TECHNICAL PROVISIONS

FROM:

156th AW/MSG BASE CIVIL ENGINEER

PUERTO RICO AIR NATIONAL GUARD

CAROLINA, PUERTO RICO

ST. CROIX ANG STATION HURRICANE MARIA REPAIR

PROJECT NO. WBGA182401

FOR:

156th AW/MSG CONTRACTING OFFICER

PUERTO RICO AIR NATIONAL GUARD

CAROLINA, PUERTO RICO

TECHNICAL PROVISIONS

ST. CROIX ANG STATION HURRICANE MARIA REPAIR

PROJECT NO. WBGA182401

GENERAL INDEX

SECTION CONTENTS PAGE NO.

A Work to be done 3 B Specifications 3 C Scope of work 3 D Special Considerations 6 E Location of the works 6 F Special Instructions to Contractor 7 G Submittal List 8 H Invoice Requirement 8 I Closeout Documentation 8 J Existing Conditions 8 Appendix A – Images

Appendix B – Specifications

A. WORK TO BE DONE:

1. The work to be performed under this project consists in furnishing all labor, equipment, appliances, materials and performing all operations in strict accordance with ethical accepted practices of engineering.

2. The following is a list of the principal features of the project as described in the specifications, shown, noted or implied upon in the accompanying drawings, showing the general characteristics and extent of the work. Parts not specifically detailed shall be constructed in a manner and spirit conforming to the class of work required for the whole project.

3. The Contractor must perform a site visit in coordination with the Contracting Officer to verify the existing site and facility conditions. Any differing conditions shall be notified in writing to request clarification.

B. SPECIFICATIONS:

1. All work shall comply with the more stringent specification from the UFC or attached specification sections.

2. Unified Facilities Guide Specification (UFGS) Web Site:

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

3. The following specification documents are attached to this Statement of Work and are directly applicable to this project.

SECTION 07 14 00 – FLUID-APPLIED WATERPROOFING

SECTION 07 57 13 – SPRAYED POLYURETHANE FOAM (SPF) ROOFING

SECTION 08 11 13 - STEEL DOORS AND FRAMES

SECTION 08 71 00 - DOOR HARDWARE

SECTION 09 90 00 - PAINTS AND COATINGS

SECTION 26 56 13.00 40 - LIGHTING POLES AND STANDARDS

SECTION 32 31 13.53 - HIGH-SECURITY CHAIN LINK FENCES AND GATES

UFC 4-022-03 - SECURITY FENCES AND GATES

C. SCOPE OF WORK:

285th Civil Engineer Squadron, St. Croix ANG Station, USVI has experienced damage due to Hurricanes Irma and Maria. The completion of the following repairs are required to maintain security of the installation and to preserve buildings.

i. Bldg. 100 Roof – Scope intends repair roof by cleaning and patching areas of the roof spray polyurethane foam (SPF) membrane and apply elastomeric finish coat over patched areas plus entire north high roof system by:

1. Pressure wash north upper roof. Access to water is needed. Downspouts will be plugged or disconnected and wash water siphoned off. Measures will be taken to prevent sediments or other materials be carried by runoff waters. Clear down spouts from debris - use of snake may be necessary.

http://www.wbdg.org/ffc/dod/unified-facilities-guide-specifications-ufgs

2. Scrape, clean and prep damaged areas to patch on center roof. (approximately 10 areas/50 SQFT - Contractor to verify center roof damaged patches with Operations Officer)

3. Spray-apply polyurethane foam in deep patch areas.

4. Apply base coat of urethane coating over new foam patched areas.

5. Remove damaged exhaust fan from upper roof area. See Appendix A.

6. Install cover plates over 2 fan ducts on north upper roof – east side. See Appendix A.

7. Apply finish coat of white silicone construction coating over entire north upper roof.

(approximately 1,500 SQFT – Contractor shall field verify and provide material required for this scope of work)

8. Apply 2 finish coats of white silicone construction coating over center roof patched areas. (Contractor to verify center roof damaged patches with Operations Officer).

• Silicone Roof Coating Type Silicone Theoretical Coverage 100 SQFT/1.5 gallons - DFT of 22 mils.

Color Bright White Durometer Hardness, Shore A 42 +/- 5 points Flash point 140.9°F (60.5°C) Max VOC 10 g/l Solid by Volume 91% +/- 3 Cure Time 2 to 6 hours Application Temp 35°F (2°C) and rising

ii. Bldg. 108 Roof – Scope intends to maintain/repair existing roof system by patching new fluid applied system:

1. Scrape and or grind off deteriorated coating area. (Contractor to verify center roof damaged patches with Operations Officer).

2. Clean and prepare underlying surfaces.

3. Allow for concrete surface to dry completely.

4. Apply 2 finish coats of white silicone construction coating over prepared areas to be patched. (Approximately 10 areas/50 SQFT – Contractor shall field verify and provide material required for this scope of work). See specification above.

iii. Building 100 HVAC Fan – This scope replaces a small roof fans on building 100. The painting of the men’s restroom ceiling will happen after the installation of the damaged fan.

1. Remove small fan on center lower roof that is for the men’s bathroom. Dispose of fan.

2. Install new fan on center roof with like fan. (Contractor shall verify and provide material required for this scope of work).

3. Repair post install damage ceiling sheetrock and paint as necessary.

iv. Bldg. 110 Exterior sheet paneling – The scope intends to replace the east wall, south end, of the exterior sheet panels that were damaged by:

1. Remove damaged panels from south east side of the building. Remove damaged insulation.

2. Clean and prep structure and area for install.

3. Install replacement panels with like color and style (Approximately 40’X16’ section - Contractor shall verify and provide material required for this scope of work).

4. Install replacement insulation of like kind (Approximately 40’X16’ section -

5. Weather seal replaced panels (Contractor shall verify and provide material required for this scope of work).

v. Bldg. 110 Roll up door frame - The scope of this intends to preserve the south roll up door.

1. Install center roll up door frame attachment with bar provided by Operations Officer.

Contractor to supply necessary hardware. High lift access will need to be provided by contractor.

