Pre-Proposal_Slides.pdf

PDF 39 KB Posted

Attached to
Cyber Fully Operational Capability (FOC) Construction B735
Solicitation number
W912L7-15-B-0002
Issued by

About this file

Pre-Bid Slides

View the file

Other files

File Type Posted
W912L7-15-B-0002-0004.pdf PDF
W912L7-15-B-0002-0003.pdf PDF
Bid_Questions_8.26.15.pdf PDF
Add_No_2.doc DOC document
14577-Elec_Add_(8-25-15).pdf PDF
W912L7-15-B-0002-0002.pdf PDF
Add_No_1.pdf PDF
13010_Communications_Rough-InRev1.pdf PDF
IT2.1.pdf PDF
13030_Computer_and_Telephone_Cabling-REV1.pdf PDF
IT2.2.pdf PDF
C1.1.pdf PDF
09650_BSD-Resilient_Flooring.pdf PDF
IT1.1.pdf PDF
QUESTIONS_AND_ANSWERS_24_AUG_2015.pdf PDF
QUESTIONS_AND_ANSWERS.pdf PDF
Pre-Bid_Sign-In_Roster.pdf PDF
W912L7-15-B-0002-0001.pdf PDF
W912L7-15-B-0002.pdf PDF
Show all 19

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project # BKTZ129083 Construct Cyber FOC, Building (B735)at the 118th Airlift

Wing , Nashville, TN

Pre-Bid Conference 04 August 2015

USPFO for Tennessee, Nashville, TN

INTRODUCTION

Randal Halbrooks – Contracting Officer

Samuel Beard – Contracting Officer, Chief Contracting Division

SYNOPSIS

•Project # BKTZ129083, Construct Cyber FOC, Building (B735)

• Magnitude is between $1,000,000 and $5,000,000 •A firm-fixed price contract will be awarded •Award will be A SMALL BUSINESS SET-ASIDE •The contract will be awarded using Sealed Bidding Procedures described in the Federal Acquisition Regulation (FAR) part 14 •Evaluation factors – listed in solicitation

Additive Bid Items (ABIs)

• There are a total of five ABIs, they will be accepted in the order they are listed on the bid schedule.

• If funds are available, the Government will evaluate bids in the order of ABI 1 then ABI 2, then ABI 3, then ABI 4, then ABI 5.

SOLICITATION, PLANS

& SPECIFICATIONS

• Via download at https://www.fbo.gov/

• Via CD by contacting COR, Major Nathan Smith https://www.fbo.gov/

WHAT IS THE CONTRACT

PERIOD?

Construction period is 365 calendar days after receiving the Notice to

Proceed

WHAT YOU MUST SUBMIT

• Price – in accordance with the bid schedule in the solicitation.

• The successful bidder will respond to a responsibility questionnaire.

BID DUE DATE

• Bids are due September 1, 2015 1:00PM

Central Time.

• Bid opening will be at 3041 Sidco Drive

Nashville, TN 37204. Please arrive early to allow for ample time to access base.

HELPFUL WEBSITES

• www.sam.gov/

• http://www.gpo.gov/davisbacon/all states.html http://www.sam.gov/ http://www.gpo.gov/davisbacon/mi.html

HOW QUESTIONS WILL BE

HANDLED

• Questions must be submitted in writing only via email to:

randal.halbrooks.mil@mil.mail

• Submit questions NLT 1:00PM, 25 August

• DO NOT CALL TECHNICAL

PERSONNEL OR A&E- THIS WILL

DELAY GETTING AN ANSWER

ANSWERS TO QUESTIONS

• All questions, and the answers will be posted as an attachment to the solicitation at https://www.fbo.gov/.

Questions ???

Site Visit Follows This Briefing

Project # BKTZ129083 Construct Cyber FOC, Building (B735)at the 118th Airlift Wing , Nashville, TN
INTRODUCTION
SYNOPSIS
Additive Bid Items (ABIs)
SOLICITATION, PLANS�& SPECIFICATIONS
WHAT IS THE CONTRACT PERIOD?
WHAT YOU MUST SUBMIT
BID DUE DATE
HELPFUL WEBSITES
HOW QUESTIONS WILL BE HANDLED
ANSWERS TO QUESTIONS
Questions ???

File details come from the government source that posted it. Updated .