W912LR-22-R-6043.pdf
PDF 724 KB Posted
- Attached to
- Communications Infrastructure Installation Project for CSJTC Federal contract opportunity
- Solicitation number
- W912LR-22-R-6043
- Issued by
- Department of the Army National Guard
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| RFIs as of 19 May 2022.pdf | ||
| CSJTC FTSP Communications Project - Clarifcations Memo1.pdf | ||
| CSJTC FTSP Communications Project - Clarifcations Memo.pdf | ||
| CSJTC AOO IDPs ver. 2.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SEE ADDENDUM
(No Collect Calls)
W912LR22R6043 30-Mar-2022
b. TELEPHONE NUMBER 8. OFFER DUE DATE/LOCAL TIME
10:00 AM 06 May 2022
5. SOLICITATION NUMBER 6. SOLICITATION ISSUE DATE
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
STANDARD FORM 1449 (REV. 2/2012)
Prescribed by GSA – FAR (48 CFR) 53.212
(TYPE OR PRINT)
(SIGNATURE OF CONTRACTING OFFICER)
ADDENDA ARE
26. TOTAL AWARD AMOUNT (For Gov t. Use Only )
23.
CODE 10. THIS ACQUISITION IS
SUCH ADDRESS IN OFFER
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT
BELOW IS CHECKED
TELEPHONE NO.
W912LR9. ISSUED BY
18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a. UNLESS BLOCK
7. FOR SOLICITATION
INFORMATION CALL:
a. NAME
JOSEPH E. VEGA
2. CONTRACT NO. 3. AWARD/EFFECTIVE DATE 4. ORDER NUMBER
(TYPE OR PRINT)
30b. NAME AND TITLE OF SIGNER 30c. DATE SIGNED 31b. NAME OF CONTRACTING OFFICER
30a. SIGNATURE OF OFFEROR/CONTRACTOR 31a.UNITED STATES OF AMERICA
0 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1. 52.212-4. FAR 52.212-3. 52.212-5 ARE ATTACHED.
25. ACCOUNTING AND APPROPRIATION DATA
1. REQUISITION NUMBER
20.
ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED.
OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, AND 30
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
0011747525-0002
ARE NOT ATTACHED
27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA ARE ARE NOT ATTACHED
(BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
. YOUR OFFER ON SOLICITATION
28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN
% FOR:SET ASIDE:UNRESTRICTED OR X
SMALL BUSINESSX
17a.CONTRACTOR/ CODE FACILITY
OFFEROR CODE
USPFO FOR PUERTO RICO
P.O. BOX 34069
FT BUCHANAN PR 00934-4069
18a. PAYMENT WILL BE MADE BY CODE
RATED ORDER UNDER
DPAS (15 CFR 700)
13a. THIS CONTRACT IS A
13b. RATING
CODE15. DELIVER TO CODE W58BNE 16. ADMINISTERED BY
12. DISCOUNT TERMS11. DELIVERY FOR FOB DESTINA-
TION UNLESS BLOCK IS
MARKED
SEE SCHEDULE
14. METHOD OF SOLICITATION
RFQ IFB RFPX
G6 (DCSIM)
MR. JESUS COLON
BLDG. 434
SALINAS PR 00751
TEL: 787-529-9346 FAX:
787 277-7659FAX:
TEL: 787 277-7657 SERVICE-DISABLED
VETERAN-OWNED
SMALL BUSINESS
8(A)
HUBZONE SMALL
BUSINESS
SIZE STANDARD:
$16,500,000
NAICS:
238210
X
OFFER DATED
29. AWARD OF CONTRACT: REF.
DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
EMAIL:
TEL:
31c. DATE SIGNED
SEE SCHEDULE
SCHEDULE OF SUPPLIES/ SERVICESITEM NO. QUANTITY UNIT UNIT PRICE AMOUNT
24.22.21.19.
WOMEN-OWNED SMALL BUSINESS (WOSB)
ELIGIBLE UNDER THE WOMEN-OWNED
SMALL BUSINESS PROGRAM
EDWOSB
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS
(CONTINUED)
PAGE 2 OF26
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: ______________________________________________________
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED INSPECTED
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE 32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE 32f . TELEPHONE NUMBER OF AUTHORIZED GOVERNMENT REPRESENTATIVE
37. CHECK NUMBER
FINALPARTIALCOMPLETE
36. PAYMENT35. AMOUNT VERIFIED
CORRECT FOR
34. VOUCHER NUMBER
FINAL
33. SHIP NUMBER
PARTIAL
38. S/R ACCOUNT NUMBER 39. S/R VOUCHER NUMBER 40. PAID BY
41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT
41b. SIGNATURE AND TITLE OF CERTIFYING OFFICER 41c. DATE
42a. RECEIVED BY (Print)
42b. RECEIVED AT (Location)
42c. DATE REC'D (YY/MM/DD) 42d. TOTAL CONTAINERS
STANDARD FORM 1449 (REV. 2/2012) BACK
Prescribed by GSA – FAR (48 CFR) 53.212
AUTHORIZED FOR LOCAL REPRODUCTION
PREVIOUS EDITION IS NOT USABLE
SEE SCHEDULE
20.
SCHEDULE OF SUPPLIES/ SERVICES
21.
QUANTITY UNIT
22. 23.
UNIT PRICE
24.
AMOUNT
19.
ITEM NO.
W912LR22R6043
Section SF 1449 - CONTINUATION SHEET
PERFORMANCE WORK STATEMENT
1.0 General.
1.1 Scope. Perform communications infrastructure installation for different buildings inside Camp Santiago Joint Training Center (CSJTC) to support the full time support personnel (FTSP). The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Section 3.0 as Government Furnished, to perform the communication infrastructure installation for the CSJTC in Salinas, Puerto Rico 00751, as defined in this PWS.
