Site_Visit_Slides_28_Jul_2017.pdf

PDF 256 KB Posted

Attached to
Repair Track Bldg 422 Federal contract opportunity
Solicitation number
W912L7-17-B-0003
Issued by
Department of the Army Tennessee Army National Guard

About this file

Site Visit Slides 17B0003

View the file

Other files for this federal contract opportunity

Other files attached to Repair Track Bldg 422, newest first.
File Type Posted
W912L717B0003_Amendment_3.pdf PDF
W912L717B0003_Amendment_2.pdf PDF
Preproposal_minutes_W912L717B0003.pdf PDF
Sign_In_Sheet.pdf PDF
Amendment_1_Drawings.zip ZIP file
W912L717B0003_Amendment_1.pdf PDF
Repair_Track_21_Apr_2017_Specifications.pdf PDF
17B0003_Documents.zip ZIP file
Construction_PWS,_PSXE172004_Repair_Track_Bldg_422.pdf PDF
Addendum_1.zip ZIP file
W912L717B0003_Final.pdf PDF
Show all 11

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

UPGRADE BASE EXTERIOR

LIGHTINGL; REPAIR PAVEMENT

AND DRAINAGE; REPAIR TRACK

AT MCGHEE TYSON ANG BASE, TN

Pre-Proposal Conference

28 Jul 2017

134 MSC, MCGHEE TYSON ANG BASE, TN

INTRODUCTION

CMSgt Richard Lusby– Contracting Officer

Maj David Barrett– Technical Representative

SYNOPSIS

• Upgrade Base Exterior Lighting at McGhee Tyson

Air National Guard Base, TN. W912L7-17-B-0001

•The estimated cost range -$1,000,000 and

$5,000,000.

•A firm-fixed price contract will be awarded.

•Award is set aside for small businesses (NAICS –

238210)

•Small Business Size Standard is $15 Million

•The contract will be awarded based on lowest price.

•Repair Pavements & Drainage Base wide at McGhee

Tyson Air National Guard Base, TN. W912L7-17-B-

•The estimated cost range -$1,000,000 and

$5,000,000.

•A firm-fixed price contract will be awarded.

•Award is set aside for small businesses (NAICS –

237310)

•Small Business Size Standard is $36.5 Million

•Repair Track Building 422 at McGhee Tyson Air

National Guard Base, TN. W912L7-17-B-0003

•The estimated cost range -$5000,000 and $1,000,000.

•A firm-fixed price contract will be awarded.

•Award is set aside for small businesses (NAICS –

237990)

•Small Business Size Standard is $36.5 Million

SOLICITATION, PLANS

& SPECIFICATIONS

• On the web: https://www.fbo.gov/

– Solicitation

– Plans and Specifications

– Questions & Answers document

– Pre-Proposal presentation

– Amendments

• check regularly & refresh web page

IFB

• In the invitation for bid (IFB), FAR Part 14, process, a public bid opening occurs when the bids are due and the prices are read to the public

– There can be no discussion

– No correction of mistakes in most cases

– Award is always to the low responsible bidder

WHAT IS THE CONTRACT

PERIOD

Construction period is 180 calendar days after receiving the Notice to

Proceed for both requirements

BID PACKAGE IN ACCORDANCE WITH

SECTION 00010 NOTES, NOTE 11

• Offer, Standard Form (SF) 1442 front and back signed

• Section 00010 Line Items- all items must be priced

• A valid Bid Bond. Standard Form 24. Section 0700 – Clause 52.228-1.

• Section 00600, Representations and Certifications, completed and return only additional certifications found in this section In addition, the offeror must have entered current and complete data within the past year in Online Representations and Certifications at https://www.sam.gov see 52.204-8 in solicitation

SECTION 00010 NOTES, NOTE 11 - Continued

• When completing the “Offeror” portion of the SF 1442

(Blocks 14 – 20), an official having the authority to contractually bind the company must sign the SF 1442 in accordance with FAR 4.102. One copy of the SF1442 is required to have an original signature. Section 00010 Line

Items- all items must be priced

• All amendments to the solicitation must be acknowledged.

