This amendment to a solicitation modifies the response date from July 27, 2023 to August 2, 2023 for a walk-in media blast cleaning system procurement. The Army Materiel Command Contracting Command Redstone Arsenal seeks one system including equipment design, shipping, installation, and training to be delivered within 18 months. The contractor must provide seven HEPA vacuums and media blast cabinets will be procured through new CLIN 0006 with sub-CLINs for design, fabrication, shipping, and installation. The low price technically acceptable proposal will be selected with evaluation based on total price of all CLINs.

View the file

Other files

Show all 14

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ARMY CONTRACTING COMMAND - REDSTONE

TERRY B. CLARK (361)961-6489

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

The purpose of this amendment is to extend the request for quote from 2:00 PM Central Time, 27 July 2023 to 2:00 PM Central Time, 02 August 2023; incorporate CLIN 0006 w ith subCLINs; and address questions #23 and #24.

All other Terms and Conditions remain unchanged.

1. CONTRACT ID CODE PAGE OF PAGES

1 12

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Jul-2023

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912NW23Q0050

X 9B. DATED (SEE ITEM 11)

12-Jun-2023

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Jul-2023

CODE

ARMY CONTRACTING COMMAND - REDSTONE

CONTRACTING OFFICE

CORPUS CHRISTI ARMY DEPOT

9035 OCEAN DR. BLDG 10, MAIL STOP 18

CORPUS CHRISTI TX 78419-5260

W912NW 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE W912NW

FACILITY CODECODE

EMAIL:TEL:

W912NW23Q0050

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE

The following have been modified:

QUESTIONS & ANSWERS

MEDIA BLAST

RFQ W912NW-23-Q-0050 Questions & Answers

Question 1. SOW paragraph 2.1.3.3. Shall include a dividing wall separating blast booth and cabinets from Dense Particle Separator, Dust Collector, and other supporting equipment in accordance with Drawing BLDG1700-3_VerA_Rev30. Please provide Drawing BLDG1700- 3_VerA_latest revision.

Answer 1. To request access to drawings, submit an email to the following:

Terry Clark: terry.b.clark4.civ@army.mil and Dawyn Martinez: dawyn.m.martinez.civ@army.mil

Question 2. SOW paragraph 2.1.4.1. The Contractor shall provide convenience outlets distributed throughout the inside of the enclosure. Please provide advise specific quantity of outlets being requested.

Answer 2. Eight (8) outlets. One to service each blast booth, and two in the mechanical room, to be used with HEPA vacuums for housekeeping. SOW updated in section 2.1.4.1. The Contractor shall provide a minimum of eight (8) convenience outlets distributed throughout the inside of the enclosure. One shall be placed near each of the blast cabinets and two in the blast system mechanical room.

Question 3. SOW paragraph 3. 2.1.4.2. Lighting: The Contractor shall provide general overhead LED lighting that provides 100 foot-candles of light as measured at any point 36 inches above the floor within the enclosure and must uniformly illuminate the floor. The light fixtures shall be recessed to prevent dust build up. The fixtures and bulbs shall be easy to replace from inside the enclosure. On/off switches shall be located inside the enclosure at all personnel doors, excluding roll up doors. Please confirm the Govt. wants the light “fixtures” to be replaceable from inside the enclosure as this is a higher cost option. Typical light “fixtures” are replaceable from outside the enclosure while allow for the bulbs to be replaceable from inside the enclosure.

Answer 3. Bulbs to be changeable from inside. Fixtures may be accessible from the outside.

SOW edited to reflect the correction in paragraph “2.1.4.2. Lighting: The Contractor shall provide general overhead LED lighting that provides 100 foot-candles of light as measured at any point 36 inches above the floor within the enclosure and must uniformly illuminate the floor. The light fixtures shall be recessed to prevent dust build up. Bulbs shall be easy to replace from inside the enclosure. On/off switches shall be located inside the enclosure at all personnel doors, excluding roll up doors.”

Question 4. SOW paragraph 2.1.5. HVAC, Filtration and Exhaust: The Enclosure shall have its own HVAC system and source of general filtration. For cost savings, the system shall use adaptive ventilation technology that changes flow based on use. The exhaust and make-up air will be supplied via 2 48”x48” roof penetrations on the building 1700.3 roof. Please confirm that the HVAC can supply air into the main building at the enclosure location, and then the enclosure air supply can be supplied from the building. This will improve management of the pressure gradient in the enclosure, ensure negative pressure within the enclosure, and simplify air management allowing for lower cost.

