Pre-Bid Conference Agenda

Text of this file

W912NS15B5001

REPAIR BOUNDARY FENCE

PRE-BID MEETING AGENDA

31 MAY 2019

1:00 p.m.

POINTS OF CONTACT:

Contracting Officer (CO): Ms. Kerrey Renkemeyer (573) 638-9550

Local Contracting Representative: TSgtMark Phillips (314) 527-8031
BCE: LtCol Dan Nelsen (314) 527-8366
FAC MANAGER/RA: MSgt Doug Blasé (314) 527-8373
Project Manager: Mr. John Matthews (314) 527-8226

PROJECT MANAGEMENT: The contractor’s responsibilities include but are not limited to:

Safety:

Comply with any applicable OSHA requirements while on the job-site.

Motor Vehicle safety: seatbelts, speed limits, hands-free cell use.
Speed limit is 15 MPH on Base unless posted differently.
Environmental & Bio-Environmental:
Off-site dumping/removal – Contractor’s dumpsters only.
Contractor needs to check with EMO regarding any hazmat they plan to bring on base; John Morrissey can tell you how much lead time he’d like to have to review HM requests and get them approved. Contractor will have to provide SDS for all hazmat and fill out an AF Form 3952 if it’s not already approved for use on the base.
Suspect contamination - notify EMO or COTR immediately.

Hazardous Storage containers shall be used if storing HAZ-MAT on base.

Discovery of cultural resources, such as human bones or unmarked graves, historic trash pits, stone walls, foundations, or discolored soils, stone tools, ceramics, military uniform items, horseshoes, etc., requires work to cease immediately and for the contractor to call the EMO and Project Manager for review and determination of next steps.

Security Police:
Police checks – allow 5 calendar days for approval.
Submit EALs by e-mail to;
John.e.matthews20.nfg@mail.mil
After a background check is approved, the EAL will be certified and distributed to the main gate.
Contractors will present a valid government issued photo ID to gate guards.
Contractor is responsible for securing site material/tools.

Fire Department:

Burning/Welding Permit – will be required if any open flames or sparks will be generated by the contractor’s work – obtain through Civil Engineering.

Emergency Response: Dial 911 from any Base phone, or 911 from your cell phone.

Real Property Worksheet:

Contractor is responsible for filling out the Real Property Worksheet 1354 and turn in to Base Real Property Manager at the end of the project (Part of Contract Close out in Base Standards).

Keep track of quantities of materials and all costs associated with each item.

PROJECT SPECIFICS:

Contractor Responsibilities: The contractor shall provide the necessary, personnel, equipment, transportation, and materials required to repair by replacement the boundary fence of Jefferson Barracks, approximately 8,650 linear feet. New fence will be 7’ of 6-gauge chain link fencing, with additional two-way outriggers with three strands of barbe wire per side.

Close out Documents: Contractor is responsible for providing;

O&M manuals, warranties, and red line drawings.
Real Property Office will require information about the project to include quantities, descriptions and cost associated with each item tracked. Provide the information as soon as the item has been installed. Real Property items will include but not limited to;

QUESTIONS? COMMENTS? SITE VISIT

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

File details come from the government source that posted it.