Project related Question & Answers as of 14 Aug 2019, 8:24 AM

View the file

Other files

Show all 11

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTIONS AND ANSWERS RELATED TO:

W912JB-19-R-5016

Munitions Roof Repair as of 14 Aug 2019

Dated: 14 Aug 2019

Q1. In considering the Munitions roof project and ways to make this beautiful, yet labor intensive project less so, we are wondering about the kind of equipment allowed in this area. For example, we are considering conveyors to remove and refill the soil and a skid steer for the same purpose. Would they be allowed? Please advise.

A1. Height restriction is 75’ around the air field. All other equipment is permitted.