Statement_of_Work_Prefabriacted_Building_W912LC-18-T-0005.pdf
PDF 43 KB Posted
- Attached to
- Prefabricated Building Greeley ANG
- Solicitation number
- W912LC-18-T-0005
About this file
Statement of Work Prefabricated Building Greeley
View the file
Other files
| File | Type | Posted |
|---|---|---|
| W912LC-18-T-0005_Prefabricated_Building_Amendment_01_with_Questions_and_Answers.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
TEMPORARY FACILITIES
SUPPORTING JMAX17058
FEBRUARY 21, 2018
1 STATEMENT OF WORK
STATEMENT OF WORK
PART 1 GENERAL
1.1 SCOPE OF PROJECT
A. This project is for the placement of a pre-fabricated building on the south side of Building 137, Greeley ANG Station, Greeley, CO.
B. Generally, the work includes the following objectives:
1. Provide a 310 sqft minimum modular data center capable of housing up to 12ea server racks, 4 desks for personnel; and meeting NFPA, Unified Facility Criteria, DoDM 5200.01 Security Standards, Weld County, and City of Greeley Codes for occupied space. The provided facility shall meet the requirements of Part 2 of this section, to include a securable door, 10 tons of cooling, and 300A 3 phase electrical service. A multi-unit solution will be accepted provided any single unit is capable of housing the 8ea MOSS Racks (referenced in Part 2 of this Section), providing 6 tons of cooling, 300A electrical service, and that these units may be joined together to form a continuous workspace meeting DoDM
5200.01 Security Standards.
2. A modular shelter similar to the C-FORTS 96, modified to meet the requirements of paragraph 1 above; or government approved equivalent, shall be considered sufficient to meet this requirement.
C. Specifications, concept drawings, manufacturer instructions, standards and government provided minimum specifications provided herein as part of the bid package are to be incorporated into the work and adapted / altered as necessary to meet the requirements.
1.2 LOCATION
A. Greeley Air National Guard Station (GANGS) is in Greeley, Colorado. The project site is located at 2605 East 8th Street, on the south side of building 137, within the Restricted Area of Greeley ANG Station.
1.3 BID SCHEDULE OPTIONS
A. Base Bid:
1. 1ea Modular Data Center as described in Part 2 of this section.
B. Options:
1. Installation of Government provided GSA combination lock on shelter door.
2 STATEMENT OF WORK
1.4 WORK NOT IN CONTRACT (N.I.C.)
A. All items and work indicated on the drawings or in the specifications as N.I.C.
will be furnished and installed by the Government. All furniture, unless otherwise described, will be furnished and installed by the government.
B. Communications wiring between bldg. 137 and the shelter, as well as communications wiring within the shelter shall be performed by the government.
C. Server racks, servers, and communications equipment shall be furnished and installed by the government.
1.5 GENERAL REQUIREMENTS
A. The Contractor shall be thoroughly familiarized with the minimum specifications to ensure against misunderstanding during contract execution.
1.6 MISCELLANEOUS REQUIREMENTS
A. Preservation and Restoration of Property: Contractors shall be responsible for the preservation of all public and private property on the surface or underground, along and adjacent to the work, and shall conduct their operations in a manner that will ensure against injury or damage thereto.
B. Where any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect or misconduct in the execution of the work, or because of non-execution thereof, on the part of the Contractors, such property shall be restored by the Contractors, at no cost to the Government, to a condition equal to that existing before such damage was done, by repairing, rebuilding or otherwise restoring same in a manner acceptable to the Government.
C. All work performed under this Contract shall proceed with due care and safety for all personnel and pedestrians. All work shall be planned so that the Project can be secured against unauthorized entry at the end of each working day.
PART 2 PRODUCTS
2.1 NONPERSONAL SERVICES:
A. The contractor shall supply all labor, tools, equipment, transportation and supervision necessary to purchase and install a minimum of 310 sqft of modular data center prefabricated building, equivalent to the C-FORTS 96 (or government approved equivalent), for 140th Civil Engineering, Buckley AFB, CO 80010, for delivery to Greeley Air National Guard Station. The modular
3 STATEMENT OF WORK
data center or data center complex shall meet the following minimum requirements:
1. Workspace capable of housing 4ea 48”x36” minimum desks (GFGI), with ADA clearance around each.
2. Walls meeting DoDM 5200.01-V3 security standards.
3. If windows are installed, shall provide coverings to meet DoDM
5200.01-V3 security standards.