Answer 4. Makeup air is to be drawn from supplied roof penetration (SOW, 2.1.5, 2.1.5.1.4, 2.2.7.2).

Question 5. SOW paragraph 2.2.4.2. Specifications

• One 30” vibratory media classifier/separator to separate large waste and fines from media

• Rare-earth magnetic separator to remove ferrous particles

• Ionizer for static build-up

• Level Sensor for hopper overfill protection

• 12” fluidized bed utilizing aluminum oxide as media

Please confirm that the DPS system should be purposely designed for aerospace. Use of other industrial systems using materials, such as wood and canvas, are not acceptable for aerospace related processes.

Answer 5. Correct. SOW changed to reflect clarification. Added to specifications:

“Constructed using durable materials suitable for aerospace production environments, wood, canvas, and other similar materials not acceptable.”

Question 6. SOW paragraph 2.2.2.5. Blast Booth shall have provisions for hanging parts to be blasted, as well as a means to lift parts onto said hangers. What is the largest size/weight that an item will be hung for blasting?

Answer 6. Max weight approximately 150 lbs, Max Dimensions 72” x 30” x 20” (LxWxH). Average parts considerable lighter and smaller. SOW updated to reflect given dimensions: “2.2.2.5. Blast Booth shall have provisions for hanging parts to be blasted, as well as a means to lift parts weighing up to 150 lbs with maximum dimensions up to 72 inches onto said hangers.”

Question 7. SOW paragraph 2.2.3 Media Recovery System

Above grade full floor pneumatic media recovery system throughout Walk-In Media Blast room.

Floor load rating of 2000 lbss per ft2 or better.

Constructed of modular sections for future maintenance and cleaning Recovery rate controllable and variable per each section of floor.

Please clarify what is meant my “controllable”. VES interprets “recovery rate” as the amount of “time” that a recovery tube is opened allowing recovery of the media? Is the intent of controllable to allow the time per tube to be adjustable by programming?

Answer 7. Yes. The ability to vary the recovery duration for areas of high media accumulation, adjustable via control PLC. Last bullet of 2.2.3 now reads, “Recovery rate variable per each section of floor and controllable via Control PLC.”

Question 8. SOW paragraph 2.2.5.1. All dust collection shall be of modular design utilizing common parts and pleated paper cartridge type HEPA filters.

8a. Please confirm that “modular” means that the dust collector number of cartridges can changed without refabrication of the existing dust collector body. Bolt together panels.

Answer 8a. Modular meaning standardized design made of interchangeable, reconfigurable parts.

A custom-built dust collector requiring special hand-made filter cartridges is not desired.

Question 8b. Please confirm that all HEPA filters are to be installed on the negative size of the exhaust blower. In this configuration all air is filtered by HEPA before being exhausted to the clean side of the blower. In an event where a cartridge filter is damaged and dirty air is exhausted into the positive side of a blower there is a potential for dirty air to enter the building should an air leak develop in the ducting before reaching an aftermarket HEPA.

Answer 8b. Specific filter location and orientation is up to contractor. Dust collection should be designed to prevent contamination. SOW changed to reflect: SOW paragraph “2.2.5.1. All dust collection shall be of modular design utilizing common parts and easily changed pleated paper cartridge type HEPA filters and constructed to prevent contamination of surrounding area during maintenance or in case of failure.”

Question 8c. Does the Govt. prefer cartridge filters that are hung in a true vertical position with the ability for them to be bagged internal to the dust collector to limit migration of hazardous outside dust collector?

Answer 8c. Specific filter location and orientation is up to contractor. Dust collection should be designed to prevent contamination. SOW changed to reflect paragraph “2.2.5.1. All dust collection shall be of modular design utilizing common parts and easily changed pleated paper cartridge type HEPA filters and constructed to prevent contamination of surrounding area during maintenance or in case of failure.”

Question 9. SOW paragraph 2.2.6. Breathable air purification system with compressed air storage tank. Please advise the minimum size requirement for the compressed air storage tank.

Answer 9. Tank may not be required by all breathable air systems. Requirement removed from SOW; paragraph now reads:“2.2.6. Breathable air purification system. The Walk-In Media Blast Booth will include a means to produce and supply breathable air to the operators.”

Question 10. SOW paragraph 2.3.3. Media Blast Cabinet Specifications:

• Work compartment: 60” wide x 48” deep x 36” high Prevent use while working compartment doors are open.

• Clear and remove debris from around door seals prior to opening.

• Have two 43” x 30” compartment doors, one on either end of working compartment.

