VUBV172265_SOW.pdf

PDF 22 KB Posted

Attached to
Update Electrical Service Smoky Hill HQ Federal contract opportunity
Solicitation number
W912JC-18-B-5007
Issued by
Department of the Army

About this file

VUBV 172265 Statement of Work

View the file

Other files for this federal contract opportunity

Other files attached to Update Electrical Service Smoky Hill HQ, newest first.
File Type Posted
OF_1419_Upgrade_Elcetrical_SH_HQ_Completed.pdf PDF
Site_Visit_Sign_in_Sheet_HQ_Electrical.pdf PDF
Pre-Proposal_Minutes_SH_HQ_Electrical_Upgrade.pdf PDF
VUBV172265_Drawings.pdf PDF
W912JC-18-B-5007.pdf PDF
VUBV172265_Submittal_Listing.pdf PDF
184_CES_Specifications.pdf PDF
Wage_Determination_KS50_MOD_02.pdf PDF
SITE_VISIT_INFORMATION_Upgrade_Electrical_Service_Smoky_Hill_HQ.pdf PDF
Presolicitation_Synopsis_Upgrade_Electrical_Service_Smoky_Hill_HQ.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

UPGRADE ELECTRICAL SERVICE AT HQ AREA

SMOKY HILL RANGE SITE, SALINA, KS (KANSAS ANG)

PROJECT VUBV172265

11 June 2018

SW-1 LOCATION: Smoky Hill National Guard Range Site, Salina, Kansas. Arrangements for entrance onto Smoky Hill must be made by contacting MSgt Glen Godsey at (316) 759-8579 between the hours of 7:00 a.m. and 4:00 p.m., Monday through Friday.

SW-2 SCOPE OF WORK: The work covered in this contract consists of furnishing all labor, expertise, equipment, materials, facilities, transportation, and appliances necessary to perform operations in connection with the work described in paragraph SW-3. It is the intent of the government for the contractor to provide a complete and useable system. Any relevant details required for a complete system that is omitted in the contract plans and specifications will be provided by the Contractor at no cost to the government.

SW-3 SUMMARY OF WORK: Work shall consist of but is not limited to the following:

Terminate and demolish approximately 980 LF of 3-Phase O/H Primary with Neutral including the poles.

Contractor has salvage rights and must remove all demolished material. Remove approximately 125 LF of 3-Phase U/G Primary. Install one 4-way sectionalizer cabinet, handholes, ductbank and approximately 750 LF of 3-Phase Primary (See Drawings for more details).

SW-4 CODES & STANDARDS: All work performed under this contract shall be in accordance with federal, state and local codes & standards, as well as widely accepted industry standards, including but not limited to: American Institute of Architects, American Concrete Institute, American Institute of Electrical Engineers, American Institute of Steel Construction, American National Standards Institute, American Society of Heating, Refrigerating and Air-Conditioning Engineers, American Society of Mechanical Engineers, American Society of Testing Materials, National Bureau of Standards, National Electric Code, American Welding Society, Brick Institute of America, Building Officials and Code Administrators, Federal Aviation Administration, National Fire Protection Association, National Electric Code, Occupational Safety & Health Administration, Rubber Manufacturers Association, Underwriters Laboratories, and the Kansas DOT. Standard specification. Additionally, all requirements of the Kansas Department of Health must be satisfied in their entirety for any work performed or materials bought under this contract. Failure to comply with any of the aforementioned codes and standards shall be considered as a failure to comply with contract specifications.

SW-5 UTILITIES: Contractors shall coordinate with all local utilities having jurisdiction. Contact Smoky Hill ANGR civil engineer personnel (316-759-8579) to request dig permit.

SW-6 CALL BEFORE YOU DIG: Contact Smoky Hill ANGR civil engineer personnel (316-759-8579) to request dig permit. All contractors shall be responsible for maintaining all markings throughout construction period.

SW-7 MATERIALS: The materials shall conform to specifications, applicable industry codes and standards and the manufacturer's recommendations, which ever is more stringent. Certificates of compliance and Technical Data Sheets are required for all materials supplied.

SW-8 SITE INSPECTION: The Contractor is required to acknowledge, at time of Bid Opening that said contractor has inspected, and is fully cognizant of conditions at the site. No allowance or consideration will be given after award for any condition(s) which was (were) existing at the time of the site visit.

SW-9 BASE ACCESS: The contractor shall be granted access to Smoky Hill ANGR to complete this project. All other areas are off limits. The Government reserves the right to deny access to any person, with no consequence to the contract.

Access and General Protection/Security Policy and Procedures. This standard language is for contractor employees with an area of performance within Government controlled installation, facility, or area. The contractor shall comply with all applicable installation/facility access and local security policies and procedures, which may be obtained from the Contracting Officer’s Representative (COR). The contractor shall also provide all information required for background checks to meet installation access requirements to be accomplished by the local installation’s Security Forces, Director of Emergency Services or local Security Office. The contractor shall ensure compliance with all personal identity verification requirements as directed by DoD, HAF and/or local policy. Should the Force Protection Condition (FPCON) change, the Government may require changes in contractor security matters or processes.

For Contractors that do not require CAC, but require access to a DoD Facility and/or Installation.

Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (AFI 31-101 and AFI 10-245), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

SW-10 SAFETY: Compliance with OSHA and other applicable laws and regulations for the protection of employees is exclusively the obligation of the commercial contractor. Government employees must comply with AFOSH. All contractors and employees will attend a pre-construction meeting prior to project work beginning.

SW-11 CLEAN-UP: Clean-up and remove debris generated by this contract to an approved off-base location. Two (2) copies of the receiving (tipping or dumping) tickets, with a cover letter from the Prime Contractor stating the full name and address of the location to which debris was taken.

SW-12 GOVERNMENT RESOURCES: No Government resources shall be made available to the contractor, unless otherwise stated in this Statement of Work. The contractor shall provide for all necessary resources to provide a complete and usable facility or systems as described in the contract documents. The contractor shall not obligate Government resources in any manner. The Government shall seek remedy for any obligation or encumbrance imposed by the Contractors actions. Government resources include, but are not limited to, government owned materials, equipment, tools, vehicles, personnel and facilities.

SW-13 SUPPLEMENTAL ATTACHMENTS:

PDF Drawings (4 Sheets)

STATEMENT OF WORK
PROJECT VUBV172265
11 June 2018