1.2 Background. The Puerto Rico Army National Guard (PRARNG), Deputy Chief of Staff for Information Management (DCSIM) provides Information Technology (IT) support to the full time personnel (FTSP) working areas through the NIPRNET connectivity and analog telephony services.
Right now, there is partial communications infrastructure serviceable to support the FTSP activities.
Also, the existing cabling in some areas needs to be removed. As part of the efforts of the PRARNG- DCSIM to continue bringing the NIPRNET and analog telephony services, the PRARNG-DCSIM is planning the communication infrastructure construction through a contract to provide the necessary services. This will greatly improve the CSJTC capacity to provide a better service and comply with the Department of Defense (DOD) regulations and standards.
1.3 Period of Performance (PoP). The Period of Performance shall not be more than one hundred and twenty two (122) calendar days starting from the Notice to Proceed.
1.4 General Information. 1.4.1 Quality Control (QC). The contractor shall develop and maintain an effective Quality Control Plan (QCP) to ensure services are performed in accordance with this PWS.
The contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The contractor’s QCP is the means by which it assures itself that its work complies with the requirements of the contract. As a minimum, the contractor shall develop QC procedures that address the areas identified in Technical Exhibit 1, Performance Requirements Summary. After acceptance of the QCP, the contractor shall obtain from the Contracting Officer’s (KO) acceptance in writing of any proposed changes to its QCP.
1.4.2 Quality Assurance (QA). The Government shall evaluate the contractor’s performance under this contract in accordance with the Quality Assurance Surveillance Plan (QASP). This plan is primarily focused on what the Government must do to ensure that the contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and acceptable quality level(s) (defect rate(s)).
1.4.3 Recognized Holidays: The following are recognized US holidays. The contractor shall not perform services on these days:
December 31, 2021 New Year’s Day (Observed) January 17, 2022 Martin Luther King, Jr.’s Birthday February 21, 2022 President’s Day May 30, 2022 Memorial Day June 20, 2022 Juneteenth Nat'l Independence Day (Observed) July 4, 2022 Independence Day
September 5, 2022 Labor Day October 10, 2022 Columbus Day November 11, 2021 Veteran’s Day November 24, 2021 Thanksgiving Day December 26, 2021 Christmas Day (Observed)
1.4.4 Place and Performance of Services. The contractor shall provide services between the hours of 0730-1600 on Monday through Friday, except on recognized US holidays or when the Government facility/installation is closed due to local or national emergencies, administrative closings, or similar Government-directed facility/installation closings. Performance shall be at Camp Santiago Joint Training Center, Salinas, Puerto Rico and Fort Allen Training Site, Juana Diaz, Puerto Rico. The contractor shall at all times maintain an adequate work force for the uninterrupted performance of all tasks defined within this PWS when the Government facility/installation is not closed for the above reasons. When hiring personnel, the contractor shall keep in mind that the stability and continuity of the work force are essential. Telecommuting is not authorized.
1.4.5 Unscheduled gate closures by the Security Police may occur at any time causing all personnel entering or exiting a closed installation to experience a delay. This cannot be predicted or prevented.
Contractors are not compensated for unexpected closures or delays. Vehicles operated by contractor personnel are subject to search pursuant to applicable regulations. Any moving violation of any applicable motor vehicle regulation may result in the termination of the contractor employee’s installation driving privileges.
1.4.6 The contractor’s employees shall become familiar with and obey the regulations of the installation; including fire, traffic, safety and security regulations while on the installation. Contractor employees should only enter restricted areas when required to do so and only upon prior approval.
All contractor employees shall always carry proper identification with them. The contractor shall ensure compliance with all regulations and orders of the installation which may affect performance.
1.4.7 Security Requirements. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DOD, HQDA and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.
1.4.8 COMSEC/IT Security. All communications with DOD organizations are subject to communications security (COMSEC) review. All telephone communications networks are continually subject to intercept by unfriendly intelligence organizations. DOD has authorized the military departments to conduct COMSEC monitoring and recording of telephone calls originating from, or terminating at, DOD organizations. Therefore, the contractor is advised that in any time the contractor place or receive a call they are subject to COMSEC procedures. The contractor shall ensure wide and frequent dissemination of the above information to all employees dealing with DOD information. The contractor shall abide by all Government regulations concerning the authorized use of the Government's computer network, including the restriction against using the network to recruit Government personnel or advertise job openings.
1.4.9 Use of Government Information Systems (IS) and access to Government networks is a revocable privilege, not a right. This contract does not require use of Government Information Systems.
1.4.10 Protection of Personally Identifiable Information (PII). The contractor shall protect all Personally Identifiable Information (PII) encountered in the performance of services in accordance with DFARS 224.103 and DoD 5400.11, Department of Defense Privacy Program, and DoD 5400.11-R. If a PII breach results from the contractor’s violation of the aforementioned policies, the contractor shall bear all notification costs, call-center support costs, and credit monitoring service costs for all individuals who’s PII has been compromised.
1.4.11 Antiterrorism Level 1 Awareness Training (AT). All contractor employees requiring access to Army Installations, facilities, and controlled access areas shall complete Level 1 AT within 10 calendar days after contract start date and within 10 calendar days of new employees commencing performance. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 AT is available at https://jko.jten.mil/courses/atl1/launch.html.
1.4.12 iWATCH Training. The contractor with an area of performance within an Army – controlled installation, facilities or area shall brief all employees on the local iWATCH program. This local developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the COR or the KO. This training shall be completed within 10 calendar days of contract award and within 10 calendar days of new employees commencing performance. The contractor shall report completion for each affected contractor employee and subcontractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training.
1.4.13 OPSEC Training. In accordance with AR 530-1, Operations Security, new contractor employees shall complete Level I OPSEC training within 10 calendar days of their reporting for duty and annually thereafter. The contractor shall submit certificates of completion for each affected contractor employee, to the COR, or to the KO if a COR is not assigned, within 10 calendar days after completion of training. Level 1 OPSEC training is available at https://securityawareness.usalearning.gov/opsec/index.htm.