4. Clad exterior doors with deadbolts and exterior lights, (OPTION: install
GSA approved combination lock, if option is selected by the Government).
5. All electric heat and air. Air conditioning shall be capable of providing a minimum of 10 tons of cooling.
6. If multiple units are provided, they shall be connected in a manner that allows safe passage of cabling and personnel between units.
7. Power, cooling, and structural capability should at a minimum support Racks 1-8 being located in a single structure, at the center of the floor, allowing front and rear access to all of the IT racks.
8. Structural capability should allow for the insertion or removal of any given rack, while fully loaded, up to 1,200 lbs. in weight.
9. Rack dimensions are as follows:
a. Racks 1 thru 5 = 40 rack units tall, 19” wide rack mount, 36” deep
(34” usable depth)
b. Rack 6 = 40 rack units tall, 19” wide rack mount, 30” deep (28” usable depth)
c. Rack 8 = Ops Area - 19 rack units tall, 19” wide rack mount, 18” deep (16” usable depth)
d. UGNT#1 (Rack C) = 38 rack units tall, 19” wide rack mount, 30” deep (20”L x 30”D x 72”H)
e. UGNT#2 (Rack A) = 38 rack units tall, 19” wide rack mount, 30” deep (20”L x 30”D x 72”H)
10. Equipment power requirements are as follows:
Description Weight (Lbs.)
Voltage (VAC) Frequency Phase Receptacle
Type Receptacle Quantity Watts
Rack #1 249 120 60 Hz Single L5-30P 2 1847
Rack #2 425 120 60 Hz Single L5-30P 2 1866
Rack #3 871 208 60 Hz 3 Phase L21-30P 2 4882
Rack #4 1092 208 60 Hz 3 Phase L21-30P 3 7466
Rack #5 417 208 60 Hz 3 Phase L21-30P 2 3051
Rack #6 372 120 60 Hz Single L5-30P 2 1488
4 STATEMENT OF WORK
Rack #8 Ops 142 120 60 Hz Single L5-30P 2 152
Operator #1 & #2 46 120 60 Hz Single L5-30P 1 380
Operator #3 46 120 60 Hz Single L5-30P 1 380
UGNT#1
Rack A 426 120 60 Hz 3
Phase L5-30P 2 991 (3726)
UGNT#2
Rack C 200 120 60 Hz 3
Phase L5-30P 2 888
14. Equipment environmental requirements are as follows:
Description Weight (Lbs.) Watts
Operating Temp (*F)
Operating Humidity
Nominal Heat
(BTU/HR)
Ventilation
Rack #1 249 1847 32 to 104 5% to 95% NC 6303 Front to
Back
Rack #2 425 1866 32 to 104 5% to 95% NC 6367 Front to
Back
Rack #3 871 4882 50 to 95 30% to 80% NC 16658 Front to
Back
Rack #4 1092 7466 50 to 95 30% to 80% NC 25475 Front to
Back
Rack #5 417 3051 50 to 95 10% to 80% NC 10411 Front to
Back
Rack #6 372 1488 50 to 95 20% to 60% NC 5077 Front to
Back Rack #8
Ops 142 152 32 to 95 10% to 90% NC 518 Ambient
Operator #1 & #2 46 380 41 to 95 30% to
80% NC 1300 Ambient
Operator #3 46 380 41 to 95 30% to
80% NC 1300 Ambient
UGNT#1
Rack A 426 991
(3726) 50 to 86 30% to
70% NC
(11,443)
Front to Back
UGNT#2
Rack C 200 888 41 to 95 10% to
90% NC 2727 Front to Back
| 1 PART 1 GENERAL |
| 1.1 SCOPE OF PROJECT |
| A. This project is for the placement of a pre-fabricated building on the south side of Building 137, Greeley ANG Station, Greeley, CO. |
| B. Generally, the work includes the following objectives: |
| 1. Provide a 310 sqft minimum modular data center capable of housing up to 12ea server racks, 4 desks for personnel; and meeting NFPA, Unified Facility Criteria, DoDM 5200.01 Security Standards, Weld County, and City of Greeley Codes for occupied spac... |
| 2. A modular shelter similar to the C-FORTS 96, modified to meet the requirements of paragraph 1 above; or government approved equivalent, shall be considered sufficient to meet this requirement. |
C. Specifications, concept drawings, manufacturer instructions, standards and government provided minimum specifications provided herein as part of the bid package are to be incorporated into the work and adapted / altered as necessary to meet the req...