• Minimum view window: 16” high x 34”

• Minimum lighting: 300 foot-candles in the cabinet workspace

• Foot control

• Door interlocks to prevent blasting while doors are open

• Aeration: media fluidized bed

• Magnetic separator with cleanout port

• Moisture separator with manual drain

• Air pressure regulator

• Media valve with clean out port and quick dump feature

• Dust collector

• Blower motor: 10 HP minimum

• HEPA filtration system

• Tie into Enclosure’s ventilation system

• Magnehelic pressure differential gauge

• Self-cleaning work view window.

• Sound control: no greater than 76 dba of noise while blasting measured 3 ft from power pack.

• Adjustable height operator seat

• Be ergonomically adjustable for a large array of users.

• HEPA rated vacuum for cleaning and maintenance.

See highlighted items in yellow. Does the Govt desire independent dust collectors with each blast cabinet as suggested above? Or, is the desire to have the blast cabinets vent to the Blast Booth dust collector as suggested by bullet # 5 under section 2.2.5.4?

Answer 10. Centrally located dust collection is desired (SOW 2.2.5.4), redundant dust collector item removed from 2.3.3.

Question 11. SOW paragraph 2.3.4. HEPA vacuum:

• 120 VAC, 11.4 amps

• 2 HP motor

• 15 gallon capacity

• 263 mbar vacuum capacity

• 112 CFM capacity

• No greater than 47 LBS. empty

• Self‐closing vacuum port

• Screw on HEPA filter with pre‐filter o HEPA filter spares, 5 each o Pre‐filter spares, 5 each

• Carry handle on top of unit

• Stainless steel push/pull handle

• 2 front swivel casters, 2 rear fixed casters

• 15 foot clean up hose

• Minimum 30’ grounded power cord

• Set of general use cleaning attachments (extensions, scrubbers, etc.)

What is the minimum number of HEPA vacuums being requested?

Answer 11. Seven. They are represented in the layout drawing on the west wall of the mechanical room.

Question 12. SOW paragraph 3.4. Air System: The Contractor shall be responsible for the connection to the shop air system to a supply drop within 10 feet of the Media Blast System equipment on page P134 of Drawing “Powertrain Ph III Machining Dwgs Vol 2. The air system shall consist of the following: Please provide copy of Powertrain Ph III Machining Dwgs Vol 2.

Answer 12. To request access to drawings, submit an email to the following:

Terry Clark: terry.b.clark4.civ@army.mil and Dawyn Martinez: dawyn.m.martinez.civ@army.mil

Question 13. SOW paragraph 4.1.4. DPS Test Plan: The Contractor shall include the following test for the DPS system. The Contractor shall use a minimum of 250 pounds of new blast media and contaminate to 0.09%, by weight, of each of the following materials: 20-29 mesh sand, 30-39 mesh sand, 80-200 mesh sand, 10-12 mesh topsoil, 200 mesh topsoil, 16-18 mesh iron, 200 mesh iron, 28 mesh aluminum, 200 mesh aluminum. The Contractor shall process the thoroughly mixed media through the DPS system at a rate of 2400 pounds per hour. The tested material must not exceed the high-density particle contamination of 200 PPM. The Contractor shall provide the results and documentation that the system meets or exceeds this requirement in accordance with DI-NDTI-80566A Test Plan, CDRL A001. Please confirm that the Govt will supply 250 pounds of new blast media and contaminate to 0.09%, by weight, of each of the following materials: 20-29 mesh sand, 30-39 mesh sand, 80-200 mesh sand, 10-12 mesh topsoil, 200 mesh topsoil, 16-18 mesh iron, 200 mesh iron, 28 mesh aluminum, 200 mesh aluminum in support of the required testing?

Answer 13. Contractor shall supply test media and prescribed containments.

Question 14. SOW paragraph 6. Training: The Contractor shall provide on-site training for up to 6 personnel. Training shall address the following:

Enclosure Operation o Ventilation o Calibration o Preventative Maintenance o Trouble Shooting o Data Logging Equipment Operation o Stripping and Blasting Process o Cleaning o Preventative Maintenance o Trouble Shooting o Controls o Filter replacement procedures and safety protocols HVAC controls and settings o Dust monitoring system:

o Theory of operations and overview o Hardware, software, UPS overview o Calibration procedures o Sensor location and replacement procedures o Data storage, reports, recall and interpretation o Indicators and alarm overviews Mechanical, electrical, plumbing drawing and equipment overview:

o Review of operator, maintenance, and calibration manuals o Troubleshooting procedures

What is the minimum time on site that training is to be conducted?