1.4.14 Physical Security. The contractor shall safeguard all Government property provided for contractor use. At the close of each work period, Government facilities, equipment and materials shall be secured.
1.4.15 Key Control. This PWS does not require handling of keys.
1.4.16 Special Qualifications. The Government does not provide training to contractors. Contractors must ensure that any personnel performing under a contract are fully trained, and qualified to provide services.
1.5 Post Award Conference/Periodic Progress Meetings. The contractor agrees to attend any post award conference convened by the KO in accordance with Federal Acquisition Regulations Subpart
42.5. The KO, Contracting Officer’s Representative (COR), and other Government personnel, as appropriate, may meet periodically with the contractor to review the contactor’s performance. At these meetings, the Contacting Officer will apprise the contractor of how the Government views the contractor’s performance and the contractor shall apprise the problems of Government, if any, being experienced, the contractor shall resolve outstanding issues raised by the Government. Contractor attendance at these meetings shall be at no additional cost to the Government.
1.6 Contract Manager (CM). The contactor shall designate a CM who shall ensure performance under this contract. The name of this person, and an alternate who shall act for the contractor when the CM is absent, shall be designated in writing to the KO within 10 calendar days after contract award. The CM or alternate shall have full authority to act for the contractor on all contract matters relating to daily operation of this contract. The CM shall work through the COR, (or the KO if a COR is not assigned), to resolve issues, receive technical instructions, and ensure adequate performance of services. The CM shall ensure that contractor employees do not perform any services outside the scope of the contract without an official modification issued by the KO. The CM shall ensure contractor employees understand that services performed outside the scope of the contract are performed wholly at the expense of the contractor.
1.7 Identification of Contractor Employees. All contractor personnel attending meetings, answering Government telephones and working in other situations where their contractor status is not obvious to third parties are required to identify themselves as such to avoid creating an impression that they are Government employees. The contractor shall ensure that all documents or reports produced by contractor personnel are suitably marked as contractor products or that contractor participation is appropriately disclosed. The contractor’s status as a “contractor” shall be predominantly displayed in all correspondence types (to include signature blocks on e- mail) and dealings with Government or non-Government entities/ Contractor personnel shall wear identification badges distinguishing themselves as such. The badges shall have the company name, employee name and the word “contractor” displayed. The contractor shall retrieve all identification media (including vehicle passes) from their employees who depart employment for any reason. All identification media (i.e., badges and vehicle passes shall be returned to the COR within the 10 days of an employee’s departure).
1.8 Combating Trafficking in Persons. The United States Government has adopted a zero tolerance policy regarding trafficking in persons. Contractors and contractor employees shall not engage in any forms of trafficking in persons during the period of performance of the contract; procure commercial sex acts during the period of performance of the contract; or use forced labor in the performance of the contract. The Contractor shall notify its employees of the United States Government’s zero tolerance policy, the actions that will be taken against employees for violations of this policy. Such actions may include, but are not limited to, removal from the contract, reduction in benefits, or termination of employment. The Contractor shall take appropriate action, up to and including termination, against employees or subcontractors that violate the US Government policy as described at FAR 22.17. Contractor shall complete the following online training within 10 calendar days after contract award: Course number is A-US1328-A; available at: https://jko.jten.mil. 1.9 Contractor Travel: Not authorized on this PWS.
1.10 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership /copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the contractor without written permission from the KO. All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. Provide a copy 10 calendar days after contract completion.
This right does not abrogate any other Government rights.
1.11 Organizational Conflicts of Interest (OCI): The contractor and subcontractor personnel performing services under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent OCIs, as defined in FAR Subpart 9.5. The contractor shall notify the KO immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the KO to avoid or mitigate any such OCI. The contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the KO and in the event the KO unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the KO may affect other remedies as he or she deems necessary, including prohibiting the contractor from participation in subsequent contracted requirements which may be affected by the
OCI.
2.0 Definitions and Acronyms.
2.1 Definitions. 2.1.1 CONTRACTOR. A supplier or vendor awarded a contract to provide specific supplies or services to the government. The term used in this contract refers to the prime.
2.1.2 CONTRACTING OFFICER (KO). A person with authority to enter into, administer, and or terminate contracts, and make related determinations and findings on behalf of the government. Note:
The only individual who can legally bind the government.
2.1.3 CONTRACTING OFFICER'S REPRESENTATIVE (COR). An employee of the U.S.
Government designated by the KO to monitor contractor performance. Such appointment shall be in writing and shall state the scope of authority and limitations. This individual has authority to provide technical direction to the Contractor as long as that direction is within the scope of the contract, does not constitute a change, and has no funding implications. This individual does NOT have authority to change the terms and conditions of the contract.
2.1.4 DEFECTIVE SERVICE. A service output that does not meet the standard of performance associated with the Performance Work Statement.
2.1.5 DELIVERABLE. Anything that can be physically delivered and includes non- manufactured things such as meeting minutes or reports.
2.1.6 KEY PERSONNEL. Contractor personnel that are evaluated in a source selection process and that may be required to be used in the performance of a contract by the Key Personnel listed in the PWS. When key personnel are used as an evaluation factor in best value procurement, an offer can be rejected if it does not have a firm commitment from the persons that are listed in the proposal.
2.1.7 PHYSICAL SECURITY. Actions that prevent the loss or damage of Government property.
2.1.8 QUALITY ASSURANCE. The government procedures to verify that services being performed by the Contractor are performed according to acceptable standards.
2.1.9 QUALITY ASSURANCE SURVEILLANCE PLAN (QASP). An organized written document specifying the surveillance methodology to be used for surveillance of contractor performance.
2.1.10 QUALITY CONTROL. All necessary measures taken by the Contractor to assure that the quality of an end product or service shall meet contract requirements.
2.1.11 SUBCONTRACTOR. One that enters into a contract with a prime contractor. The Government does not have privity of contract with the subcontractor.
