Phase I Pre-Proposal Conference
W912LP-17-R-0001
Project No. 190025 Davenport Readiness Center Davenport, Iowa
12 April 2017
Agenda
| Proposed schedule |
| Disclaimer |
| Section 00010 |
| Section 00100 |
| Section 00110 |
| Section 00120 |
| Questions |
Proposed Schedule for Phase I
| Issue Solicitation | 7 April 2017 |
| Pre-Proposal Conference | 12 April 2017 |
| Cut Off Date for Phase 1 Questions | 3 May 2017 |
| Phase 1 Proposal Closing | 8 May 2017 |
| Notification to Offerors | 21 June 2017 |
| Issue Phase Two Solicitation | 21 June 2017 |
Proposed Schedule for Phase II
| Hold Phase Two Pre-Proposal Conference | 28 June 2017 |
| Phase 2 Proposal Preparation Period (Closing) | 5 Aug 2017 |
| Schedule Oral Presentation | 15 Aug 2017 |
| Contract Award (Assuming Discussions are not needed) | 2 Oct 2017 |
| Notice-to-Proceed | 12 Oct 2017 |
Disclaimer
THE FOLLOWING IS A BRIEF OVERVIEW OF THE PROPOSAL REQUIREMENTS
OFFERORS ARE STRONGLY CAUTIONED TO CAREFULLY READ THE REQUIREMENTS OF THE SOLICITATION AND COMPLY ACCORDINGLY
THE GOVERNMENT INTENDS TO AWARD WITHOUT DISCUSSION AND THERE MAY NOT BE A CHANCE FOR DISCUSSIONS, CORRECTIONS, OR REVISED PROPOSALS !!
Section 00100 Davenport Readiness Center Project includes the design and construction of a one- or two-story facility consisting of an assembly hall, offices, classrooms, kitchen, latrines, and storage areas, physical fitness, vehicle work bays, and supporting spaces to be constructed on a 37 acre site along Highway 6/Kimberly Road and located west of Wisconsin Avenue in Davenport, Iowa. The approximate size of the building is not to exceed 87,300 SF. Supporting facilities include fenced military parking areas and privately-owned parking area, aprons, curbs, sidewalks and access roads totaling approximately 25,500 SY of concrete. The project also includes a loading dock, loading ramp, and a fuel containment area. Finish work to include landscaping, seeding, and sodding as required.
Davenport Readiness Center Location
Continued
| Two-Phase Design Build Solicitation |
| The Government intends to select three (3), but no less than two (2) or more than five (5), of the highest rated contractors to receive the technical requirements package and provide a technical and cost proposal for consideration by the Government. |
| Programmed amount |
| $21,230,000.00 |
Pre-proposal conference amendment https://www.fbo.gov/spg/USA/NGB/DAHA13/W912LP-17-R-0001/listing.html
Continued
| Questions for Phase I (paragraph 3.1) |
| POC is Ms. Brenda McKnight at brenda.m.mcknight.civ@mail.mil |
| Alternate POC is CW4 Mark Thompson at mark.l.thompson10.mil@mail.mil |
| Five days prior to closing date (3 May 2017) |
| Submit via email using Exhibit F format |
| Answers provided in Amendment posted three days prior to closing (5 May 2017) |
| Amendments posted to FedBizOpps: |
https://www.fbo.gov/spg/USA/NGB/DAHA13/W912LP-17-R-0001/listing.html
Continued Hand carried proposals (paragraph 5):
USPFO for Iowa Bldg 3475 7105 NW 70TH Avenue Johnston, Iowa 50131-1824 Proposal due date:
1:00 P.M. (CST) on 8 May 2017
Section 00110 Continued
| Proposal Preparation (Paragraph 1.1) |
| Mark envelope/box: |
PROPOSAL NO. W912LP-17-R-0001, DO NOT OPEN-
COMPETITIVE ACQUISITION
| Proposal Format (Paragraph 3) |
| Written proposals |
| 8 ½” X 11” paper |
| 10 font (minimum) |
| Table of Contents (Paragraph 2.0) for each binder (if applicable) |
| Volume 2 & 3 limited to # of pages identified |
| Binding – 3 ring “D” type binders preferred |
Continued Volume 1 – Pro Forma Documents (Para 4.1)
| SF 1442 & Section 00600 |
| Separate envelope |
| Label “Pro Forma Information” |
| Complete SAM registration (paragraph 4.1.2.) |
| Executive Summary (paragraph 4.1.3.) |
| Joint Venture Requirements (if applicable) (paragraph 4.1.4) |
| Executive Summary & Joint Venture Agreement |
| Evidence of Board of Directors approval of Joint Venture |
| Joint Venture must be registered in SAM. |
Continued
| Volume 2 – Technical Capability |
| Submit 1 original, 3 hard copies and 1 electronic copy |
| Technical Approach Narrative |
| Maximum 15 pages |
| Reference section 00110, paragraph 4.2.1. |
| Remember Government Design-Build Projects are FFP |
| Offeror’s Team Experience |
| Maximum 15 pages |
| Reference section 00110, paragraph 4.2.2. |
| Discuss at least three projects (completed within 5 years) |
| Demonstrate experience of design & lead construction personnel |
Continued
| Volume 2 – Technical Capability (continued) |
| Other Capability Information |
| Maximum 10 single pages |
| Reference section 00110, paragraph 4.2.3. |
| Discuss Information Systems, Scheduling, and Administration |
| Bonding Capability |
| Maximum 5 single pages |
| Reference section 00110, paragraph 4.2.4. |
| Demonstrate Bonding Capabilities |
Continued
| Volume 3 – Past/Present Performance |
| 1 Original, 3 hard copies and 1 electronic copy |
| Exhibit A Part 1 |
| For not more than five contracts (at least 90% complete) |
| Similar in scope, complexity, and size |
| Within past five years |
| List problems encountered & corrective actions |
| Exhibit A Part 2 (One time not project specific) |
| Other past performance considerations (optional) |
Continued Volume 3 – Past Performance (Continued)
| Exhibit B, Subcontractor Information & Consent Form |
| Provide a list of proposed key Subcontractors/Teaming Partners |
| Each Subcontractor/Teaming Partner must submit an Exhibit B |
| The design team shall also provide current SF 330, Parts 1 and 2 |
Continued
| Volume 3 – Past Performance (Continued) |
