Question_11Dec2017.pdf
PDF 164 KB Posted
- Attached to
- Conneaut East Breakwater Repair
- Solicitation number
- W912P418B0008
About this file
Please see attachment with contractor question.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Bid_Abstract_20Dec2017.xlsx | XLSX spreadsheet | |
| CONN17BelowWater(All)NEG.xyz | XYZ file | |
| CONN17AboveWater(All)NEG.xyz | XYZ file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Question:
We have been in contact with the P&C Dock and they advise that due to the previous years Army Corp Armor Stone supply contract material not yet having been removed from the dock there is not any dock area available to stage stone for this years project.
Would the Army Corps consider an alternative bid schedule or alternate completion timeframe dependent on the dock area becoming available?
Answer:
The Corps is not considering an alternative bid schedule or alternate completion timeframe dependent on dock space availability. Bids should be based on the solicitation documents as provided.