2.1.12 WORKDAY. The number of hours per day the Contractor provides services in accordance with the contract.
2.1.13 WORK WEEK. Monday through Friday, unless specified otherwise.
2.2 Acronyms.
AQL Acceptable Quality Level ARNG Army National Guard AR Army Regulation CFR Code of Federal Regulations CM Contract Manager COR Contracting Officer Representative COTR Contracting Officer's Technical Representative DA Department of the Army DD250 Department of Defense Form 250 (Receiving Report) DD254 Department of Defense Contract Security Requirement List DFARS Defense Federal Acquisition Regulation Supplement DOD Department of Defense FAR Federal Acquisition Regulation FPCON Force Protection Condition IT Information Technology JFHQ Joint Forces Headquarters KO Contracting Officer MDF Medium Density Fiber Optic NLT Not Later Than OPSEC Operations Security OSP Outside Plant PII Protection of Personally Identifiable Information POC Point of Contact PRS Performance Requirements Summary PWS Performance Work Statement QA Quality Assurance QASP Quality Assurance Surveillance Plan QC Quality Control SME Subject Matter Expert TE Technical Exhibit
3.0 Government Furnished Property, Material, Equipment and Services (GFP/M/E/S). The Government will provide the property, material, equipment, and/or services listed below solely for the purpose of performance under this contract.
3.1 Property: None.
3.2 Materials: None.
3.3 Equipment: None.
3.4 Services: None.
3.5 Utilities: All utilities in the facility will be available for the contactor’s use in the performance of this contract. The contractor shall instruct employees in utilities conservation practices. The contractor shall operate under conditions that preclude the waste of utilities, which include turning off the water faucets or valves after using the required amount.
4.0 Contractor Furnished Property, Materials, and Equipment (CFP/M/E). 4.1 General: Except for those items specifically stated to be Government-Furnished in Section 3.0, the contractor shall furnish everything required to perform these services as indicated in Paragraph 1.1.
5.0 Requirements
5.1 Enterprise-wide Contractor Manpower Reporting Application (ECMRA) 5.1.1 The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for the Puerto Rico Army National Guard via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: http://www.ecmra.mil/
Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the FY, all data shall be reported no later than October 31 of each calendar year, beginning with 2013. Contractors may direct questions to the help desk at help desk at:
http://www.ecmra.mil/
5.2 CSJTC Old Broken Fiber Optic and Copper Cables Removal and Disposal 5.2.1 The contractor shall remove, through the new SMF installation and telephone cable route; wood poles not in service, not serviceable and old hanging fiber optic cables, copper cables not in service, and debris. DCSIM personnel shall determine which cables can be removed.
5.2.2 Contractor shall be responsible to dispose the removed poles, cables and debris.
5.3 Building 880 Backbones 5.3.1 Fiber Optic Installation from Building 1013 to Building 880
5.3.1.1 The contractor shall provide and install an OSP 12 strands single mode (SMF) fiber optic cable from building 1013 to building 880.
5.3.1.2 The contractor shall use the existing pole infrastructure and underground facilities from building 1013 to building 880.
5.3.1.3 The contractor shall provide the fiber optic tray and install it in an existing network cabinet and terminate the 12 strands single mode fiber optic cable with LC connectors to include its related hardware to secure and protect the fiber optic cable inside building 880.
5.3.1.4 The contractor shall fusion the fiber optic cable inside the intermediate distribution point (IDP) to an existing fiber optic cable that run to inside building 1013.
5.3.1.5 The contractor shall provide the fiber optic tray and install it in an existing network cabinet and terminate the 12 strands single mode fiber optic cable with LC connectors to include its related hardware to secure and protect the fiber optic cable inside building 1013.
5.3.1.6 The contractor shall provide two (2) LC-LC SM fiber optic patch cables to this installation.
5.3.1.7 The contractor shall label the tray related to the installation of the 12 strands single mode fiber optic cable inside the building 880, inside the IDP in front of building 1013, and the cable tray inside building 1013.
5.3.1.8 Labeling shall consist of a durable self-adhesive machine generated printout label or better quality. Handwriting labels are not authorized.
5.3.2 OSP 25 Pairs Telephone Cable Installation From Building 1013 to building 880 5.3.2.1 The contractor shall provide and install a 25 pairs copper telephone cable from telecommunication room in building 1013 to building 880.
5.3.2.2 The contractor shall use the existing pole infrastructure and underground facilities from building 1013 to building 880.
5.3.2.3 Contractor shall provide and terminate the copper telephone cable with a 110-telephone protected block in building 880.
5.3.2.4 Contractor shall provide and install line terminal protector modules to the 110-telephone protected block in building 880.
5.3.2.5 Contractor shall provide and perform grounding and bonding to the line terminal protector in building 880 connecting it to the existing ground bar.
5.3.2.6 Contractor shall provide and terminate the copper telephone cable with a 110-telephone block in building 1013.
5.3.2.7 The contractor shall label the 110-telephone block related to the installation inside the building 880 as “TO BLDG 1013”.
5.3.2.8 The contractor shall label the 110-telephone block related to the installation inside the building 1013 as “TO BLDG 880”
5.3.2.9 Labeling shall consist of a durable self-adhesive machine generated printout label or better quality. Handwriting labels are not authorized.
5.4 Building 510 Backbones 5.4.1 Fiber Optic Installation from Building 100 to Building 510
5.4.1.1 The contractor shall provide and install an OSP 12 strands single mode (SMF) fiber optic cable from building 100 to building 510.
5.4.1.2 The contractor shall use the existing pole infrastructure and underground facilities from building 100 to building 510.
5.4.1.3 The contractor shall provide the fiber optic tray and install it in an existing network cabinet and terminate the 12 strands single mode fiber optic cable with LC connectors to include its fan out kits and related hardware to secure and protect the fiber optic cable inside building 100.
