Extend deadline for questions until 2 Sep 09 at 1600 EST and answer a question.

View the file

Other files

File Type Posted
document2009-09-09-145506.pdf PDF
Amendment 8.pdf PDF
Amendment 7.doc DOC document
Amendment 5.doc DOC document
Amendment 4.doc DOC document
Sources Sought sign-in sheet.pdf PDF
10B Amendment 3.doc DOC document
DSCN0469.jpg JPG image
DSCN0459.jpg JPG image
DSCN0472.jpg JPG image
document2009-08-14-103004.pdf PDF
DSCN0462.jpg JPG image
DSCN0466.jpg JPG image
W912P4-09-B-0010 amend1.doc DOC document
DSCN0463.jpg JPG image
W91P4-09-B-0010 amend2.doc DOC document
DSCN0473.jpg JPG image
DSCN0464.jpg JPG image
DSCN0465.jpg JPG image
DSCN0468.jpg JPG image
DSCN0467.jpg JPG image
DSCN0461.jpg JPG image
DSCN0460.jpg JPG image
DSCN0470.jpg JPG image
DSCN0458.jpg JPG image
Final Solicitation.pdf PDF
Show all 26

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00800 - SPECIAL CONTRACT REQUIREMENTS

The following have been added by full text:

AMENDMENT 6

1. On Amendment 5, which acknowledgement date should be used, Aug. 27th (date signed) or of Sep. 9th (effective date)?

Answer: The amendments need to be acknowledged with your bid. The acknowledgment date can be either date; as long as it is acknowledged prior to the bid opening.

(End of Summary of Changes)