2. Inspect and operational check door.

vi. Bldg. 110 North side vent doors – The scope is to replace damaged weather vent door.

1. Removed damaged weather vent door frame at foundation base of north west side of building.

2. Construct door frame, door, and door locking mechanism using corrosion resistant hardware and treated wood of like kind. (Contractor shall verify and provide material required for this scope of work).

vii. Light poles – The scope intends to return the perimeter light system to its full capability by replacing poles, lights, and equipment necessary.

1. Remove two light poles and base hardware and dispose of them.

2. Remove current pole junction boxes for install on new posts.

3. Install ((2) 30 foot tall corrosion poles – Contractor shall field verify and provide

4. Install current pole junction boxes to new posts. (Contractor shall field verify and provide material required for this scope of work)

5. Install 2 flood lights per pole on new poles, install lights on existing poles (Contractor shall verify and provide material required for this scope of work.)

6. Install corrosion resistant light mount and brackets for 2 flood lights, aircraft warning light, and security camera per pole.

7. Install 1 aircraft warning light on north east hill post.

8. Install electrical wires from junction to flood lights and security camera (Contractor shall verify and provide material required for this scope of work).

9. Conduct light operational check of entire perimeter light system.

viii. Concrete utility pole guyed wire – The scope of this intends to preserve the structure of the utility pole that connects the base to power and communication supply.

1. Install guyed wire on concrete power and communication pole located near gate in northwest corner of base. (Contractor shall verify and provide material required for this scope of work).

2. Install guyed wire anchor toward east side of pole and attach guyed wire from anchor to concrete pole.

ix. Painting – Water damage from high rain fall caused two areas of damage to painted locations. This scope intends to remove damaged paint and repaint area with like color. See section C.i above regarding the small fan replacement in building 100.

1. Remove damaged paint from ceiling of men’s restroom 100 and west wall of office in building 107.

2. Prepare both areas for paint to protect surrounding floors and ceilings.

3. Paint both walls with like color and sheen of paint. (Approximately 400 SQFT -

x. Bldg. 100 Steel Exterior Door – The scope intends to remove and replace the bent exterior door on the east side of building 100.

1. Remove exterior door and dispose.

2. Install door of like kind – paint with like color (Contractor shall verify and provide

3. Key door using master key plan provided by Operations Officer.

xi. Perimeter Fence - The scope intends to repair hurricane damaged fence.

1. Construct approximately 150 FT of new 6 feet high fabric, outriggers, and barbed wire IAW UFC 4-022-03 Table 2 (Protection Level 1), Table 1 (Type A2), the new line posts will be located in the same location as the existing fence posts. The replacement fence will match existing fence specifications and the attached FE6 Chain – Link Security Fence Details.

2. There will be 15 sections of fence replaced with this contract. The contractor shall verify quantities of materials.

3. Install new chain link fence IAW UFGS 32 31 13.53

4. Provide and install 3 new barbed wire lines on a single arm angled outrigger as per drawing and specifications. Outriggers must be permanently affixed to the fence posts with screws or by spot welding.

5. Removal and disposition of existing fence, posts, and concrete.

6. Saw cut the existing fence line.

7. All new line and terminal posts will be buried and encased in concrete footings as per construction drawings; ground level termination for the concrete will have convex finish to prevent the water accumulation at the base of the poles.

8. Contractor will provide one year minimum warranty on equipment, materials, and installation.

D. SPECIAL CONSIDERATIONS:

1. Solid Waste Management:

• All waste materials and debris generated by work under this contract shall be processed, handled, transported, stored, and disposed of by the contractor in accordance with all federal, state, local, regulations, and laws. All waste streams will be quantify and reported to the Base Environmental Manager.

2. Fire Safety:

• The Contractor shall comply with all local fire regulations and NFPA 241 during all demolition and construction work. All fire extinguishers required shall be provided and maintained by the contractor, but must be approved for use by the contracting officer prior to use. “Hot-work” operations, those involving welding, soldering, brazing, or torch heating shall not commence before an AF Form 592 is completed and signed by the Fire Inspector. The contractor shall contact the Fire Department’s inspection section at least one work day prior to hot-work operations for assistance and completing the Form 592. There shall be no open burning of waste materials or debris during this contract.

E. LOCATION OF THE WORKS:

1. The site of the work covered by these specifications is 285th Civil Engineer Squadron, St.

Croix ANG Station, USVI.

F. SPECIAL INSTRUCTIONS:

1. For additional information on drawings and specifications, and for entering the Site premises contact the Operations Officer, Maj. Ryan Barry 285th CES, building 100, RR- I, Box 9900. Telephone (340) 513-0171.

• Must request Digging Permit before work start.

2. For additional contracting issues will be directed to the Contracting Officer in Building 29, Muñíz ANG Base at telephone (787) 253-5238 or 7438.

• Must fill out Base Access Letter before project start.

3. For additional Environmental information contact the Environmental Manager Office in Building 25, Muñíz ANG Base telephone (787) 253-5192, or fax (787) 253-5226 or 7415.

4. For additional Safety information contact the Safety Office in Building 22, Muñíz ANG Base telephone at (787) 253-5275

• Must request Confine Space Entry AF Form 1024 before work start.

5. For additional Bioenvironmental information contact the Bioenvironmental Office in Building 16, Muñíz ANG Base telephone at (787) 253-5265

6. For additional Fire information contact the Fire Department in Building 3, Muñíz ANG Base telephone at (787) 253-5222

• Must request permit to use open flame equipment or grinders.

7. For additional Security information contact the Base Defense Operation Center in Building 2, Muñíz ANG Base telephone at (787) 253-5204

8. Contractors must be registered (current) in the System for Award Management (SAM) internet program at: http://www.sam.gov

9. All invoices must be submitted using Wide Area Workflow (WAWF) internet program at: https://wawf.eb.mil

10. Contractor will verify status of all invoices My Invoice link at: https://wawf.eb.mil

11. Contractor Manpower Reporting Application (CMRA): The contractor shall completely fill in all required data fields using the following web address: http://www.ecmra.mil/ Reporting inputs shall be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30.