5.4.1.4 The contractor shall provide the fiber optic tray and install it in an existing network cabinet and terminate the 12 strands single mode fiber optic cable with LC connectors to include its fan out kits and related hardware to secure and protect the fiber optic cable inside building 510.
5.4.1.5 The contractor shall provide LC-LC SM fiber optic patch cables and patch one pair of the single mode fiber optic cable at each end.
5.4.1.6 The contractor shall label the fiber optic tray related to the installation of the 12 strands single mode fiber optic cable inside the building 100, and in the building 510.
5.4.1.7 Labeling shall consist of a durable self-adhesive machine generated printout label or better quality. Handwriting labels are not authorized.
5.4.2 OSP 25 Pairs Telephone Cable Installation From Building 100 to building 510 5.4.2.1 The contractor shall provide and install a 25 pairs copper telephone cable from telecommunication room in building 100 to building 510.
5.4.2.2 The contractor shall use the existing pole infrastructure facilities from building 100 to building 510.
5.4.2.3 Contractor shall provide and terminate the copper telephone cable with a 110-telephone protected block in building 510.
5.4.2.4 Contractor shall provide and install line terminal protector modules to the 110-telephone protected block in building 510.
5.4.2.5 Contractor shall provide and perform grounding and bonding to the line terminal protector in building 510.
5.4.2.6 Contractor shall provide and terminate the copper telephone cable with a 110-telephone block in building 100.
5.4.2.7 The contractor shall label the 110-telephone block related to the installation inside the building 510 as “TO BLDG 100”.
5.4.2.8 The contractor shall label the 110-telephone block related to the installation inside the building 100 as “TO BLDG 510”
5.4.2.9 Labeling shall consist of a durable self-adhesive machine generated printout label or better
5.5 Fiber Optic Cable Installation for Buildings 16, 31, 165, 207, 598, 745 5.5.1.1 The contractor shall provide and install an OSP 6 strands single mode (SMF) fiber optic cable from the distribution building to end point building as listed in item 5.5.1.9.
5.5.1.2 The contractor shall use the existing pole infrastructure facilities from the IDP building to the end point buildings as listed in the item 5.5.1.9.
5.5.1.3 The contractor shall provide the necessary fiber optic trays to accommodate the amount of fiber optic cables from the distributed buildings and install them in an existing rack and terminate the 6 strands single mode fiber optic cable with LC connectors to include its fan out kits and related hardware to secure and protect the fiber optic cables inside the network rack of the assigned IDP building.
5.5.1.4 The contractor shall install two (2) 24 inches network cabinets and the fiber optic tray in the buildings identified in item 5.5.1.9. The network cabinets are available in the PRARNG and shall be picked up by the contractor.
5.5.1.5 The contractor shall terminate the 6 strands single mode fiber optic cables with LC connectors to include its fan out kits and related hardware to secure and protect the fiber optic cable inside the listed buildings.
5.5.1.6 The contractor shall provide LC-LC SM fiber optic patch cables and patch one pair of the single mode fiber optic cable at each end in the buildings.
5.5.1.7 The contractor shall label the fiber optic tray related to the installation of the 6 strands single mode fiber optic cable inside the network rack of the assigned IDP building, and in the buildings listed in item 5.5.1.9.
5.5.1.8 Labeling shall consist of a durable self-adhesive machine generated printout label or better
5.5.1.9 Table 1: Building list.
Building Need SMF Tray Network cabinet Connects to IDP building
16 Yes Network cabinet in place.
31 Yes 24 inches network cabinet available.
Needs installation.
165 Yes 24 inches network cabinet available.
Needs installation.
207 Yes Network cabinet in place.
598 Yes Network cabinet in place.
745 Yes Network cabinet in place.
5.5.1.10 The contractor shall provide and install fire block foam sealant to cover all orifices created by drilling the walls of the orderlies in order to give entrance to the fiber optic cable inside the buildings.
5.6 Fiber optic cables testing certification 5.6.1.1 The contractor shall test all fiber optic cables worked in this PWS.
5.6.1.2 The tests shall comply with the ANSI/EIA/TIA 568 industry standards for single mode fiber optic cable run.
5.6.1.3 The contractor shall provide the results of all cables tested in this PWS in digital format or hard copy to the COR.
5.7 Warranty 5.7.1.1 Contractor shall provide in written, at least, one year of warranty in service, installation and components of the single mode fiber optic cable and the telephone copper cable.
5.7.1.2 Single mode fiber optic cable manufacturer shall provide 20 years warranty, and the contractor shall be the point of contact to claim the warranty.
5.7.1.3 Telephone copper cable manufacturer shall provide 20 years warranty, and the contractor shall be the point of contact to claim the warranty.
Technical Exhibit 1
Performance Requirements Summary
This Performance Requirements Summary includes performance standards applicable to this PWS.
The Government will use these standards to determine contractor performance and will compare contractor performance to the Acceptable Quality Level (AQL).
PWS
Paragraph
Task Performance Standard
Acceptable Quality Levels
(AQL)
Surveillance Method By Whom
Enterprise-wide Contractor Manpower Reporting Application
(ECMRA)
5.1
Report ALL contractor labor hours.
100% 100% Inspection /
KO
CSJTC Old Broken Fiber Optic and Copper Cables Removal and Disposal 5.2
Remove old wood poles fiber optic cables and copper cables, not in service.
100% 80% Inspection /
COR
Building 880 Backbones 5.3
Provide and install OSP 12 strands fiber optic and 25 pairs copper cables
100% 90% Inspection /
COR
Building 510 Backbones 5.4
Provide and install OSP 12 strands fiber optic and 25 pairs copper cables
100% 90% Inspection /
COR
Fiber Optic Installation for Buildings 16, 31, 165, 207, 598, 5.5
Provide and install OSP 6 strands fiber optic
100% 80% Inspection /
COR
Technical Exhibit 2
Deliverables Schedule
Deliverable Frequency # of Copies Medium / Format Submit To Fiber optics cables
65 days from Contract award
NA Photo and COR evaluation
COR
Copper Cables 65 days from Contract award
NA Photo and COR evaluation
COR
SMF Tray and Cable termination
95 days from Contract award
NA Photo and COR evaluation
COR
SMF and Copper Labeling
100 days from Contract award
NA Photo and COR evaluation
COR
Fiber Optic and Copper Cables Tests
110 days from Contract award
1 Copy per Document
Digital or hard copy report and COR evaluation
COR
Warranty Documentation
120 days from Contract award.
