Addendum 01 - Paint Removal B500.docx

DOCX document 25 KB Posted

Attached to
Paint Removal Federal contract opportunity
Solicitation number
W912LM-22-R-1007
Issued by
Department of the Army Minnesota Army National Guard

View the file

Other files for this federal contract opportunity

Other files attached to Paint Removal, newest first.
File Type Posted
B 07 Preproposal Conference 148th.pptx PPTX presentation
Pre-Bid Roster - Paint Removal B500.pdf PDF
B 08 W912LM-22-R-1007 Paint Removal.pdf PDF
EXHIBIT B Paint(Attachment).docx DOCX document
EXHIBIT D Letter of Commitment Paint (Attachment).docx DOCX document
B 08 Release Form 66 Paint.pdf PDF
EXHIBIT A Paint (Attachment).docx DOCX document
EXHIBIT C Reference_Questionnaire_Package Paint(Attachment).docx DOCX document
A 03 SOW_Paint B500.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Paint Removal B500 8/11/2022

FMKM222007

ADDENDUM 01

ANSWERS TO CONTRACTOR QUESTIONS:

1. Question: Q1. It was discussed onsite that an epoxy/ urethane paint system would be acceptable instead of the High Performance Architectural Latex Coating, MPI Division 5. Please confirm an epoxy/ urethane system is acceptable.

Response: An epoxy/urethane system is acceptable. Contractor shall provide a material submittal.

2. Question: Q2. Please confirm the Owner will Lock Out Tag Out all electrical and HVAC equipment.

Response: Confirmed, Owner will LOTO electrical/HVAC equipment.

3. Question: Q3. Please confirm two bays will be given to the contractor at the same time.

Response: Confirmed, Contractor will have access to two hangar bays at a time.

4. Question: Q4. Please confirm all cross bracing, building girts, electrical conduit and piping shall be included in the scope of work.

Response: Confirmed, all painted components mounted on walls are included in the scope of paint removal.

5. Question: Q5. Please confirm the scope of work will stop at the “Cream” color paint on the walls and will not include any steel at the ceiling.

Response: Confirmed, scope does not include the ceilings.

6. Question: Q6. As discussed onsite, the Owner is looking for an option to remove the wall coverings at the corner beams. Please confirm the contractor shall provide an option to perform this work.

Response: No, this is not included in the scope of work and no option is required.

7. Question: Q7. Please confirm the Owner shall be responsible for the disposal of all hazardous materials/ waste.

Response: The Owner shall be responsible for hazardous material disposal, provided the Contractor provides TCLP testing and pre-treatment.

8. Question: Q8. Please confirm it is acceptable for the contractor to use pretreatment (EnviroPrep or Blastox) for the lead paint removal.

Response: Pre-treatment is acceptable. Contractor shall provide and pay for Toxicity Characteristic Leaching Procedure (TCLP) testing.

9. Question: Q9. It was discussed onsite to prep and paint the exposed portions of the beam over the doors. Will a SSPC-SP2/ SSPC-SP3 be acceptable for this beam instead of abrasive blasting, so additional containment will not be required?

Response: Yes, SSPC-SP2/SSPC-SP3 cleaning method is acceptable.