B119_Roof_Replacement_Q&A_22AUG19.pdf
PDF 15 KB Posted
- Attached to
- BLD119 Roof Replacement
- Solicitation number
- W912L8-19-B-0091
About this file
Q&A B119 Roof Replacement as of 22AUG2019
View the file
Other files
| File | Type | Posted |
|---|---|---|
| OF_1419_-_167_B119_Roor_Replace.pdf | ||
| OF_1419A_-_167_B119_Roof_Replace.pdf | ||
| B119_Roof_Q&A_26AUG19.pdf | ||
| B119_Roof_Q&A_23AUG19.pdf | ||
| 119_Roof_Project.pdf | ||
| Site_Visit_PP_-_B119_Roof_Replacement.pptx | PPTX presentation | |
| SOW_-_Roof_repairs_BLDG_119_-_Signed.pdf | ||
| IFB_-_167_B119_Roof_Replacement.pdf | ||
| NEW_SFS_Background_Check_Form_-_UPDATED_2019_March.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
8/23/2019 Page 1 of 1
SOLICITATION W912L8-19-B-0091
Building 119 Roof Replacement
167th Airlift Wing, Martinsburg, West Virginia, Air National Guard
Invitation for Bid (Questions) and Answers
RFI # Date Question Answer
1. August 22 Is the project to include the mechanical room roofs?
No mechanical rooms are included in the project scope.
2. August 22 Are the gutters and downspouts to be included in the scope?
Yes, contractor shall remove existing and provide and install new guttering and downspouts adequate for new roof.
3. August 22 Does the lightening protection system have to be repaired?
Yes, the LPS system is included in this work.
The contractor shall remove existing LPS system and reinstall with appropriate repairs the LPS and test IAW UFC 3-575-01 and AFI32-1065 testing requirements.