12. Every day all garbage and remaining materials related to the work will be taken to a garbage container provided by contractor.

13. Only company cars with distinctive logos posted at passenger and driver doors will be authorized inside BASE premises.

14. All personnel are required to show a valid not expired ID in the main entrance gate before entering the Base premises.

15. At the end of each working day all areas will be clear from equipment, tools and materials.

https://www.sam.gov/ http://www.sam.gov/ https://wawf.eb.mil/ https://wawf.eb.mil/ http://www.ecmra.mil/

16. Special precautions will be taken at no cost to government to protect base property during the project execution.

17. The use of Personal Protective Equipment is mandatory at all time while working in the project.

G. SUBMITTAL LIST

a) List of Personal Protective Equipment to be used.

b) Worker Compensation Insurance Certificate

c) Review attached specification sections for additional submittal requirements

d) Design Drawings and Specifications For:

a. Concrete utility pole guyed wire design.

b. Light post installation

e) Product data for the following items:

a. Building 108 wall panel type and color sample.

b. Aircraft warning lights

c. Security flood lights

d. Electrical components (wire, conduit, connectors)

e. Building 100 and 108 paint sample

f. Flag pole ground light and hardware

g. Flagpole and base mount parts and hardware

h. Light pole and base mount parts and hardware

i. Small fan replaced on building 100

f) Submittals for Perimeter Fence Scope

1. Shop Drawings:

a. Fence Installation

b. Installation Drawings

c. Location of gate, former, end, and pull posts

d. Gate Assembly

e. Gate Hardware and Accessories

2. Product Data:

a. Fence Installation

b. Gate Assembly

c. Gate Hardware and Accessories

3. Samples:

a. Fabric

b. Posts

c. Post Caps

d. Braces

e. Line Posts

f. Bottom Rail

g. Tension Wire

h. Barbed Wire

i. Wire Ties

j. Stretcher Bars

k. Top Rail

l. Gate Posts

m. Gate Hardware and Accessories

4. Certificates:

a. Chain Link Fence

b. Reports

c. Fabric

d. Barbed Wire

e. Stretcher Bars

f. Gate Hardware and Accessories

g. Concrete

h. Gate Operator

5. Manufacturer’s Instructions:

a. Fence Installation

b. Gate Assembly

c. Hardware Assembly

d. Accessories

6. Operation and Maintenance Data:

a. Gate Operator

b. Operating and Maintenance Instructions

H. INVOICE REQUIREMENTS:

1. Electronic pictures of work to be invoiced (Before and After)

2. Breakdown for Payment

3. Monthly Report from: Contractor Manpower Reporting Application (CMRA)

4. Progress Report of activities.

5. Project Schedule (CPM): Baseline Vs Update. Initial detailed schedule that includes critical path must be submitted with bid proposal.

I. CLOSEOUT DOCUMENTATION:

1. Contractor workmanship warranty letter for 1 year for all non-roof items.

2. Contractor workmanship warranty letter for 10 years for all roof repairs.

3. Manufacturers’ warranties as applicable.

4. Recycling or landfill proof of disposition document.

5. Contractor certificates of no debts to suppliers and vendors.

6. Commissioning and acceptance of system.

J. EXISTING CONDITIONS: as of 2-Nov-2017

1. Hurricane Maria damage 285th Civil Engineer Squadron, St. Croix ANG Station, USVI.

See Appendix A.

APPENDIX A

Building 108 - Damaged exterior panels

Building 100 - Damaged pain on ceiling in men’s bathroom

Damaged perimeter light pole with current flood and aircraft warning lights

West side of station - Concrete utility post. Damaged fence in background.

Building 110 - Roll up door center support missing

Building 108 – Example of damaged top sealant

Building 100 – Upper roof damaged spots

Building 100 – Center roof damaged spots

Building 100 – Upper roof top coat sealant with traped water (foreground) and HVAC fan to be removed and capped (top left)

Building 100 - Roof vent fan damaged blades and motor

Building100 – Roof fan duct requires cap

St Croix ANG Station map for reference

Building 100 for reference

USACE / NAVFAC / AFCEC / NASA UFGS-07 14 00 (February 2012) Change 1 - 08/17 Preparing Activity: NAVFAC Superseding UFGS-07 14 00 (April 2006)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2017

SECTION TABLE OF CONTENTS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

SECTION 07 14 00

FLUID-APPLIED WATERPROOFING

02/12

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PREWATERPROOFING CONFERENCE

1.4 DELIVERY, STORAGE, AND HANDLING

1.5 ENVIRONMENTAL CONDITIONS

1.6 WARRANTY

1.6.1 Roof Membrane Manufacturer Warranty

1.6.2 Roofing System Installer Warranty

1.6.3 Continuance of Warranty

PART 2 PRODUCTS

2.1 FLUID-APPLIED MEMBRANE

2.2 MEMBRANE PRIMER

2.3 SEALANT

2.4 SEALANT PRIMER

2.5 BACKING MATERIAL

2.6 [JOINT FILLER

2.7 BOND BREAKER

2.8 ELASTOMERIC SHEET

2.9 ELASTOMERIC SHEET ADHESIVE

2.10 FLEXIBLE FOAM-BACKED ELASTOMERIC SHEET

2.11 PROTECTION BOARD

2.12 DRAINAGE COURSE AGGREGATE

2.13 INSULATION

PART 3 EXECUTION

3.1 PREPARATION

3.1.1 Flashings

3.1.1.1 Drains

3.1.1.2 Penetrations and Projections

3.1.1.3 Walls and Vertical Surfaces

SECTION 07 14 00 Page 1

3.1.2 Cracks and Joints

3.1.3 Priming

3.2 SPECIAL PRECAUTIONS

3.3 APPLICATION

3.3.1 Work Sequence

3.3.2 Protection Board

3.3.3 Drainage Course

3.3.4 Insulation

3.4 FIELD QUALITY CONTROL

3.4.1 Moisture Test

3.4.2 Film Thickness

3.4.3 Flood Test

3.5 INSTRUCTIONS TO GOVERNMENT PERSONNEL

3.6 INFORMATION CARD

-- End of Section Table of Contents --

SECTION 07 14 00 Page 2

USACE / NAVFAC / AFCEC / NASA UFGS-07 14 00 (February 2012) Change 1 - 08/17 Preparing Activity: NAVFAC Superseding UFGS-07 14 00 (April 2006)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2017

SECTION 07 14 00

FLUID-APPLIED WATERPROOFING

02/12

NOTE: This guide specification covers the requirements for fluid-applied elastomeric waterproofing systems for building decks over occupied space where membrane is protected of a separate wearing course.

Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable item(s) or insert appropriate information.

Remove information and requirements not required in respective project, whether or not brackets are present.

Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR) .

NOTE: This guide specification should not be used to specify waterproofing of structures subject to hydrostatic pressure. It includes the fluid-applied membrane, protection board, drainage layer, and insulation. It does not include structural deck, protection slab, or wearing course; these elements influence performance of the waterproofing system.

See UFC 3-110-03, "Roofing" for design recommendations.

Technical Reference : ASTM C898, "High Solids Content, Cold Liquid-Applied Elastomeric Waterproofing Membrane with Separate Wearing

SECTION 07 14 00 Page 3

Course." This document contains guidelines for design of the waterproofing system, and may be used as a source of supplementary information.

1. Slope: Provide slope toward drains (after deflections due to applied load and creep) of not less than one percent 10 mm per meter 1/8 inch per foot.

2. Wall Flashing: Extend wall flashing to at least 100 mm 4 inches above wearing surface and higher where exposure is more severe. If top of flashing is recessed under a concrete wall, counterflashing is not necessary. Metal counterflashing is necessary at masonry wall intersections. Flash right-angle intersection of deck and wall with an elastomeric sheet.

NOTE: This section contains both metric and inch-pound graphics.

NUMBER TITLE

1 Basic Components of Membrane with Separate Wearing Course

2 Flashing at Cracks and Nonmoving Joints in the Concrete

3 Expansion Joint Flashing

4 Expansion Joint Flashing at Wall

5 Terminal Condition with Masonry Above Finish Wearing Surface at Grade

6 Wall Flashing on Concrete Wall

7 Wall - Deck Flashing

8 Penetration Flashing

9 Drain Flashing

DO NOT INCLUDE THE SKETCHES OR LIST OF SKETCHES IN

THE PROJECT SPECIFICATIONS. USE SKETCHES FOR

PREPARING DETAILS ON THE DRAWINGS.

NOTE: TO DOWNLOAD UFGS GRAPHICS

Go to http://www.wbdg.org/FFC/NAVGRAPH/graphtoc.pdf

SECTION 07 14 00 Page 4

PART 1 GENERAL

1.1 REFERENCES

NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.

Use the Reference Wizard's Check Reference feature when you add a Reference Identifier (RID) outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates.

References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

ASTM INTERNATIONAL (ASTM)

ASTM C33/C33M (2016) Standard Specification for Concrete Aggregates

ASTM C578 (2016) Standard Specification for Rigid, Cellular Polystyrene Thermal Insulation

ASTM C836/C836M (2015) High Solids Content, Cold Liquid-Applied Elastomeric Waterproofing Membrane for Use With Separate Wearing Course

ASTM D1056 (2014) Standard Specification for Flexible Cellular Materials - Sponge or Expanded Rubber

ASTM D1751 (2004; E 2013; R 2013) Standard Specification for Preformed Expansion Joint Filler for Concrete Paving and Structural Construction (Nonextruding and Resilient Bituminous Types)

ASTM D1752 (2004a; R 2013) Standard Specification for Preformed Sponge Rubber Cork and Recycled PVC Expansion

1.2 SUBMITTALS

SECTION 07 14 00 Page 5

NOTE: Review Submittal Description (SD) definitions in Section 01 33 00 SUBMITTAL PROCEDURES and edit the following list to reflect only the submittals required for the project.

The Guide Specification technical editors have designated those items that require Government approval, due to their complexity or criticality, with a "G". Generally, other submittal items can be reviewed by the Contractor's Quality Control System. Only add a “G” to an item, if the submittal is sufficiently important or complex in context of the project.

For submittals requiring Government approval on Army projects, a code of up to three characters within the submittal tags may be used following the "G" designation to indicate the approving authority.

Codes for Army projects using the Resident Management System (RMS) are: "AE" for Architect-Engineer; "DO" for District Office (Engineering Division or other organization in the District Office); "AO" for Area Office; "RO" for Resident Office; and "PO" for Project Office. Codes following the "G" typically are not used for Navy, Air Force, and NASA projects.

Use the "S" classification only in SD-11 Closeout Submittals. The "S" following a submittal item indicates that the submittal is required for the Sustainability eNotebook to fulfill federally mandated sustainable requirements in accordance with Section 01 33 29 SUSTAINABILITY REPORTING.

Choose the first bracketed item for Navy, Air Force and NASA projects, or choose the second bracketed item for Army projects.

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are [for Contractor Quality Control approval.][for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government.] Submittals with an "S" are for inclusion in the Sustainability eNotebook, in conformance to Section 01 33 29 SUSTAINABILITY REPORTING. Submit the following in accordance with Section 01 33 00

SUBMITTAL PROCEDURES:

SD-03 Product Data

Fluid-Applied Membrane

Membrane Primer

Elastomeric Sheet

Flexible Foam-Backed Elastomeric Sheet

Solvent

SECTION 07 14 00 Page 6

Moisture Meter

Protection Board

Bond Breaker

Submit material description and physical properties, application details, and recommendations regarding shelf life, application procedures, and precautions on flammability and toxicity.

SD-11 Closeout Submittals

Warranty

Information Card

Instructions To Government Personnel

Include copies of Safety Data Sheets for maintenance/repair materials.