Classroom instruction – minimum amount of time?

Hands-on instruction – minimum amount of time?

Answer 14. No specific time requirement. Training should be lengthy enough to cover all topics listed to an audience that includes end use artisans, equipment maintenance personnel, and supervisors.

Question 15. Will the Govt. be considering vendor past performance for both Prime Contractor and ANY Sub-Contractors they utilize in its evaluation of award determination?

Answer 15. See FAR Clause 52.212-2, on page 16 of 96, Evaluation factor is based on Lowest Price of all CLINs combined.

Question 16a.SOW paragraph 2.1.5 HVAC, Filtration and Exhaust: The Enclosure shall have its own HVAC system and source of general filtration. For cost savings, the system shall use adaptive ventilation technology that changes flow based on use. The exhaust and make-up air will be supplied via 2 48”x48” roof penetrations on the building 1700.3 roof. Please advise the building 1700.3 roof load design? Optimal positioning of the AMU is on the building roof, so we wish to confirm there is sufficient design load to support the AMU.

Answer 16a. No equipment will be allowed on the roof of 1700.3. Acceptable locations for supporting equipment include on top of enclosure and directly to the west of the enclosure mechanical room as indicated in the drawing. See also updated SOW 3.14 which now reads, SOW paragraph“3.14.Exhaust Fans: All exhaust and make-up blowers and equipment shall be mounted within the building, not on the roof and adhere to all applicable regulations such as UFC 3-410-04 (Industrial Ventilation), OSHA 29 CFR 1910.94, (Ventilation), and OSHA 40 CFR

53.463 (Air Program) The capacity of the exhaust fans shall be rated for a smooth and balanced air flow from the machine exhaust to outside air. The Contractor shall provide calculations for each exhaust fan in the installed machines’ product drawings.”

Question16b. Please confirm it is acceptable to allow the AMU to feed air supply into the building and allow the enclosure to pull air from the building? Having the MAU feed air directly into the Enclosure creates design challenges for maintaining pressure gradient within the Enclosure creating a risk for the Enclosure to be under positive pressure. Having the Enclosure pull air from the building eliminates this risk. The AMU would still be tied to the Enclosure operations and only operate for replacement of the air volume being exhausted by the Enclosure.

Answer 16b. Makeup air is to be drawn from supplied roof penetration (SOW, 2.1.5, 1.5.1.4, 2.2.7.2). Enclosure is to maintain a negative air pressure relative to the building. (SOW 2.2.7.3)

Question 17. SOW paragraph 2.1.6.6. The monitoring system will consist of at least 4 sensors in the general area of the enclosure and 1 inside the walk-in media blast booth and 2 in the dust collection mechanical room. It shall control the ventilation system, causing the system to operate efficiently. Please confirm the number of monitoring systems being requested is Qty 7?

Statement 1 -The equipment being considered for this requirement has one hazardous material analysis system per building sensor (i.e. probe). Each analysis system collects air from a single probe, analyzes the air sample, and directs the system ventilation based on the results of the single probe. Each analysis system does not allow for multiple probes. Therefore, in support of cost reduction we would recommend minimizing the number of probes (analysis systems) to only those necessary. It is suggested to have one probe in any area that has a high probability of generating hazardous dust under normal operations.

Answer 17. Number of sensors required by different systems may come into play. The quantity of sensors has been removed. SOW updated to:

“2.1.6.6. The monitoring system will consist of enough sensors in the enclosure, the walk-in media blast booth and dust collection mechanical room to detect the presence of harmful levels of Cadmium and Chrome. It shall control the ventilation system, causing the system to operate efficiently.”

Statement – The ability to expand the detection for other materials would require modification of the analysis system as opposed to changing of the “sensor heads” (i.e. probes). The system proposed will be capable of detecting Cadmium and Total Chrome.

Question 18. SOW paragraph SOW changed to clarify intent. Now reads:

“2.1.6.2. Future capability to change the target monitored containments to detect beryllium, manganese, lead or thorium due to change in workload. The contractor shall only be required to provide capability for detecting cadmium and chromates for this contract.”

Question 19. SOW paragraph 2.2.2.5 - Parts to be lifted? If so size and weight of the biggest part ? type of lifting device?

Answer 19. Max weight approximately 150 lbs, Max Dimensions 72” x 30” x 20” (LxWxH).

Average parts considerable lighter and smaller. SOW Updated to reflect given dimensions:

“2.2.2.5. Blast Booth shall have provisions for hanging parts to be blasted, as well as a means to lift parts weighing up to 150 lbs with maximum dimensions up to 72 inches onto said hangers.”