| 1.2 LOCATION |
| A. Greeley Air National Guard Station (GANGS) is in Greeley, Colorado. The project site is located at 2605 East 8th Street, on the south side of building 137, within the Restricted Area of Greeley ANG Station. |
| 1.3 bid schedule options |
| A. Base Bid: |
| 1. 1ea Modular Data Center as described in Part 2 of this section. |
| B. Options: |
| 1. Installation of Government provided GSA combination lock on shelter door. |
| 1.4 WORK NOT IN CONTRACT (N.I.C.) |
| A. All items and work indicated on the drawings or in the specifications as N.I.C. will be furnished and installed by the Government. All furniture, unless otherwise described, will be furnished and installed by the government. |
| B. Communications wiring between bldg. 137 and the shelter, as well as communications wiring within the shelter shall be performed by the government. |
| C. Server racks, servers, and communications equipment shall be furnished and installed by the government. |
| 1.5 GENERAL REQUIREMENTS |
| A. The Contractor shall be thoroughly familiarized with the minimum specifications to ensure against misunderstanding during contract execution. |
| 1.6 MISCELLANEOUS REQUIREMENTS |
| A. Preservation and Restoration of Property: Contractors shall be responsible for the preservation of all public and private property on the surface or underground, along and adjacent to the work, and shall conduct their operations in a manner that wi... |
| B. Where any direct or indirect damage is done to public or private property by or on account of any act, omission, neglect or misconduct in the execution of the work, or because of non-execution thereof, on the part of the Contractors, such property ... |
| C. All work performed under this Contract shall proceed with due care and safety for all personnel and pedestrians. All work shall be planned so that the Project can be secured against unauthorized entry at the end of each working day. |
| 2 PART 2 PRODUCTS |
| 2.1 NONPERSONAL SERVICES: |
| A. The contractor shall supply all labor, tools, equipment, transportation and supervision necessary to purchase and install a minimum of 310 sqft of modular data center prefabricated building, equivalent to the C-FORTS 96 (or government approved equi... |
| 1. Workspace capable of housing 4ea 48”x36” minimum desks (GFGI), with ADA clearance around each. |
| 2. Walls meeting DoDM 5200.01-V3 security standards. |
| 3. If windows are installed, shall provide coverings to meet DoDM 5200.01-V3 security standards. |
| 4. Clad exterior doors with deadbolts and exterior lights, (OPTION: install GSA approved combination lock, if option is selected by the Government). |
| 5. All electric heat and air. Air conditioning shall be capable of providing a minimum of 10 tons of cooling. |
| 6. If multiple units are provided, they shall be connected in a manner that allows safe passage of cabling and personnel between units. |
| 7. Power, cooling, and structural capability should at a minimum support Racks 1-8 being located in a single structure, at the center of the floor, allowing front and rear access to all of the IT racks. |
| 8. Structural capability should allow for the insertion or removal of any given rack, while fully loaded, up to 1,200 lbs. in weight. |
| 9. Rack dimensions are as follows: |
| a. Racks 1 thru 5 = 40 rack units tall, 19” wide rack mount, 36” deep (34” usable depth) |
| b. Rack 6 = 40 rack units tall, 19” wide rack mount, 30” deep (28” usable depth) |
| c. Rack 8 = Ops Area - 19 rack units tall, 19” wide rack mount, 18” deep (16” usable depth) |
| d. UGNT#1 (Rack C) = 38 rack units tall, 19” wide rack mount, 30” deep (20”L x 30”D x 72”H) |
| e. UGNT#2 (Rack A) = 38 rack units tall, 19” wide rack mount, 30” deep (20”L x 30”D x 72”H) |
| 10. Equipment power requirements are as follows: |
| 14. Equipment environmental requirements are as follows: |