Forklift (with Factory rating of Fifteen ft. or more of lift),Hoist (on steel erection), Hydraulic/Krupp Drill Type Mucking Machines, Remote controlled excavator with attachments (Brokk type or similar), Ross Carrier (and similar type), Three-Drum Hoist(when all three drums are in use)
GROUP 2: A-Frame Truck, Backfilling Machine, Backhoe -tractor mounted, Barber Green and similar type machines, Belt Crete and similar type machines, Bituminous spreading machine 3/8 yd. capacity or less(Factory Rating), Bulldozer, Carry-all type scraper, Compressors: Four (4) not to exceed 2000 CFM combined capacity; or three (3) or less with more than1200 CFM but not to exceed 2000 CFM, Concrete Mixer, Concrete Placer, Concrete Pump, Dinky Locomotives (all types), Elevating Grader, Elevator Fine Grade and Finish, Rollers, Fine Grade Machines(all kinds), Forklift with Factory rating of less than fifteen(15) feet of lift, Front End Loader, Gunite Pumping Machine, High Pressure Boiler, Hoist (1 or 2 drums), Maintenance Engineer (Mechanic), Mechanical Slurry Machine (all kinds), Mega Mixers and similar type machines, Motor Grader, Post Hole Digger, Pumps (regardless of motive power) no more than four (4) in number not to exceed twenty (20) inches in total capacity, Shot Crete Pumping Machine, Side Boom Tractor, Skid Steer Loader with Attachments, Stone Crusher Tournadozer and similar types Tournapull and similar types, Trenching Machines, Well Drill, WellPoint System EXCEPTION: Single electric pumps up to and including four (4) inches need not be manned.
GROUP 3: Any combination (Not to exceed three (3) pieces of equipment) Compressors �three (3) or less, or not to exceed 1200 CFM combined capacity, Fireman, Longitudinal Float, Mechanical Heater Pumps (regardless of motive power) No more than three (3) in number, not to exceed twelve (12) inches total capacity, Roller (Fill and Grade)Rubber Tired Tractor Welding Machine or Mechanical Conveyor (over 12ft.
in length) EXCEPTION: Single gasoline driven welding machine up to 300amps need not be manned.
GROUP 4: Oilers
GROUP 5: Cranes up to and including 25 tons
GROUP 6: Cranes 25-250 tons
GROUP 7: Cranes 251 and over tons
GROUP 8: Tower Cranes
IRON0033-003 07/01/2019
REMAINDER OF COUNTY
https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 11/15
Rates Fringes
Ironworkers:
Sheeter.....................$ 30.05 26.89 Structural, ornamental, rodman, machinery mover-rigger, fence erector precast concrete erector, reinforcing, stone derrickman..................$ 28.00 26.89
LABO0435-004 05/01/2019
Rates Fringes
Laborers:
BUILDING:
Blaster....................$ 27.87 18.59 Chuck tender...............$ 26.74 18.59 Concrete vibrators.........$ 26.98 18.59 Drillers and asphalt raker.$ 26.94 18.59 Hazardous waste removal....$ 27.14 17.99 Jack hammer, mortar mixers.$ 26.84 18.59 Pipe layers, burners and cutters....................$ 26.84 18.59 Powder Monkey..............$ 27.41 18.59 Unskilled Laborer..........$ 26.54 18.59 Yardman, clean-up..........$ 23.69 18.59
HEAVY/HIGHWAY
GROUP 1....................$ 28.54 19.92
GROUP 2....................$ 29.24 19.92
GROUP 3....................$ 29.44 19.92
GROUP 4....................$ 30.27 19.92
GROUP 5....................$ 30.04 19.92
FOOTNOTES:
a. PAID HOLIDAYS: New Year's Day, Memorial Day, Independence Day, Labor Day, Thanksgiving Day and Christmas Day, provided the employee has worked the working day before and the working day after the holiday.