1 Copy per Document
Digital or hard copy report and COR evaluation
COR
---------------- End of Performance Work Statement (PWS) --------------
ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT
0001 1 Job Communications Infrastructure Install
FFP
Perform communications infrastructure installation for different buildings inside Camp Santiago Joint Training Center (CSJTC) to support the full time support personnel (FTSP). The contractor shall provide all personnel, equipment, tools, materials, supervision, and quality control necessary, except as specified in Section
3.0 as Government Furnished, to perform the communication infrastructure installation for CSJTC in Salinas, Puerto Rico as defined in PWS.
FOB: Destination
PURCHASE REQUEST NUMBER: 0011747525-0002
PSC CD: 5995
NET AMT
INSPECTION AND ACCEPTANCE TERMS
Supplies/services will be inspected/accepted at:
CLIN INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY
0001 N/A N/A Destination Government
DELIVERY INFORMATION
CLIN DELIVERY DATE QUANTITY SHIP TO ADDRESS DODAAC /
CAGE
0001 POP 20-MAY-2022 TO
19-SEP-2022
N/A G6 (DCSIM)
MR. JESUS COLON
BLDG. 434
SALINAS PR 00751
787-529-9346 FOB: Destination
W58BNE
CLAUSES INCORPORATED BY REFERENCE
52.204-24 Representation Regarding Certain Telecommunications and
Video Surveillance Services or Equipment
DEC 2021
52.204-25 Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment
DEC 2021
52.204-26 Covered Telecommunications Equipment or Services-- Representation.
OCT 2020
52.209-10 Prohibition on Contracting With Inverted Domestic Corporations
NOV 2015
52.212-3 Offeror Representations and Certifications--Commercial Products and Commercial Services
DEC 2021
52.212-4 Contract Terms and Conditions--Commercial Products and Commercial Services
DEC 2021
52.219-6 Notice Of Total Small Business Set-Aside NOV 2020 52.219-8 Utilization of Small Business Concerns OCT 2018 52.222-19 Child Labor -- Cooperation with Authorities and Remedies JAN 2022 52.222-26 Equal Opportunity SEP 2016 52.222-50 Combating Trafficking in Persons DEC 2021 52.232-40 Providing Accelerated Payments to Small Business
Subcontractors
DEC 2021
52.243-1 Changes--Fixed Price AUG 1987 52.247-34 F.O.B. Destination NOV 1991 252.203-7000 Requirements Relating to Compensation of Former DoD
Officials
SEP 2011
252.204-7006 Billing Instructions OCT 2005 252.204-7012 Safeguarding Covered Defense Information and Cyber
Incident Reporting
DEC 2019
252.204-7018 Prohibition on the Acquisition of Covered Defense Telecommunications Equipment or Services
JAN 2021
252.211-7003 Item Unique Identification and Valuation MAR 2016 252.232-7003 Electronic Submission of Payment Requests and Receiving
Reports
DEC 2018
252.232-7010 Levies on Contract Payments DEC 2006
CLAUSES INCORPORATED BY FULL TEXT
52.212-5 CONTRACT TERMS AND CONDITIONS REQUIRED TO IMPLEMENT STATUTES OR
EXECUTIVE ORDERS--COMMERCIAL PRODUCTS AND COMMERCIAL SERVICES (JAN 2022)
(a) The Contractor shall comply with the following Federal Acquisition Regulation (FAR) clauses, which are incorporated in this contract by reference, to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services:
(1) 52.203-19, Prohibition on Requiring Certain Internal Confidentiality Agreements or Statements (JAN 2017) (section 743 of Division E, Title VII, of the Consolidated and Further Continuing Appropriations Act, 2015 (Pub. L.
113-235) and its successor provisions in subsequent appropriations acts (and as extended in continuing resolutions)).
(2) 52.204-23, Prohibition on Contracting for Hardware, Software, and Services Developed or Provided by Kaspersky Lab and Other Covered Entities (NOV 2021) (Section 1634 of Pub. L. 115-91).
(3) 52.204-25, Prohibition on Contracting for Certain Telecommunications and Video Surveillance Services or Equipment. (NOV 2021) (Section 889(a)(1)(A) of Pub. L. 115-232).
(4) 52.209-10, Prohibition on Contracting with Inverted Domestic Corporations (Nov 2015).
(5) 52.233-3, Protest After Award (AUG 1996) (31 U.S.C. 3553).
(6) 52.233-4, Applicable Law for Breach of Contract Claim (OCT 2004) (Public Laws 108-77 and 108-78 (19 U.S.C. 3805 note)).
(b) The Contractor shall comply with the FAR clauses in this paragraph (b) that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services: [Contracting Officer check as appropriate.]
___ (1) 52.203-6, Restrictions on Subcontractor Sales to the Government (JUN 2020), with Alternate I (NOV 2021) (41 U.S.C. 4704 and 10 U.S.C. 2402).
XXX (2) 52.203-13, Contractor Code of Business Ethics and Conduct (NOV 2021) (41 U.S.C. 3509).
___ (3) 52.203-15, Whistleblower Protections under the American Recovery and Reinvestment Act of 2009 (JUN 2010) (Section 1553 of Pub. L. 111-5). (Applies to contracts funded by the American Recovery and Reinvestment Act of 2009.)
___ (4) 52.204-10, Reporting Executive Compensation and First-Tier Subcontract Awards (JUN 2020) (Pub. L.
109-282) (31 U.S.C. 6101 note).