1.3 PREWATERPROOFING CONFERENCE

NOTE: Include the requirement for a prewaterproofing conference when the waterproofing system will be used on large areas, e.g., promenade decks over occupied space, and will require work by other trades, e.g., mechanical subcontractors, electrical subcontractor, or tile setters on the membrane.

Prior to starting application of waterproofing system, arrange and attend a prewaterproofing conference to ensure a clear understanding of drawings and specifications. Give the Contracting Officer 7 days advance written notice of the time and place of meeting. Ensure that the mechanical and electrical subcontractor, flashing and sheetmetal subcontractor, and other trades that may perform other types of work on or over the membrane after installation, attend this conference.

1.4 DELIVERY, STORAGE, AND HANDLING

Deliver waterproofing materials in manufacturer's original, unopened containers, with labels intact and legible. Containers of materials covered by a referenced specification number shall bear the specification number, type, and class of the contents. Deliver materials in sufficient quantity to continue work without interruption. Store and protect materials in accordance with manufacturer's instructions, and use within their indicated shelf life. When hazardous materials are involved, adhere to special precautions of the manufacturer, unless precautions conflict with local, state, and federal regulations. Promptly remove from the site materials or incomplete work adversely affected by exposure to moisture or freezing. Store materials on pallets and cover from top to bottom with canvas tarpaulins.

SECTION 07 14 00 Page 7

1.5 ENVIRONMENTAL CONDITIONS

Apply materials when ambient temperature is 4 degrees C 40 degrees F or above for a period of 24 hours prior to the application and when there is no ice, frost, surface moisture, or visible dampness on the substrate surface. Apply materials when air temperature is expected to remain above 4 degrees C 40 degrees F during the cure period recommended by the manufacturer. Moisture test for substrate is specified under paragraph entitled "Moisture Test." Work may be performed within heated enclosures, provided the surface temperature of the substrate is maintained at a minimum of 4 degrees C 40 degrees F for 24 hours prior to the application of the waterproofing, and remains above that temperature during the cure period recommended by the manufacturer.

1.6 WARRANTY

Provide roof system material and workmanship warranties meeting specified requirements. Provide revisions or amendment to standard membrane manufacturer warranty to comply with the specified requirements. Minimum manufacturer warranty shall have no dollar limit, cover full system water-tightness, and shall have a minimum duration of 20 years.

1.6.1 Roof Membrane Manufacturer Warranty

NOTE: Insulated and routinely occupied facilities or facilities containing sensitive equipment or operations require a warranty of not less than 15 years. Designer may specify 5 or 10 year manufacturer warranty on facilities of small roof area and of minor importance where interiors and contents are not severely impacted by potential water intrusion. Environmentally controlled interiors require minimum 10 year warranty regardless of small size.

Furnish the roof membrane manufacturer's 20-year no dollar limit roof system materials and installation workmanship warranty, including flashing, insulation, and accessories necessary for a watertight roof system construction. Write the warranty directly to the Government commencing at time of Government's acceptance of the roof work. Provide the the following statements for such warranty:

a. If within the warranty period the roof system, as installed for its intended use in the normal climatic and environmental conditions of the facility, becomes non-watertight, shows evidence of moisture intrusion within the assembly, blisters, splits, tears, cracks, delaminates, separates at the seams, or shows evidence of excessive weathering due to defective materials or installation workmanship, the repair or replacement of the defective and damaged materials of the roof system assembly and correction of defective workmanship are the responsibility of the roof membrane manufacturer. All cost associated with the repair or replacement work are the responsibility of the roof membrane manufacturer.

b. The warranty must remain in full force and effect, including emergency temporary repairs performed by others, when the manufacturer or his approved applicator fail to perform the repairs within 72 hours of

SECTION 07 14 00 Page 8 notification.

1.6.2 Roofing System Installer Warranty

The roof system installer must warrant for a minimum period of two years that the roof system, as installed, is free from defects in installation workmanship, to include the roof membrane, flashing, insulation, accessories, attachments, and sheet metal installation integral to a complete watertight roof system assembly. Write the warranty directly to the Government. The roof system installer is responsible for correction of defective workmanship and replacement of damaged or affected materials.

The roof system installer is responsible for all costs associated with the repair or replacement work.

1.6.3 Continuance of Warranty

Approve repair or replacement work that becomes necessary within the warranty period and accomplished in a manner so as to restore the integrity of the roof system assembly and validity of the roof membrane manufacturer warranty for the remainder of the manufacturer warranty period.

PART 2 PRODUCTS

2.1 FLUID-APPLIED MEMBRANE

NOTE: ASTM C836/C836M is a materials performance specification; it does not specify any particular elastomer or elastomeric-extender combination.

ASTM C836/C836M.

2.2 MEMBRANE PRIMER

As recommended by the fluid-applied membrane manufacturer unless specifically prohibited by the manufacturer of the fluid-applied membrane.

2.3 SEALANT

NOTE: Specify sealant conforming to FS TT-S-227 or FS TT-S-230 in Section 07 92 00 JOINT SEALANTS. If no such section is required, specify sealant in this section.

As specified in Section 07 92 00 JOINT SEALANTS.

2.4 SEALANT PRIMER

As specified in Section 07 92 00 JOINT SEALANTS.

2.5 BACKING MATERIAL

NOTE: Include the following paragraph in Section

07 92 00 JOINT SEALANTS.

SECTION 07 14 00 Page 9

"Special Backing Material: Backing materials used for sealants in conjunction with fluid-applied waterproofing are specified in this section.

Premolded, closed-cell, polyethylene, or polyurethane foam rod having a diameter 25 percent larger than joint width before being compressed into joint. Provide bond breaker of polyethylene film or other suitable material between backing material and sealant.

2.6 [JOINT FILLER

As specified in [Section 03 30 00 CAST-IN-PLACE CONCRETE,] [ ASTM D1751] [or] [ ASTM D1752].]

2.7 BOND BREAKER

As recommended by the fluid-applied membrane manufacturer. Bond breaker shall not interfere with the curing process or other performance properties of the fluid-applied membrane.