HEAVY AND HIGHWAY LABORER CLASSIFICATIONS
GROUP 1: Flaggers;
GROUP 2: Laborers GROUP 3: Rakers, drillers, pipelayers, and torch operators GROUP 4: Blasters GROUP 5: Hazardous waste removal
PAIN0004-015 05/01/2019
DANSVILLE, NUNDA, OSSIAN, PORTAGE, SPARTA, SPRINGWATER AND WEST
SPRATA
Rates Fringes
Painters: (BUILDING
CONSTRUCTION)
BUILDING CONSTRUCTION
Brush and Roller...........$ 24.68 19.51 Drywall/Taping.............$ 25.18 19.51 https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 12/15
Wallcovering, Spray Painting, Sandblasting.....$ 24.93 19.51
HEAVY & HIGHWAY
CONSTRUCTION
Bridges....................$ 38.50 28.40
PAIN0004-028 05/01/2019
Rates Fringes
Painters:
BUILDING CONSTRUCTION
Brush & Roll...............$ 23.22 22.43 Drywall Taper..............$ 24.56 22.49 Sandblasting...............$ 23.97 23.97 Spray......................$ 23.82 22.43 Wallcovering...............$ 23.52 22.43
HEAVY & HIGHWAY
CONSTRUCTION:
Bridge Work................$ 38.50 28.40
PAIN0677-004 05/01/2020
Rates Fringes
GLAZIER..........................$ 25.75 24.40
PLUM0013-001 05/01/2020
Rates Fringes
Plumber and Steamfitter..........$ 34.23 23.83
ROOF0022-001 06/01/2020
Rates Fringes
ROOFER...........................$ 29.80 21.57
SFNY0669-001 01/02/2020
Rates Fringes
SPRINKLER FITTER.................$ 36.80 24.35
SHEE0046-001 05/01/2017
Rates Fringes
Sheet metal worker...............$ 32.13 23.40
TEAM0118-003 07/01/2020
Rates Fringes
Truck drivers:
GROUP 1.....................$ 24.72 24.68+a GROUP 2.....................$ 24.77 24.68+a GROUP 3.....................$ 24.82 24.68+a GROUP 4.....................$ 24.97 24.68+a GROUP 5.....................$ 25.12 24.68+a
Hazardous Waste Site Work receives an additional $1.50 per hour https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 13/15
FOOTNOTE: a. Paid Holidays: New Years Day; Memorial Day;
Independence Day; Laobr Day; Thanksgiving Day; Christmas Day
TRUCK DRIVER CLASSIFICATIONS
GROUP 1: Pick-ups; panel trucks; flatboy materials trucks (straight jobs); single axle dump trucks; dumpsters;
receivers; greasers; truck tireman.
GROUP 2: Tandems; batch truck; mechanics.
GROUP 3: Semi-trailers; low-boy trucks; asphalt distributor trucks; agitator; mixer trucks and dumpcrete type vehicles;
truck mechanic; fuel truck.
GROUP 4: Specialized earth moving equipment - euclid type or similar off-highway equipment, where not self-loaded;
straddle (Ross) carrier; self-contained concrete unit.
GROUP 5: Off-highway tandem back dump; twin engine equipment; double-hitched equipment shere not self-loaded.
WELDERS - Receive rate prescribed for craft performing operation to which welding is incidental.
Note: Executive Order (EO) 13706, Establishing Paid Sick Leave for Federal Contractors applies to all contracts subject to the Davis-Bacon Act for which the contract is awarded (and any solicitation was issued) on or after January 1, 2017. If this contract is covered by the EO, the contractor must provide employees with 1 hour of paid sick leave for every 30 hours they work, up to 56 hours of paid sick leave each year.
Employees must be permitted to use paid sick leave for their own illness, injury or other health-related needs, including preventive care; to assist a family member (or person who is like family to the employee) who is ill, injured, or has other health-related needs, including preventive care; or for reasons resulting from, or to assist a family member (or person who is like family to the employee) who is a victim of, domestic violence, sexual assault, or stalking. Additional information on contractor requirements and worker protections under the EO is available at www.dol.gov/whd/govcontracts.
Unlisted classifications needed for work not included within the scope of the classifications listed may be added after award only as provided in the labor standards contract clauses (29CFR 5.5 (a) (1) (ii)).
