QUESTIONS AND ANSWERS_7_7_21.pdf

PDF 114 KB Posted

Attached to
Refuse Services Federal contract opportunity
Solicitation number
W912HZ21R0016
Issued by
Department of the Army Corps of Engineers Engineer Research and Development Center

About this file

This document contains a questions and answers file and a federal contract opportunity solicitation. The questions and answers file provides details on a prior contract award from 2016 for refuse removal services at the U.S. Army Engineer Research and Development Center in Hanover, New Hampshire. The total award value was $226,496.88 to Casella Waste Management, Inc. The solicitation seeks fixed-price proposals for refuse services, including zero sort hauls, wood hauls, and construction and demolition debris removal. Proposals are due by July 11, 2021 to be considered for the one base year and four option year contract. The North American Industry Classification System code is 56211 and the size standard is $41.5 million in average annual receipts. Evaluation will consider pricing and factors in Section M of the solicitation. The contracting agency is the Department of the Army Corps of Engineers Engineer Research and Development Center.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

QUESTION 1: WHAT WAS THE PRIOR AMOUNT AWARDED ON THIS

CONTRACT?

ANSWER 1:

Contract Award Date: May 11, 2016 Contract Award Number: W913E5-16-C-0003 Contractor Awarded Name: CASELLA WASTE MANAGEMENT, INC.

Contractor Awarded Address: White River Junction, VT 05001 USA Base and All Options Value (Total Contract Value): $226,496.88

QUESTION 2: CAN THIS WORK BE SUBCONTRACTED 100%?

ANSWER 2: Yes.

QUESTION 3: WOULD RECENT CPARS EVALUATIONS WORK FOR A

SUBSTITUTION FOR THE PPQ AS LONG AS THEY ARE THE SAME AS THE PAST

PERFORMANCE REFERENCES USED IN THE BID?

ANSWER 3: Yes.

QUESTION 4: FOR CLIN ITEMS XXX4; CAN A LINE BE ADDED FOR A PER TON

RATE FOR THE CONCRETE? HOW MANY 15YD ROLLOFF CLEAN CONCRETE

HAULS AND TONS WERE REPORTED IN THE FULL YEAR OF 2019 AND 2020?

HOW MANY 15YD ROLLOFF CONTAMINATED CONCRETE HAULS AND TONS

WERE REPORTED IN THE FULL YEAR OF 2019 AND 2020? FOR THE FULL

YEARS OF 2019 AND 2020; HOW MANY 15YD C&D HAULS AND TONS WERE

REPORTED? FOR THE FULL YEARS OF 2019 AND 2020; HOW MANY 30YD C&D

HAULS AND TONS WERE REPORTED?

ANSWER 4: Line Item 0004, line items will be priced in accordance with the current line items structure.

QUESTION 5: WHAT DOES THE GOVERNMENT MEAN BY “CONTAMINATED

CONCRETE”? WILL THIS CONCRETE HAVE ANY METAL AND/OR REBAR

STICKING OUT? WILL THIS CONCRETE BE BROKEN DOWN TO A

MANAGEABLE SIZE FOR THE CONTRACTOR TO SAFELY DISPOSE?

ANSWER 5: Yes. The concrete will have rebar and metal in it and sized in accordance to be in a 15 yard rolloff.

QUESTION 6: FOR CLIN ITEMS XXX2; FOR FULL YEARS 2019 AND 2020; HOW

MANY 15YD ROLLOFF ZERO SORT HAULS AND TONS WERE REPORTED?

ANSWER 6: 5 per year.

QUESTION 7: FOR CLIN ITEMS XXX3; FOR FULL YEARS 2019 AND 2020; HOW

MANY 30YD ROLLOFF WOOD HAULS AND TONS WERE REPORTED?

ANSWER 7: 10 per year.