• Mark the front of the envelope with the following: “BID No. W912L7-17-B-0001, W912L7-17-B-0002, or W912L7- 17-B-0003 as applicable” and the Name and Address of Bidder. See Block 13A of SF 1442 for required number of copies.

SECTION 00010 NOTES, NOTE 11 - Continued

• ALL ITEMS ON THE PREVIOUS SLIDES ARE

IN THE SOLICITATION INSTRUCTIONS. IT

IS THE RESPONSIBILITY OF THE BIDDER

TO MAKE SURE THAT THEIR BID

CONFORMS TO THE SOLICITATION.

PROPOSAL DUE DATES

• W912L7-17-B-0001 - Bids are due 2:00 P.M. (EST) 21 August 2017

• Proposal must be signed by officer of your company

• No facsimile or electronic offers will be accepted

• W912L7-17-B-0002 - Bids are due 2:00 P.M. (EST) 23 August 2017

• Proposal must be signed by officer of your

• W912L7-17-B-0003 - Bids are due 2:00 P.M. (EST) 22 August 2017

• Proposal must be signed by officer of your

IMPORTANT REMINDERS

W912L7-17-B-0001

•Questions concerning these project must be received by close of business 15 August 2017. Section 00100 Paragraph 5 for format.

•Contractor must submit information listed in Section 00100

Notes, paragraph 4.2 in order to gain access to installation for dropping off bids. Delivery must allow for vehicle inspection time at gate. MUST BE SUBMITTED BY 17 August 2017

•Wage determination TN170078, Mod 0, Dated 1/06/2017, Building is applicable

• Liquidated damages to the Government in the amount of

$468.76 for each calendar day of delay until the work is completed or accepted and a one time fixed cost per modification of $320.78.

W912L7-17-B-0002

•Questions concerning these project must be received by close of business 15 August 2017. Section 00100 Paragraph 5 for format.

•Contractor must submit information listed in Section 00100

Notes, paragraph 4.2 in order to gain access to installation for dropping off bids. Delivery must allow for vehicle inspection time at gate. MUST BE SUBMITTED BY 17 August 2017

•Wage determination TN170148, Mod 0, Dated 1/06/2017, Highway is applicable

• Liquidated damages to the Government in the amount of

$468.76 for each calendar day of delay until the work is

W912L7-17-B-0003

•Questions concerning these project must be received by close of business 15 August 2017. Section 00100 Paragraph 5 for format.

•Contractor must submit information listed in Section 00100

Notes, paragraph 4.2 in order to gain access to installation for dropping off bids. Delivery must allow for vehicle inspection time at gate. MUST BE SUBMITTED BY 17 August 2017

•Wage determination TN170148, Mod 0, Dated 1/06/2017, Highway is applicable

• Liquidated damages to the Government in the amount of

$468.76 for each calendar day of delay until the work is

HELPFUL WEBSITES

https://www.fbo.gov https://www.sam.gov https://www.wdol.gov

HOW QUESTIONS WILL BE

HANDLED

• Questions must be submitted in writing only via email to:

richard.m.lusby.mil@mail.mil

• Use Format in Section 00100, Para 5.1

• DO NOT CALL TECHNICAL PERSONNEL OR

A&E- THIS WILL DELAY GETTING AN

ANSWER

ANSWERS TO QUESTIONS

• All questions, on a non-attribution basis, and the answers will be posted to the web site https://www.fbo.gov/

• If necessary addendums, issued by an amendment, will also be posted

• Check web site regularly and don’t forget to refresh web page!!

IMPORTANT

OFFERORS ARE STRONGLY

CAUTIONED TO CAREFULLY

READ THE REQUIREMENTS OF

THE SOLICITATION AND

COMPLY ACCORDINGLY

Questions ???

Site Visit Follows This Briefing