W912JA-18-B-6002_SF_30_Amend_0001.pdf

PDF 142 KB Posted

Attached to
Construction of Storage Facility Federal contract opportunity
Solicitation number
W912JA-18-B-6002
Issued by
Department of the Army Alabama Army National Guard

About this file

Amendment 1 SF 30

View the file

Other files for this federal contract opportunity

Other files attached to Construction of Storage Facility, newest first.
File Type Posted
Abstract.pdf PDF
2018-05-24_Addendum__2.pdf PDF
W912JA-18-B-6002_SF_30_Amend_0003.pdf PDF
W912JA-18-B-6002_Amend_0003.pdf PDF
RFI_5_24_2018.docx DOCX document
CE_Structure_Site_Visit_Roster.pdf PDF
W912JA-18-B-6002_Amend_0002.pdf PDF
2018-05-17_Addendum__1.pdf PDF
W912JA-18-B-6002_SF_30_Amend_0002.pdf PDF
Pre-Bid_slides.ppt PPT presentation
W912JA-18-B-6002_FINAL.pdf PDF
W912JA-18-B-6002_Amend_0001.pdf PDF
Show all 12

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F6L32D7257AW01

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Purpose of Amendment is to add 2 additive bid items and associtated clauses.

1. CONTRACT ID CODE PAGE OF PAGES

J 1 5

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 27-Apr-2018

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912JA-18-B-6002

X 9B. DATED (SEE ITEM 11)

27-Apr-2018

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

27-Apr-2018

CODE

NGAL-PFO-PC

187TH FIGHTER WING - MSG,

5187 SELMA HIGHWAY

MONTGOMERY AL 36108-4824

W912JA 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W912JA-18-B-6002

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION 00010 - SOLICITATION CONTRACT FORM

CLIN 0001

Exhibit A has been added.

CLIN 0002

The signal code A has been added.

The PSC code C1AA has been added.

The PROG code C20 has been added.

The WSC Equipment code 000 has been added.

The MDAP/MAIS Code 000 has been added.

CLIN 0003 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0003 1 Job OPTION Additive Bid Item 1

FFP

Exterior Cladding Upgrades: Alternate shall include all plant labor and material required for the installation of additional brick masonry exterior cladding, split faced CMU veneer, and aluminum composite wall panel systems as depcited on alternate elevations drawing sheet A4.1A, alternate sections and details drawings sheets A5.1A/A5.2A. If alternate is not awarded, the base bid shall include installation of aluminum break metal and metal wall panel systems as depicted in Base Bid elevations drawing sheet A4.1 and base bid sections and details drawings sheets A5.1/A5.2/A5.3.

FOB: Destination

SIGNAL CODE: A

PSC CD: C1AA

NET AMT

CLIN 0004 is added as follows:

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0004 1 Job OPTION Additive Bid Item 2

FFP

Metal Soffit Panels: Includes all plant, labor, and materials for the installation of metal soffit panels at the underside of all roof structure as dpeicted on alternate roof and reflected ceiling plans drawings sheet A2.2A and alternate sections and details drawing sheets A5.1A/A5.2A/A5.3A. If the alternate is not awarded, the base bid shall include no finished soffit/ceiling materials (structure and underside of roof panels will be exposed to view) as depicted in base bid roof and reflected ceiling plan drawing sheet A2.2 and base bid sections and details drawing sheets A5.1/A5.2/A5.3. If the alternate is not awarded the base bid shall include installation of break metal flashings at perimeter eave conditions as shown on details 2/A2.2 and 3/A2.2.

FOB: Destination

SIGNAL CODE: A

PSC CD: C1AA

NET AMT

INSPECTION AND ACCEPTANCE

The Acceptance/Inspection Schedule for CLIN 0002 has been changed from:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

N/A N/A N/A Government

To:

INSPECT AT INSPECT BY ACCEPT AT ACCEPT BY

Destination Government Destination Government

The following Technical Office was added for CLIN 0002:

F6L32D--187TH CIVIL ENGINEERING / FOMA

ADAM.W.SANDERS.MIL@MAIL.MIL

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

The following Acceptance/Inspection Schedule was added for CLIN 0003:

The following Technical Office was added for CLIN 0003:

ADAM.W.SANDERS.MIL@MAIL.MIL

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

The following Acceptance/Inspection Schedule was added for CLIN 0004:

The following Technical Office was added for CLIN 0004:

ADAM.W.SANDERS.MIL@MAIL.MIL

5187 SELMA HIGHWAY

BLDG 1801

MONTGOMERY AL 36108

SECTION 00100 - BIDDING SCHEDULE/INSTRUCTIONS TO BIDDERS

The following have been added by full text:

252.236-7007 ADDITIVE OR DEDUCTIVE ITEMS. (DEC 1991)

(a) The low offeror and the items to be awarded shall be determined as follows --

(1) Prior to the opening of bids, the Government will determine the amount of funds available for the project.

(2) The low offeror shall be the Offeror that --

(i) Is otherwise eligible for award; and

(ii) Offers the lowest aggregate amount for the first or base bid item, plus or minus (in the order stated in the list of priorities in the bid schedule) those additive or deductive items that provide the most features within the funds determined available.

(3) The Contracting Officer shall evaluate all bids on the basis of the same additive or deductive items.

(i) If adding another item from the bid schedule list of priorities would make the award exceed the available funds for all offerors, the Contracting Officer will skip that item and go to the next item from the bid schedule of priorities;

and

(ii) Add that next item if an award may be made that includes that item and is within the available funds.

(b) The Contracting Officer will use the list of priorities in the bid schedule only to determine the low offeror. After determining the low offeror, an award may be made on any combination of items if --

(1) It is in the best interest of the Government;

(2) Funds are available at the time of award; and

(3) The low offeror's price for the combination to be awarded is less than the price offered by any other responsive, responsible offeror.

(c) "Example." The amount available is $100,000. Offeror A's base bid and four additives (in the order stated in the list of priorities in the bid Schedule) are $85,000, $10,000, $8,000, $6,000, and $4,000. Offeror B's base bid and four additives are $80,000, $16,000, $9,000, $7,000, and $4,000. Offeror A is the low offeror. The aggregate amount of offeror A's bid for purposes of award would be $99,000, which includes a base bid plus the first and fourth additives. The second and third additives were skipped because each of them would cause the aggregate bid to exceed $100,000.

(End of Summary of Changes)