CSJTC FTSP Communications Project - Clarifcations Memo1.pdf

PDF 151 KB Posted

Attached to
Communications Infrastructure Installation Project for CSJTC Federal contract opportunity
Solicitation number
W912LR-22-R-6043
Issued by
Department of the Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Communications Infrastructure Installation Project for CSJTC, newest first.
File Type Posted
RFIs as of 19 May 2022.pdf PDF
CSJTC FTSP Communications Project - Clarifcations Memo.pdf PDF
CSJTC AOO IDPs ver. 2.pdf PDF
W912LR-22-R-6043.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PUERTO RICO NATIONAL GUARD

JOINT FORCE HEADQUARTERS

DEPUTY CHIEF OF STAFF FOR INFORMATION

MANAGEMENT 552 BORINQUENEER STREET

FORT BUCHANNAN, PR 00934

NGPR-IMT 26 March 2022

MEMORANDUM THRU United States Property and Fiscal Office for Puerto Rico, Attn:

Purchasing and Contracting Division, Fort Buchanan, PR 00934

SUBJECT: Project W912LR22R6043 Fiber Optic Backbone Upgrade Clarifications

Purpose. To clarify sections in doubt of the project W912LR22R6043 performance work statement.

1. Nomenclature of building 1013 anywhere in the PWS is to be corrected to building 1033.

2. Section 5.3.1.4, the 12 strands fiber optic cable shall end at the outside splicing cabinet, which is at the base of the pole, then the contractor shall fusion it in the available fiber optic cassette. The distance from the manhole to the splicing cabinet is 60 feet approximately.

3. Section 5.3.2.6, the 25 pairs copper cable shall run all the way inside the building 1033 using the existing underground facilities.

4. Section 5.4.1.4, the 12 strands fiber optic cable shall be terminated at the outside splicing cabinet, which is behind the building 510. The contractor shall fusion the fiber optic cable in the available fiber optic cassette.

5. Section 5.4.2.3, the 25 pairs copper cable shall run all the way inside building 510 and terminated on the concrete wall next to the existing network cabinet. The distance from the cable entrance of the building to the network room is approximately 100 feet.

6. Point of contact for this memorandum is Mr. Jesus A. Colon at (787) 529-9346 or via email to jesus.a.colon.civ@army.mil.

Jesus A. Colon

T5 GS-11

Network Specialist

1. Nomenclature of building 1013 anywhere in the PWS is to be corrected to building 1033.
2. Section 5.3.1.4, the 12 strands fiber optic cable shall end at the outside splicing cabinet, which is at the base of the pole, then the contractor shall fusion it in the available fiber optic cassette. The distance from the manhole to the splicing ...
3. Section 5.3.2.6, the 25 pairs copper cable shall run all the way inside the building 1033 using the existing underground facilities.
4. Section 5.4.1.4, the 12 strands fiber optic cable shall be terminated at the outside splicing cabinet, which is behind the building 510. The contractor shall fusion the fiber optic cable in the available fiber optic cassette.
5. Section 5.4.2.3, the 25 pairs copper cable shall run all the way inside building 510 and terminated on the concrete wall next to the existing network cabinet. The distance from the cable entrance of the building to the network room is approximately...
6. Point of contact for this memorandum is Mr. Jesus A. Colon at (787) 529-9346 or via email to jesus.a.colon.civ@army.mil.