2.8 ELASTOMERIC SHEET

Preformed; as recommended by the fluid-applied membrane manufacturer. Bond strength between the fluid-applied membrane and the preformed elastomeric sheet shall be a minimum of 7 kPa one psi when tested in accordance with

ASTM C836/C836M.

2.9 ELASTOMERIC SHEET ADHESIVE

As recommended by the elastomeric sheet manufacturer.

2.10 FLEXIBLE FOAM-BACKED ELASTOMERIC SHEET

Flexible foam-backed elastomeric sheet for protection over preformed elastomeric sheet at expansion joints shall be 13 mm 1/2 inch thick, minimum, closed cell foam conforming to ASTM D1056, Type 2, Class B, Grades 2 or 3, factory-bonded to 2 mm 1/16 inch thick, minimum, preformed elastomeric sheet.

2.11 PROTECTION BOARD

Premolded bitumen composition board, 3 mm 1/8 inch minimum thickness or other composition board compatible with the fluid-applied membrane.

2.12 DRAINAGE COURSE AGGREGATE

ASTM C33/C33M, size No. 8.

2.13 INSULATION

Polystyrene foam conforming to ASTM C578, Class IV, thickness as [indicated] [required by indicated R-value].

PART 3 EXECUTION

3.1 PREPARATION

Coordinate work with that of other trades to ensure that components to be

SECTION 07 14 00 Page 10 incorporated into the waterproofing system are available when needed.

Inspect and approve surfaces immediately before application of waterproofing materials. Remove laitance, loose aggregate, sharp projections, grease, oil, dirt, curing compounds, and other contaminants which could adversely affect the complete bonding of the fluid-applied membrane to the concrete surface.

3.1.1 Flashings

Make penetrations through sleeves in concrete slab watertight before application of waterproofing. After flashing is completed, cover elastomeric sheet with fluid-applied waterproofing during waterproofing application.

3.1.1.1 Drains

Make drain flanges flush with surface of structural slab. Apply a full elastomeric sheet around the drain, with edges fully adhered to drain flange and to structural slab. Do not adhere elastomeric sheet over joint between drain and concrete slab. Do not plug drainage or weep holes. Cover elastomeric sheet with fluid-applied waterproofing during waterproofing application. Lap elastomeric sheet a minimum of 100 mm 4 inches onto concrete slab.

3.1.1.2 Penetrations and Projections

Flash penetrations and projections through structural slab with an elastomeric sheet adhered to the concrete slab and the penetration. Leave elastomeric sheet unadhered for 25 mm one inch over joint between penetration and concrete slab. Adhere elastomeric sheet a minimum of 100 mm 4 inches onto horizontal deck.

3.1.1.3 Walls and Vertical Surfaces

Flash wall intersections which are not of monolithic pour or constructed with reinforced concrete joints with an elastomeric sheet adhered to both vertical wall surfaces and concrete slab. Flash intersections which are monolithically poured or constructed with reinforced concrete joints with either an elastomeric sheet or a vertical grade of fluid-applied waterproofing adhered to vertical wall surfaces and concrete slab. Leave sheet unadhered for a distance of 25 mm one inch from the corner on both vertical and horizontal surfaces.

3.1.2 Cracks and Joints

Prepare visible cracks and joints in substrate to receive fluid-applied waterproofing membrane by placing a bond breaker and an elastomeric slip sheet between membrane and substrate. Cracks that show movement shall receive a 50 mm 2 inch bond breaker followed by an elastomeric sheet adhered to the deck. Nonmoving cracks shall be double coated with fluid-applied waterproofing.

3.1.3 Priming

Prime surfaces to receive fluid-applied waterproofing membrane. Apply primer as required by membrane manufacturer's printed instructions.

SECTION 07 14 00 Page 11

3.2 SPECIAL PRECAUTIONS

Protect waterproofing materials during transport and application. Do not dilute primers and other materials, unless specifically recommended by materials manufacturer. Keep containers closed except when removing contents. Do not mix remains of unlike materials. Thoroughly remove residual materials before using application equipment for mixing and transporting materials. Do not permit equipment on the project site that has residue of materials used on previous projects. Use cleaners only for cleaning, not for thinning primers or membrane materials. Ensure that workers and others who walk on cured membrane wear clean, soft-soled shoes to avoid damaging the waterproofing materials.

3.3 APPLICATION

Over primed surfaces, provide a uniform, wet, monolithic coating of fluid-applied membrane, 1.5 mm 60 mils thick, plus or minus 0.125 mm 5 mils by following manufacturer's printed instructions. Apply material by trowel, squeegee, roller, brush, spray apparatus, or other method recommended by membrane manufacturer. Check wet film thickness as specified in paragraph entitled "Film Thickness" and adjust application rate as necessary to provide a uniform coating of the thickness specified.

Where possible, mark off surface to be coated in equal units to facilitate proper coverage. At expansion joints, control joints, prepared cracks, flashing, and terminations, carry membrane over preformed elastomeric sheet in a uniform 1.5 mm 60 mil thick, plus or minus 0.125 mm 5 mils, wet thickness to provide a monolithic coating. If membrane cures before next application, wipe previously applied membrane with a solvent to remove dirt and dust that could inhibit adhesion of overlapping membrane coat. Use solvent recommended by the membrane manufacturer, as approved.

3.3.1 Work Sequence

Perform work so that protection board is installed prior to using the waterproofed surface. Do not permanently install protection board until the membrane has passed the flood test specified under paragraph entitled "Flood Test." Move material storage areas as work progresses to prevent abuse of membrane and overloading of structural deck.

3.3.2 Protection Board

Protect fluid-applied membrane by placing protection board over membrane at a time recommended by the membrane manufacturer. Protect membrane application when protection board is not placed immediately. Butt protection boards together and do not overlap.

3.3.3 Drainage Course

Place drainage course where shown after flood tests are completed and concrete protection slab or wearing course is ready to be installed.

3.3.4 Insulation

Place insulation of thickness indicated, on top of drainage course just prior to placement of concrete protection slab.

