Bid_Abstract_20Dec2017.xlsx
XLSX spreadsheet 26 KB Posted
- Attached to
- Conneaut East Breakwater Repair
- Solicitation number
- W912P418B0008
About this file
Please see attached bid abstract.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Question_11Dec2017.pdf | ||
| CONN17BelowWater(All)NEG.xyz | XYZ file | |
| CONN17AboveWater(All)NEG.xyz | XYZ file |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Bids 1-4 Bid Abstract Conneaut East Breakwater
| IGE | Upstate | Con. | Great | Lakes | Huffman | Equip | GEO | Gradel | |||||
| Item No. | Description | Unit | Quantity | Unit Price | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount |
| 1 | Mobilization and Demobilization | JOB | 1 | $221,317.00 | $221,317.00 | $600,500.00 | $600,500.00 | $340,395.00 | $340,395.00 | $250,000.00 | $250,000.00 | $139,690.00 | $139,690.00 |
| 2 | Record (As-built) Drawings | JOB | 1 | $21,700.00 | $21,700.00 | $15,000.00 | $15,000.00 | $13,600.00 | $13,600.00 | $20,000.00 | $20,000.00 | $20,250.00 | $20,250.00 |
| 3 | Breakwater Repair (Sta. 0+00~0+75) | ||||||||||||
| a. | Armor Stone | TN | 10,710 | $138.05 | $1,478,515.50 | $91.85 | $983,713.50 | $112.02 | $1,199,734.20 | $125.60 | $1,345,176.00 | $125.00 | $1,338,750.00 |
| b. | Underlayer Stone | TN | 1,885 | $82.65 | $155,795.25 | $75.00 | $141,375.00 | $68.58 | $129,273.30 | $91.95 | $173,325.75 | $133.00 | $250,705.00 |
| 4 | Removal and Reuse of Existing Stone | JOB | 1 | $58,325.00 | $58,325.00 | $16,000.00 | $16,000.00 | $32,340.00 | $32,340.00 | $20,000.00 | $20,000.00 | $52,900.00 | $52,900.00 |
| 5 | Concrete Leveling Pad and Navigation | JOB | 1 | $34,385.00 | $34,385.00 | $33,900.00 | $33,900.00 | $17,185.00 | $17,185.00 | $15,000.00 | $15,000.00 | $13,900.00 | $13,900.00 |
| Total Amount (Items 1 ~ 5) | $1,970,037.75 | $1,790,488.50 | $1,732,527.50 | $1,823,501.75 | $1,816,195.00 | ||||||||
| Option "A" | |||||||||||||
| 6 | Breakwater Repair (Sta. 0+75 ~ 1+50) | ||||||||||||
| a. | Armor Stone | TN | 6,335 | $137.95 | $873,913.25 | $91.85 | $581,869.75 | $112.02 | $709,646.70 | $125.60 | $795,676.00 | $125.00 | $791,875.00 |
| b. | Underlayer Stone | TN | 817 | $89.80 | $73,366.60 | $75.00 | $61,275.00 | $56,029.86 | $56,029.86 | $91.95 | $75,123.15 | $133.00 | $108,661.00 |
7 Removal and Reuse of Existing Stone JOB 1 $35,810.00 $35,810.00 $16,000.00 $16,000.00 $21,560.00 $21,560.00 $10,000.00 $10,000.00 $24,900.00 $24,900.00
Total Amount (Items 6 and 7) $983,089.85 $659,144.75 $787,236.56 $880,799.15 $925,436.00
Total Amount (Items 1 ~ 7) $2,953,127.60 $2,449,633.25 $2,519,764.06 $2,704,300.90 $2,741,631.00
Bids 5-7 Bid Abstract Conneaut East Breakwater
| IGE | Luedtke | Ryba | Marine | S.E.T. | Inc. | ||||||||
| Item No. | Description | Unit | Quantity | Unit Price | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount | Unit Cost | Bid Amount |
| 1 | Mobilization and Demobilization | JOB | 1 | $221,317.00 | $221,317.00 | $335,000.00 | $335,000.00 | $802,500.00 | $802,500.00 | $1,398,212.00 | $1,398,212.00 |
| 2 | Record (As-built) Drawings | JOB | 1 | $21,700.00 | $21,700.00 | $15,000.00 | $15,000.00 | $50,000.00 | $50,000.00 | $45,000.00 | $45,000.00 |
| 3 | Breakwater Repair (Sta. 0+00~0+75) | ||||||||||
| a. | Armor Stone | TN | 10,710 | $138.05 | $1,478,515.50 | $151.00 | $1,617,210.00 | $165.00 | $1,767,150.00 | $155.00 | $1,660,050.00 |
| b. | Underlayer Stone | TN | 1,885 | $82.65 | $155,795.25 | $126.00 | $237,510.00 | $150.00 | $282,750.00 | $135.00 | $254,475.00 |
| 4 | Removal and Reuse of Existing Stone | JOB | 1 | $58,325.00 | $58,325.00 | $50,000.00 | $50,000.00 | $100,000.00 | $100,000.00 | $165,000.00 | $165,000.00 |
| 5 | Concrete Leveling Pad and Navigation | JOB | 1 | $34,385.00 | $34,385.00 | $30,000.00 | $30,000.00 | $44,000.00 | $44,000.00 | $25,000.00 | $25,000.00 |
| Total Amount (Items 1 ~ 5) | $1,970,037.75 | $2,284,720.00 | $3,046,400.00 | $3,547,737.00 | |||||||
| Option "A" | |||||||||||
| 6 | Breakwater Repair (Sta. 0+75 ~ 1+50) | ||||||||||
| a. | Armor Stone | TN | 6,335 | $137.95 | $873,913.25 | $140.00 | $886,900.00 | $100.00 | $633,500.00 | $203.00 | $1,286,005.00 |
| b. | Underlayer Stone | TN | 817 | $89.80 | $73,366.60 | $115.00 | $93,955.00 | $100.00 | $81,700.00 | $180.00 | $147,060.00 |
7 Removal and Reuse of Existing Stone JOB 1 $35,810.00 $35,810.00 $50,000.00 $50,000.00 $77,500.00 $77,500.00 $80,000.00 $80,000.00
Total Amount (Items 6 and 7) $983,089.85 $1,030,855.00 $792,700.00 $1,513,065.00
Total Amount (Items 1 ~ 7) $2,953,127.60 $3,315,575.00 $3,839,100.00 $5,060,802.00