___ (5) [Reserved]
___ (6) 52.204-14, Service Contract Reporting Requirements (Oct 2016) (Pub. L. 111-117, section 743 of Div. C).
___ (7) 52.204-15, Service Contract Reporting Requirements for Indefinite-Delivery Contracts (Oct 2016) (Pub.
L. 111-117, section 743 of Div. C).
___ (8) 52.209-6, Protecting the Government's Interest When Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment. (NOV 2021) (31 U.S.C. 6101 note).
___ (9) 52.209-9, Updates of Publicly Available Information Regarding Responsibility Matters (OCT 2018) (41 U.S.C. 2313).
____ (10) [Reserved]
____ (11) 52.219-3, Notice of HUBZone Set-Aside or Sole-Source Award (SEP 2021) (15 U.S.C. 657a).
____ (12) 52.219-4, Notice of Price Evaluation Preference for HUBZone Small Business Concerns (SEP 2021) (if the offeror elects to waive the preference, it shall so indicate in its offer) (15 U.S.C. 657a).
____ (13) [Reserved]
____ (14)(i) 52.219-6, Notice of Total Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-6.
____ (15)(i) 52.219-7, Notice of Partial Small Business Set-Aside (NOV 2020) (15 U.S.C. 644).
____ (ii) Alternate I (MAR 2020) of 52.219-7.
____ (16) 52.219-8, Utilization of Small Business Concerns (OCT 2018) (15 U.S.C. 637(d)(2) and (3)).
____ (17)(i) 52.219-9, Small Business Subcontracting Plan (NOV 2021) (15 U.S.C. 637(d)(4)).
____ (ii) Alternate I (NOV 2016) of 52.219-9.
____ (iii) Alternate II (NOV 2016) of 52.219-9.
____ (iv) Alternate III (JUN 2020) of 52.219-9.
____ (v) Alternate IV (SEP 2021) of 52.219-9.
XXX (18) (i) 52.219-13, Notice of Set-Aside of Orders (MAR 2020) (15 U.S.C. 644(r)).
____ (ii) Alternate I (MAR 2020) of 52.219-13.
____ (19) 52.219-14, Limitations on Subcontracting (SEP 2021) (15 U.S.C. 657s).
____ (20) 52.219-16, Liquidated Damages—Subcontracting Plan (SEP 2021) (15 U.S.C. 637(d)(4)(F)(i)).
____ (21) 52.219-27, Notice of Service-Disabled Veteran-Owned Small Business Set-Aside (SEP 2021) (15 U.S.C.
657f).
____ (22) (i) 52.219-28, Post-Award Small Business Program Rerepresentation (SEP 2021) (15 U.S.C. 632(a)(2)).
____ (ii) Alternate I (MAR 2020) of 52.219-28.
____ (23) 52.219-29, Notice of Set-Aside for, or Sole-Source Award to, Economically Disadvantaged Women- Owned Small Business Concerns (SEP 2021) (15 U.S.C. 637(m)).
____ (24) 52.219-30, Notice of Set-Aside for, or Sole-Source Award to, Women-Owned Small Business Concerns Eligible Under the Women-Owned Small Business Program (SEP 2021) (15 U.S.C. 637(m)).
____ (25) 52.219-32, Orders Issued Directly Under Small Business Reserves (MAR 2020) (15 U.S.C. 644(r)).
____ (26) 52.219-33, Nonmanufacturer Rule (SEP 2021) (15 U.S.C. 657s).
XXX (27) 52.222-3, Convict Labor (JUN 2003) (E.O. 11755).
XXX (28) 52.222-19, Child Labor--Cooperation with Authorities and Remedies (JAN 2022) (E.O. 13126).
____ (29) 52.222-21, Prohibition of Segregated Facilities (APR 2015).
XXX (30)(i) 52.222-26, Equal Opportunity (SEPT 2016) (E.O. 11246).
____ (ii) Alternate I (FEB 1999) of 52.222-26.
____ (31)(i) 52.222-35, Equal Opportunity for Veterans (JUN 2020) (38 U.S.C. 4212).
____ (ii) Alternate I (JUL 2014) of 52.222-35.
____ (32)(i) 52.222-36, Equal Opportunity for Workers with Disabilities (JUN 2020) (29 U.S.C. 793).
____ (ii) Alternate I (JUL 2014) of 52.222-36.
____ (33) 52.222-37, Employment Reports on Veterans (JUN 2020) (38 U.S.C. 4212).
____ (34) 52.222-40, Notification of Employee Rights Under the National Labor Relations Act (DEC 2010) (E.O.
13496).
XXX (35)(i) 52.222-50, Combating Trafficking in Persons (NOV 2021) (22 U.S.C. chapter 78 and E.O. 13627).
____ (ii) Alternate I (MAR 2015) of 52.222-50 (22 U.S.C. chapter 78 and E.O. 13627).
____ (36) 52.222-54, Employment Eligibility Verification (NOV 2021). (E. O. 12989). (Not applicable to the acquisition of commercially available off-the-shelf items or certain other types of commercial products or commercial services as prescribed in FAR 22.1803.)
____ (37)(i) 52.223-9, Estimate of Percentage of Recovered Material Content for EPA–Designated Items (MAY 2008) (42 U.S.C. 6962(c)(3)(A)(ii)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (ii) Alternate I (MAY 2008) of 52.223-9 (42 U.S.C. 6962(i)(2)(C)). (Not applicable to the acquisition of commercially available off-the-shelf items.)
____ (38) 52.223-11, Ozone-Depleting Substances and High Global Warming Potential Hydrofluorocarbons (JUN 2016) (E.O. 13693).
____ (39) 52.223-12, Maintenance, Service, Repair, or Disposal of Refrigeration Equipment and Air Conditioners
(JUN 2016) (E.O. 13693).