Question 20. SOW paragraph 3.7.1 – Is Government providing chilled water for make-up air for enclosure ?

Answer 20. Yes. A 2” chilled water supply and return is in the area, should the project require more, the contractor can tap and route and supply and return line from the chilled water main at the southern end of the building in the mezzanine.

Question 21. SOW paragrap3.15 – Are there floor drainpipe located in the area of sink need to be drained in an industrial waste drain due to presence of hexavalent chrome?

Answer 21. Floor drains are required for emergency eye wash/safety showers and handwash sinks and are supplied by the building. All floor drains flow to industrial waste for water treatment and are independent of sanitary connections.

Question 22. What kind of media does the end user intend to use on Blast booth and all blast cabinets ?

Answer 22. Plastic Media is currently intended for the blast booth and 5 of the blast cabinets.

Currently the final cabinet is planned to use glass bead.

Note: In answering these questions, it was noticed that the PLC control system requirement was omitted from the original. Added back in via section 2.2.9 which reads:

SOW paragraph “2.2.9 Walk-In Media Blast booth shall be controlled via a PLC control system.

2.2.9.1. PLC control system shall consist of at least a 15” touchscreen control panel capable of controlling the following functions:

• Dust Collection Blower on and off

• Media Recovery system on and off

• Media recovery rate

• Blast media flow rate

• Emergency Stop/Panic Stop”

Question 23. The solicitation CLIN structure does not have a place for the requirements in section 2.3 of the scope of work. CLIN 0001 corresponds to section 2.2 Walk in media booth, and CLIN 0002 corresponds to section 2.1 Enclosure, but there is no CLIN for section 2.3 Media Blast cabinets. Which CLIN do we put the costs for section 2.3 in? 0002 the Enclosure?

Answer 23. CLIN 0006 has been incorporated for the Media Blast Cabinets with subCLINs for the Design, Fabrication, Shipping and Install.

Question 24. Would the government consider adding the FAR clause for commercial financing to the contract for use with SLIN 0002AB Enclosure Fabrication?

Answer 24. At this time, the Contracting Officer has determined financing is not necessary for this acquisition and is consistent with customary commercial practices.

SECTION SF 1449 - CONTINUATION SHEET

SOLICITATION/CONTRACT FORM

The required response date/time has changed from 27-Jul-2023 02:00 PM to 02-Aug-

2023 02:00 PM.

SUPPLIES OR SERVICES AND PRICES

CLIN 0006 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

MEDIA BLAST CABINET

FFP

The Contractor shall provide One (1) Walk - In Media Blast Cabinet in accordance with the Statement of Work (SOW) contained herein.

NET AMT

SUBCLIN 0006AA is added as follows:

0006AA Each

MEDIA BLAST CABINET DESIGN

FFP

The Contractor shall Design a Media Blast Cabinet in accordance with the Statement of Work (SOW) contained herein.

Dates of design completion shall be mutually agreed upon.

FOB: Destination

PSC CD: 5350

SUBCLIN 0006AB is added as follows:

0006AB Each

MEDIA BLAST FABRICATION

FFP

The Contractor shall Fabricate a Media Blast Cabinet in accordance with the Statement of Work (SOW) contained herein.

Dates of design completion shall be mutually agreed upon.

SUBCLIN 0006AC is added as follows:

0006AC Each

MEDIA BLAST SHIPPING

FFP

The Contractor shall provide Shipping for a Media Blast Cabinet in accordance with the Statement of Work (SOW) contained herein.

Dates of design completion shall be mutually agreed upon.

SUBCLIN 0006AD is added as follows:

0006AD Each

MEDIA BLAST CABINET INSTALLATION

FFP

The Contractor shall Install a Media Blast Cabinet in accordance with the Statement of Work (SOW) contained herein.

Dates of design completion shall be mutually agreed upon.

DELIVERIES AND PERFORMANCE

The following Delivery Schedule for SUBCLIN 0006AA has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

18 mths. ADC N/A

The following Delivery Schedule for SUBCLIN 0006AB has been added:

DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /

CAGE

The following Delivery Schedule for SUBCLIN 0006AC has been added:

CAGE

The following Delivery Schedule for SUBCLIN 0006AD has been added:

CAGE

INSPECTION AND ACCEPTANCE

The following Acceptance/Inspection Schedule was added for CLIN 0006:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A N/A

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AA:

Destination Government Destination Government

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AB:

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AC:

The following Acceptance/Inspection Schedule was added for SUBCLIN 0006AD:

N/A N/A N/A Government