SECTION 07 14 00 Page 12

3.4 FIELD QUALITY CONTROL

3.4.1 Moisture Test

Prior to application of fluid-applied waterproofing, measure moisture content of substrate with a moisture meter in the presence of the Contracting Officer. An acceptable device is the Delmhorst Moisture Meter, Model BD7/2E/CS, Type 21 E. Similar meters by other manufacturers, which are suitable for the purpose, may be used as approved by the Contracting Officer. Do not begin application until meter reading indicates "dry" range.

3.4.2 Film Thickness

Measure wet film thickness every 10 square meters 100 square feetduring application by placing flat metal plates on the substrate or using a mil-thickness gage especially manufactured for the purpose.

3.4.3 Flood Test

After application and curing is complete, plug drains and fill waterproofed area with water to a depth of 50 mm 2 inches. A minimum 48 hour cure time, or longer cure time if recommended by the membrane manufacturer, shall be required prior to flood testing. Allow water to stand 24 hours. Test watertightness by measuring water level at beginning and end of the 24 hour period. If water level falls, drain water, allow installation to dry, and inspect. Make repairs or replace as required and repeat the test. Work shall not proceed before approval of repairs or replacement.

3.5 INSTRUCTIONS TO GOVERNMENT PERSONNEL

Furnish written and verbal instructions on proper maintenance procedures to designated Government personnel. Furnish instructions by a competent representative of the roof membrane manufacturer and include a minimum of 4 hours on maintenance and emergency repair of the membrane. Include a demonstration of membrane repair, and give sources of required special tools. Furnish information on safety requirements during maintenance and emergency repair operations.

3.6 INFORMATION CARD

For each roof application, furnish a minimum 215 mm 8-1/2 inch by 11 inch information card for facility records and a card laminated in plastic and framed for interior display at roof access point, or a photoengraved 1 mm

0.032 inch thick aluminum card for exterior display. Identify facility name and number; location; contract number; approximate roof area; detailed roof system description, including deck type, membrane, number of plies, method of application, manufacturer, insulation and cover board system and thickness; presence of tapered insulation for primary drainage, presence of vapor retarder; date of completion; installing contractor identification and contract information; membrane manufacturer warranty expiration, warranty reference number, and contact information. Install card at roof top or access location as directed by the Contracting Officer and provide a paper copy to the Contracting Officer.

SECTION 07 14 00 Page 13

FORM 1

FLUID-APPLIED WATERPROOFING SYSTEM COMPONENTS

1. Contract Number

2. Date Work Completed

3. Project Specification Designation

4. Substrate Material

5. Slope of Substrate

6. Drains Type/Manufacturer

7. Waterproofing

a. Membrane

b. Sealant

c. Elastomeric Sheet

d. Materials Manufacturer(s)

8. Protection Board

a. Type

b. Thickness

c. Manufacturer's Name

9. Drainage Course Material Graduation

10. Insulation

a. Type

b. Thickness

c. Manufacturer's Name

11. Protection Slab

a. Material

b. Thickness

c. Support

SECTION 07 14 00 Page 14

FORM 1

FLUID-APPLIED WATERPROOFING SYSTEM COMPONENTS

d. Joint System

12. Wearing Course

a. Type

b. Slope

c. Joint System

d. Sealant/Gasket Type

13. Wearing Surface Type

Manufacturer's Name

14. Warranty

a. Manufacturer warranty expiration

b. Warranty reference number

15. Statement of Compliance or Exception

Contractor's Signature Date Signed

Inspector's Signature Date Signed

-- End of Section --

SECTION 07 14 00 Page 15

USACE / NAVFAC / AFCEC / NASA UFGS-07 57 13 (May 2011) Change 2 - 08/17 Preparing Activity: NAVFAC Superseding UFGS-07 57 13 (August 2010)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2017