The body of each wage determination lists the classification and wage rates that have been found to be prevailing for the cited type(s) of construction in the area covered by the wage determination. The classifications are listed in alphabetical order of ""identifiers"" that indicate whether the particular rate is a union rate (current union negotiated rate for local), a survey rate (weighted average rate) or a union average rate (weighted union average rate).
https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 14/15
Union Rate Identifiers
A four letter classification abbreviation identifier enclosed in dotted lines beginning with characters other than ""SU"" or ""UAVG"" denotes that the union classification and rate were prevailing for that classification in the survey. Example:
PLUM0198-005 07/01/2014. PLUM is an abbreviation identifier of the union which prevailed in the survey for this classification, which in this example would be Plumbers. 0198 indicates the local union number or district council number where applicable, i.e., Plumbers Local 0198. The next number, 005 in the example, is an internal number used in processing the wage determination. 07/01/2014 is the effective date of the most current negotiated rate, which in this example is July 1, 2014.
Union prevailing wage rates are updated to reflect all rate changes in the collective bargaining agreement (CBA) governing this classification and rate.
Survey Rate Identifiers
Classifications listed under the ""SU"" identifier indicate that no one rate prevailed for this classification in the survey and the published rate is derived by computing a weighted average rate based on all the rates reported in the survey for that classification. As this weighted average rate includes all rates reported in the survey, it may include both union and non-union rates. Example: SULA2012-007 5/13/2014. SU indicates the rates are survey rates based on a weighted average calculation of rates and are not majority rates. LA indicates the State of Louisiana. 2012 is the year of survey on which these classifications and rates are based. The next number, 007 in the example, is an internal number used in producing the wage determination. 5/13/2014 indicates the survey completion date for the classifications and rates under that identifier.
Survey wage rates are not updated and remain in effect until a new survey is conducted.
Union Average Rate Identifiers
Classification(s) listed under the UAVG identifier indicate that no single majority rate prevailed for those classifications; however, 100% of the data reported for the classifications was union data. EXAMPLE: UAVG-OH-0010 08/29/2014. UAVG indicates that the rate is a weighted union average rate. OH indicates the state. The next number, 0010 in the example, is an internal number used in producing the wage determination. 08/29/2014 indicates the survey completion date for the classifications and rates under that identifier.
A UAVG rate will be updated once a year, usually in January of each year, to reflect a weighted average of the current negotiated/CBA rate of the union locals from which the rate is based.
WAGE DETERMINATION APPEALS PROCESS
1.) Has there been an initial decision in the matter? This can be:
https://beta.sam.gov/wage-determination/NY20210030/2?index=wd&keywords=&is_active=true&sort=-modifiedDate&date_filter_index=0&date_rad… 15/15
* an existing published wage determination
* a survey underlying a wage determination
* a Wage and Hour Division letter setting forth a position on a wage determination matter
* a conformance (additional classification and rate) ruling
On survey related matters, initial contact, including requests for summaries of surveys, should be with the Wage and Hour Regional Office for the area in which the survey was conducted because those Regional Offices have responsibility for the Davis-Bacon survey program. If the response from this initial contact is not satisfactory, then the process described in 2.)
and 3.) should be followed.
With regard to any other matter not yet ripe for the formal process described here, initial contact should be with the Branch of Construction Wage Determinations. Write to:
Branch of Construction Wage Determinations Wage and Hour Division U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
2.) If the answer to the question in 1.) is yes, then an interested party (those affected by the action) can request review and reconsideration from the Wage and Hour Administrator (See 29 CFR Part 1.8 and 29 CFR Part 7). Write to:
Wage and Hour Administrator U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
The request should be accompanied by a full statement of the interested party's position and by any information (wage payment data, project description, area practice material, etc.) that the requestor considers relevant to the issue.
3.) If the decision of the Administrator is not favorable, an interested party may appeal directly to the Administrative Review Board (formerly the Wage Appeals Board). Write to:
Administrative Review Board U.S. Department of Labor 200 Constitution Avenue, N.W.
Washington, DC 20210
4.) All decisions by the Administrative Review Board are final.
END OF GENERAL DECISION"
Questions and Answers for MMD VC Road
A Site Visit was held at Mt. Morris Dam on 23 March 2021 with Armitage Architecture in attendance.
The Following questions were either submitted or asked at the site visit.
Will there be a staging area for the contractor?
Response – A staging area will be provided and discussed during the pre-construction meeting.
Does the construction debris/refuse need to be moved off site?
Response – Yes, the construction debris/refuse becomes the property of the contractor and must be disposed of properly.