| Exhibit C, Reference Package Information & Forms |
| General Contractor must prepare and submit to all clients listed on Exhibit A, Part 1 |
| Subcontractors/Teaming Partners must prepare and submit to three (3) references (NOTE: Clearly identify the prime contractor’s their firm’s names on top of Exhibit C) |
| Applicable to Design team members and subcontractors to be utilized on design and oversight team |
| May not use offeror on this project as a reference |
| The completed questionnaires should arrive not later than the closing date for receipt of proposal shown on the SF 1442. |
| Offerors should contact their references three days prior to closing date to ensure questionnaires have been completed and submitted. Offerors may also contact the USPFO to verify the receipt of the questionnaires. POC: Brenda McKnight, PH. 515-252-4114. |
Section 00120
| Paragraph 1.3.1. - Past/Present Performance is approximately equal to technical capabilities. |
| Paragraph 2.2.1.1 - Technical capability evaluation |
| The relative importance of the three (3) technical subfactors are: Technical Approach being more important than Offeror’s Team Experience; and when combined, Technical Approach and Offeror’s Team Experience are significantly more important than Other Capability Information |
| Paragraph 2.2.2.6. - Past performance evaluation |
| There are six (6) Subfactors, with Quality Control as the most significant Subfactor. Other Subfactors are listed in descending order of importance. An overall evaluation for Past/Present Performance will be at the factor level. |
Questions Asked to Date
Q1. The solicitation section 13.4, page 8, and the brand name J&A Document both reference a requirement for a Honeywell branded fire alarm system. Since all fire alarm systems are proprietary, there will be no other product that will be com-patible with the Honeywell/Notifier product other than those manufactured by Honeywell/Notifier. It is our under-standing that this facility will be a new building, separated from any existing facilities and not connecting to an existing system where compatibility will be an issue or concern.
A1. The Iowa Army National Guard has updated its Fire Alarm monitoring system over the past few years to allow statewide monitoring of our Readiness Center centrally at Camp Dodge, Johnston, IA. The head-end equipment at Camp Dodge is Honeywell, therefore, for proper reporting and compatibility with the reporting system we now require all of our client systems be Honeywell.
Q2. If the same example projects (and Owner reference) are being used for both the Sioux City and Davenport projects, please confirm that only 1 copy of Owner’s Exhibit C is required to be submitted by Owner with name of both projects at top of each page?
A2. The contractor may request one past performance questionnaire be filled out by its references for both the Sioux City and Davenport projects. The contractor requesting the references needs to change the header to reflect both project titles and solicitation numbers. Remember the past performance references for the Sioux City project are due on 1 May 2017 and the past performance references for Davenport are due 8 May 2017. Past performance questionnaires that do not clearly reference the solicitation number may not be considered in the evaluation process, so please make sure the header clearly indicates the solicitation number.
Q3. 00010 2.3: Refers to FAR 52.228-5 for insurance requirements. However the referenced clause does not provide schedule of insurance types and limits required for this project for both the design and construction phases. Please advise.
A3. The Government will not take ownership of the building until it is 100% complete, therefore, insurance is the responsibility of the GC. It is highly recommended that the GC carry Builders Insurance.
Q4. 00100 1.5.2: Refers to “formally organized design-build entities” and “project-specific design/build associations”. The latter appears to be fairly generic e.g. it would allow both design-led or constructor-led teams where the Offeror acts as a prime contract-holder and the rest of the team members as subcontractors
A4. Design-Build teams can be organized in multiple ways to include, but not limited to, Design-Led, Constructor-Led, Integrated firms, and Joint-Venture. Each team has its advantages and disadvantages. The Government is not restricting how the team is organized.
Q5. 00110 5.6.4.1.4 & 5.6.4.2.5: Subject to stand-off distances, parts of the project may be subject to Anti-Terrorism/Force Protection measures such as blast-resistant products and construction. Please advise if Blast Analysis and/or Progressive Collapse Analysis, Modelling or Engineering will be required. These services are provided by specialty consultants beyond standard structural engineering.
A5. The Design-Build firm’s solution shall comply with all Anti-Terrorism/Force Protection requirements identified. The need for and extent of analysis performed by a structural engineer experienced in blast-resistant design may vary dependent upon the Design-Builder’s proposed solution.
Q6. 00100 1.6: Confirm no portion of the building will be categorized as ICC 500 (tornado shelter) or FEMA P-361 (community safe room)
A6. The facility will not be utilized as a tornado shelter or community safe room.
Q7. 00100 1.6: Describe on-site fuel dispensing & storage requirements
A7. There will be on on-site fuel dispensing units. The Iowa National Guard will have a fuel containment requirement in its vehicle storage area for fuel tankers.
Questions