SECTION TABLE OF CONTENTS

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

SECTION 07 57 13

SPRAYED POLYURETHANE FOAM (SPF) ROOFING

05/11

PART 1 GENERAL

1.1 REFERENCES

1.2 DESCRIPTION OF ROOF SYSTEM

1.2.1 Design Requirements

1.2.1.1 Fire and Wind Uplift

1.2.2 Performance Requirements

1.3 SUBMITTALS

1.4 QUALITY ASSURANCE

1.4.1 Qualification of Manufacturer

1.4.1.1 Manufacturer's Technical Representative

1.4.2 Qualification of Applicator

1.4.3 Preroofing Conference

1.4.4 Foam Roof System Mock-Up

1.4.5 Sample Warranty

1.4.6 Sustainable Design Certification

1.5 DELIVERY, STORAGE, AND HANDLING

1.5.1 Delivery

1.5.2 Storage

1.5.3 Handling

1.6 ENVIRONMENTAL CONDITIONS

1.6.1 Primer

1.6.2 Sprayed Polyurethane Foam

1.6.3 Elastomeric Coating

1.7 COORDINATION

1.7.1 Flashing

1.8 WORK SEQUENCE

1.9 CONTRACTOR'S FOAM SPRAY EQUIPMENT

1.9.1 Applicator

1.9.2 Equipment Calibration

1.9.3 Metering Equipment Requirements

1.9.4 Moisture Protection

1.9.5 Compressed Air

1.9.6 Dispense Excess Materials

1.10 SPECIAL SAFETY PROVISIONS

SECTION 07 57 13 Page 1

1.10.1 Special Equipment

1.10.1.1 Air Masks

1.10.1.2 Eye and Face Masks

1.10.1.3 Clothing and Gloves

1.10.2 Handling Precautions

1.10.2.1 Venting of Material Containers

1.11 WARRANTY

1.11.1 Roof System Manufacturer Warranty

1.11.2 Roofing System Installer Warranty

1.11.3 Continuance of Warranty

1.12 CONFORMANCE AND COMPATIBILITY

PART 2 PRODUCTS

2.1 SPRAY URETHANE FOAM

2.2 PROTECTIVE COATING

2.2.1 Type A Coating

2.2.2 Type B Coating

2.2.3 Type CB Coating

2.2.4 Type CF Coating

2.2.5 Coating Color

2.3 PRIMER

2.4 CERAMIC GRANULES

2.5 SEALANTS

2.6 WALKPADS

2.7 TRAFFIC AREA FABRIC

2.8 INSPECTION TOOLS

PART 3 EXECUTION

3.1 PROTECTION OF PROPERTY

3.1.1 Masking

3.1.2 Warning Signs

3.2 SPECIAL PRECAUTIONS AND INSTRUCTIONS

3.2.1 Safe Working Load Limits

3.2.2 Primers

3.2.3 Material Handling

3.2.4 Shoes

3.2.5 Fire and Explosion Hazards

3.3 ROOF AREA PREPARATION

3.3.1 Preapplication Inspection

3.3.1.1 Surface Examination

3.3.2 Close Intake Vents

3.4 GENERAL APPLICATION

3.5 SURFACE PREPARATION FOR FOAM APPLICATION

3.5.1 Ferrous Metal

3.5.2 Concrete Decks

3.5.3 Wood Decks and Other Wood Surfaces

3.5.4 Existing Roof Covering Surfaces

3.6 SPRAY FOAM APPLICATION

3.6.1 Spray Foam

3.6.2 Terminations

3.6.3 Surface Uniformity

3.6.4 Finish Appearance and Texture

3.6.5 Foam Finish Correction

3.6.6 Finish Removal

3.6.7 Application Time Limits

3.6.8 Curing Time

3.6.9 Spray Foam Clean Up

SECTION 07 57 13 Page 2

3.7 SURFACE PREPARATION FOR PROTECTIVE COATING APPLICATION

3.7.1 [Metal] [Concrete] [and] [Masonry] Surfaces

3.7.2 Primer

3.7.3 Sealant

3.8 PROTECTIVE COATING APPLICATION

3.8.1 Base Coat Application

3.8.2 Intermediate Coat Application

3.8.3 Finish Coat Application

3.8.4 Minimum Dry Film Thickness (DFT)

3.8.5 Granule Surfacing

3.8.6 Penetrations

3.8.7 Walkways

3.8.8 Coating Application Clean-Up

3.9 FIELD QUALITY CONTROL

3.9.1 Construction Monitoring

3.9.2 Coating Wet Film Thickness Monitoring

3.9.3 Slit samples

3.9.4 Core samples

3.9.5 Manufacturer's Field Inspection

3.9.6 Visual Inspection and Moisture Scanning

3.10 CORRECTION OF DEFICIENCIES

3.11 CLEAN-UP AND DISPOSAL

3.12 INFORMATION CARD

-- End of Section Table of Contents --

SECTION 07 57 13 Page 3

USACE / NAVFAC / AFCEC / NASA UFGS-07 57 13 (May 2011) Change 2 - 08/17 Preparing Activity: NAVFAC Superseding UFGS-07 57 13 (August 2010)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

References are in agreement with UMRL dated July 2017

SECTION 07 57 13

SPRAYED POLYURETHANE FOAM (SPF) ROOFING

05/11

NOTE: This guide specification covers the requirements for spray applied urethane foam roofing systems with a fluid applied elastomeric protection coating.

Adhere to UFC 1-300-02 Unified Facilities Guide Specifications (UFGS) Format Standard when editing this guide specification or preparing new project specification sections. Edit this guide specification for project specific requirements by adding, deleting, or revising text. For bracketed items, choose applicable item(s) or insert appropriate information.

Remove information and requirements not required in respective project, whether or not brackets are present.

Comments, suggestions and recommended changes for this guide specification are welcome and should be submitted as a Criteria Change Request (CCR) ..

NOTE: Roof must be sloped to drain, with minimum slope after deflection of 20 mm per meter 1/4 inch per foot. Roof slope will be obtained by sloping the structural deck and not by varying the thickness of the sprayed insulation. The roofing system will not be applied when deck is of lightweight concrete or when other than light foot traffic is anticipated on the roof. Broomed finish should be specified for concrete decks.

The designer will determine the minimum required R-value and calculate the insulation thickness based on the aged R-value of 5.6. Insulation thickness shall be specified or indicated on drawings but not be less than 38 mm 1-1/2 inches and will be shown on the drawings.

SECTION 07 57 13 Page 4

This section shall be coordinated with other system components specifications such as decking and sheet metal flashing. This section shall also be coordinated with the criteria of UFC 3-110-03, "Roofing" as it relates to the specific project and Service Exceptions indicated therein.

PART 1 GENERAL

1.1 REFERENCES

NOTE: This paragraph is used to list the publications cited in the text of the guide specification. The publications are referred to in the text by basic designation only and listed in this paragraph by organization, designation, date, and title.

Use the Reference Wizard's Check Reference feature when you add a Reference Identifier (RID) outside of the Section's Reference Article to automatically place the reference in the Reference Article. Also use the Reference Wizard's Check Reference feature to update the issue dates.

References not used in the text will automatically be deleted from this section of the project specification when you choose to reconcile references in the publish print process.

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

AMERICAN INDUSTRIAL HYGIENE ASSOCIATION (AIHA)

AIHA Z88.6 (2006) Respiratory Protection - Respirator Use-Physical Qualifications for Personnel

ASTM INTERNATIONAL (ASTM)

ASTM C177 (2013) Standard Test Method for Steady-State Heat Flux Measurements and Thermal Transmission Properties by Means of the Guarded-Hot-Plate Apparatus

ASTM C273/C273M (2016) Shear Properties of Sandwich Core Materials

ASTM C518 (2015) Steady-State Thermal Transmission Properties by Means of the Heat Flow Meter Apparatus

ASTM D1621 (2016) Standard Test Method for Compressive Properties of Rigid Cellular

SECTION 07 57 13 Page 5

Plastics

ASTM D1622/D1622M (2014) Apparent Density of Rigid Cellular Plastics

ASTM D1623 (2009) Tensile and Tensile Adhesion Properties of…