____ (40) (i) 52.223-13, Acquisition of EPEAT® Registered Imaging Equipment (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (OCT 2015) of 52.223-13.
____ (41)(i) 52.223-14, Acquisition of EPEAT® Registered Televisions (JUN 2014) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-14.
____ (42) 52.223-15, Energy Efficiency in Energy-Consuming Products (MAY 2020) (42 U.S.C. 8259b).
____ (43)(i) 52.223-16, Acquisition of EPEAT®-Registered Personal Computer Products (OCT 2015) (E.O.s 13423 and 13514).
____ (ii) Alternate I (JUN 2014) of 52.223-16.
XXX (44) 52.223-18, Encouraging Contractor Policies to Ban Text Messaging While Driving (JUN 2020) (E.O.
13513).
____ (45) 52.223-20, Aerosols (JUN 2016) (E.O. 13693).
____ (46) 52.223-21, Foams (JUN 2016) (E.O. 13693).
____ (47)(i) 52.224-3, Privacy Training (JAN 2017) (5 U.S.C. 552a).
____ (ii) Alternate I (JAN 2017) of 52.224-3.
____ (48) 52.225-1, Buy American--Supplies (NOV 2021) (41 U.S.C. chapter 83).
____ (49) (i) 52.225-3, Buy American--Free Trade Agreements--Israeli Trade Act (NOV 2021) (41 U.S.C. chapter 83, 19 U.S.C. 3301 note, 19 U.S.C. 2112 note, 19 U.S.C. 3805 note, 19 U.S.C. 4001 note, Pub. L. 103-182, 108-77, 108-78, 108-286, 108-302, 109-53, 109-169, 109-283, 110-138, 112-41, 112-42, and 112-43.
____ (ii) Alternate I (JAN 2021) of 52.225-3.
____ (iii) Alternate II (JAN 2021) of 52.225-3.
____ (iv) Alternate III (JAN 2021) of 52.225-3.
____ (50) 52.225-5, Trade Agreements (OCT 2019) 19 U.S.C. 2501, et seq., 19 U.S.C. 3301 note).
____ (51) 52.225-13, Restrictions on Certain Foreign Purchases (FEB 2021) (E.O.'s, proclamations, and statutes administered by the Office of Foreign Assets Control of the Department of the Treasury).
____ (52) 52.225-26, Contractors Performing Private Security Functions Outside the United States (OCT 2016) (Section 862, as amended, of the National Defense Authorization Act for Fiscal Year 2008; 10 U.S.C. 2302 Note).
____ (53) 52.226-4, Notice of Disaster or Emergency Area Set-Aside (NOV 2007) (42 U.S.C. 5150
____ (54) 52.226-5, Restrictions on Subcontracting Outside Disaster or Emergency Area (NOV 2007) (42 U.S.C.
5150).
____ (55) 52.229-12, Tax on Certain Foreign Procurements (FEB 2021).
____ (56) 52.232-29, Terms for Financing of Purchases of Commercial Products and Commercial Services (NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
____ (57) 52.232-30, Installment Payments for Commercial Products and Commercial Services (NOV 2021) (41 U.S.C. 4505, 10 U.S.C. 2307(f)).
XXX (58) 52.232-33, Payment by Electronic Funds Transfer—System for Award Management (OCT 2018) (31 U.S.C. 3332).
____ (59) 52.232-34, Payment by Electronic Funds Transfer—Other than System for Award Management (JUL 2013) (31 U.S.C. 3332).
____ (60) 52.232-36, Payment by Third Party (MAY 2014) (31 U.S.C. 3332).
____ (61) 52.239-1, Privacy or Security Safeguards (AUG 1996) (5 U.S.C. 552a).
____ (62) 52.242-5, Payments to Small Business Subcontractors (JAN 2017)(15 U.S.C. 637(d)(13)).
____ (63)(i) 52.247-64, Preference for Privately Owned U.S.-Flag Commercial Vessels (NOV 2021) (46 U.S.C.
55305 and 10 U.S.C. 2631).
____ (ii) Alternate I (APR 2003) of 52.247-64.
____ (iii) Alternate II (NOV 2021) of 52.247-64.
(c) The Contractor shall comply with the FAR clauses in this paragraph (c), applicable to commercial services, that the Contracting Officer has indicated as being incorporated in this contract by reference to implement provisions of law or Executive orders applicable to acquisitions of commercial products and commercial services: [Contracting Officer check as appropriate.]
_____ (1) 52.222-41, Service Contract Labor Standards (AUG 2018) (41 U.S.C. chapter 67).
_____ (2) 52.222-42, Statement of Equivalent Rates for Federal Hires (MAY 2014) (29 U.S.C. 206 and 41 U.S.C.
chapter 67).
_____ (3) 52.222-43, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (Multiple Year and Option Contracts) (AUG 2018) (29 U.S.C. 206 and 41 U.S.C. chapter 67).
_____ (4) 52.222-44, Fair Labor Standards Act and Service Contract Labor Standards--Price Adjustment (MAY 2014) (29 U.S.C 206 and 41 U.S.C. chapter 67).
_____ (5) 52.222-51, Exemption from Application of the Service Contract Labor Standards to Contracts for Maintenance, Calibration, or Repair of Certain Equipment--Requirements (MAY 2014) (41 U.S.C. chapter 67).
_____ (6) 52.222-53, Exemption from Application of the Service Contract Labor Standards to Contracts for Certain Services--Requirements (MAY 2014) (41 U.S.C. chapter 67).
_____ (7) 52.222-55, Minimum Wages for Contractor Workers Under Executive Order 14026 (JAN 2022) (E.O.
13658).
_____ (8) 52.222-62, Paid Sick Leave Under Executive Order 13706 (JAN 2022) (E.O. 13706).
_____ (9) 52.226-6, Promoting Excess Food Donation to Nonprofit Organizations (JUN 2020) (42 U.S.C. 1792).
(d) Comptroller General Examination of Record.
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .