AMEND 0004_W912HY21B0019.pdf
PDF 738 KB Posted
- Attached to
- Gulf Intracoastal Waterway, Texas High Island to Rollover and Bolivar Flare, Pipeline Dredging
- Solicitation number
- W912HY21B0019
About this file
This document package includes specifications for a pipeline dredging project on the Gulf Intracoastal Waterway in Texas. The solicitation seeks dredging of sections between High Island and Rollover Pass, and in the Bolivar Flare area. Work includes removal of shoaled material to required depths and placement in designated upland containment areas or a beneficial use site. The contract will be awarded by the USACE Galveston District and work must be completed within 215 days of the notice to proceed. Bidders are required to dredge a minimum daily volume and use plant with certain operational capacities. The specifications provide requirements for dredging and placement operations, environmental protections, permits, safety protocols, and surveys to measure quantities removed.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
THE SPECIFICATIONS FOR SOLICITATION NO. W912HY21B0019, GIWW, TEXAS HIGH ISLAND TO ROLLOVER AND BOLIVAR FLARE PIPELINE DREDGING, FOR WHICH BID OPENING IS SCHEDULED FOR 3 SEPT. 2021 AT 2:00 P.M.Centrall Time ARE HEREBY AMENDED AS FOLLOWS:
CONTINUE ON PAGE 2
1. CONTRACT ID CODE PAGE OF PAGES
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W912HY21B0019
X 9B. DATED (SEE ITEM 11)
29-Jul-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO.
5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE
DATE
31 Aug-2021
CODE
US ARMY CORPS OF ENGINEERS
2000 FORT POINT ROAD
P.O. BOX 1229
GALVESTON TX 77553-1229
W912HY 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HY21B0019
A0004-2
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
1.THE SPECIFICATIONS FOR SOLICITATION NO. W912HY21B0019, GIWW, TEXAS HIGH
ISLAND TO ROLLOVER AND BOLIVAR FLARE PIPELINE DREDGING, IN CHAMBERS
AND GALVESTON COUNTIES, TEXAS, ARE HEREBY AMENDED AS FOLLOWS:
a) Specifications.
(1) SECTION 00 11 00.00 45, BID SCHEDULE – The enclosed SECTION 00 11 00.00 45 entitled BID SCHEDULE supersedes that issued with this Solicitation.
(2) SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD – The enclosed SECTION 00 73 00.01 45 entitled SPECIAL CONTRACT REQUIREMENTS, STANDARD supersedes that issued with this Solicitation.
(3) SECTION 35 20 23.16 45, PIPELINE DREDGING – The enclosed SECTION 35 20 23.16 45 entitled PIPELINE DREDGING supersedes that issued with this Solicitation.
(4) SECTION 35 20 23.16 45, APPENDIX 1, QUANTITY SUMMARY TABLE – The enclosed SECTION 35 20 23.16 45 entitled APPENDIX 1, QUANTITY SUMMARY TABLE supersedes that issued with this Solicitation.
2. This amendment shall be attached to and become a part of the solicitation.
4 Encls:
1. SECTION 00 11 00.00 45, BID SCHEDULE
2. SECTION 00 73 00.01 45, SPECIAL CONTRACT REQUIREMENTS, STANDARD
3. SECTION 35 20 23.16 45, PIPELINE DREDGING
4. SECTION 35 20 23.16 45, APPENDIX 1, QUANTITY SUMMARY TABLE
SWG FILE NO.: IWW 1101-0299 SOLICITATION NO.: W912HY21B0019
SECTION TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
SECTION 00 11 00.00 45
BID SCHEDULE
PART 1 GENERAL
1.1 BID SCHEDULE
1.1.1 Schedule No. 1 AM#2
1.1.2 Option No. 1 AM#2
1.1.3 Option No. 2 AM#4
1.1.4 Option No. 3
1.1.5 Option No. 4
1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
-- End of Section Table of Contents --
DOCUMENT 00 11 00.00 45 Page 1
TO ACCOMPANY AMENDMENT NO 0004 TO SOLICITATION W912HY21B0019
THIS PAGE INTENTIONALLY LEFT BLANK
DOCUMENT 00 11 00.00 45 Page 2
SECTION 00 11 00.00 45
BID SCHEDULE
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 BID SCHEDULE
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.1 Schedule No. 1 AM#2
Item No. Description Estimated Quantity
Unit Unit Price Estimated Amount
SCHEDULE NO. 1
0001 Mobilization and Demobilization 1 JOB SUM $___________
0002 Pipeline Management - GIWW, High Island to Bolivar Flare - Section Nos. 1-7 & 10-20
1 JOB SUM $___________
0003 Dredging - GIWW High Island to Port Bolivar - Section Nos. 1-7 & 10-18
717,000 C.Y. $_________ $___________
0004 Dredging - GIWW - Bolivar Flare - Section Nos. 19 &
395,000 C.Y. $_________ $___________
TOTAL SCHEDULE NO. 1 $___________
NOTE: Completion time stated in SECTION 00 73 00.01 45 SPECIAL CONTRACT REQUIREMENTS, STANDARD is for Schedule No. 1 work.
DOCUMENT 00 11 00.00 45 Page 3
BID SCHEDULE (CONT'D)
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.2 Option No. 1 AM#2
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 1
0005 Pipeline Management - GIWW, Rollover Pass - Section Nos. 8 & 9
1 JOB SUM $___________
0006 Dredging - GIWW, Rollover Pass - Section Nos. 8 & 9
14,000 C.Y. $_________ $___________
TOTAL OPTION NO. 1 $___________
TOTAL SCHEDULE NO. 1 AND OPTION NO. 1 $___________
NOTE FOR OPTI ON NO. 1: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 15 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 4
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.3 Option No. 2 AM#4
Item No. Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 2
0007 Pipeline Management
- GIWW,Channel to Port Bolivar - Section No. 21
1 JOB SUM $___________
0008 Dredging - GIWW,Channel to Port Bolivar - Section No. 21
149,000 C.Y. $_________ $___________
TOTAL OPTION NO. 2 $___________
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1 AND 2 $___________
NOTE FOR OPTI ON NO. 2: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 20 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 5
(TO BE ATTACHED TO STANDARD FORM 1442)
1.1.4 Option No. 3
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 3
0009 Pipeline Management - GIWW,Causeway to Greens Lake, Placement in Pierce Marsh BUS Cell 1 - Section No. 22
1 JOB SUM $___________
Dredging - GIWW,Causeway to Greens Lake, Placement in Pierce Marsh Cell 1 - Section No. 22
101,000 C.Y. $_________ $___________
0011 Perimeter Berm Raising - Pierce Marsh BUS Cell 1
7,500 L.F. $_________ $_________
TOTAL OPTION NO. 3 $___________
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, AND 3 $___________
NOTE FOR OPTI ON NO. 3: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 55 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 6
1.1.5 Option No. 4
Item No.
Description Estimated Quantity
Unit Unit Price Estimated Amount
OPTION NO. 4
Pipeline Management - GIWW,Causeway to Greens Lake, Placement in Pierce Marsh BUS Cell 2 - Section No. 23
1 JOB SUM $___________
Dredging - GIWW,Causeway to Greens Lake, Placement in Pierce Marsh Cell 2 - Section No. 23
119,000 C.Y. $_________ $___________
0014 Perimeter Berm Raising - Pierce Marsh BUS Cell 2
2,500 L.F. $_________ $_________
TOTAL OPTION NO. 4 $___________
TOTAL SCHEDULE NO. 1 AND OPTIONS NOS. 1, 2, 3, AND 4 $___________
NOTE FOR OPTI ON NO. 4: The Gover nment may exer ci se t hi s Opt i on by wr i t t en not i ce t o t he Cont r act or pr i or t o compl et i on of al l aut hor i zed wor k. An addi t i onal t i me of 30 cal endar days wi l l be added t o t hi s Cont r act f or compl et i on of t hi s Opt i on.
DOCUMENT 00 11 00.00 45 Page 7
(TO BE ATTACHED TO STANDARD FORM 1442)
1.2 EVALUATION OF OPTIONS (July 1990) (FAR 52.217-5)
Except when it is determined in accordance with FAR 17.206(b) not to be in the Government's best interests, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).
-- End of Document --
DOCUMENT 00 11 00.00 45 Page 8
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
DOCUMENT 00 73 00.01 45
SPECIAL CONTRACT REQUIREMENTS, STANDARD
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR
52.211-10)
1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)
1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4) AM#4
1.4 QUANTITY SURVEYS (APR 1984) (FAR 52.236-16)
1.5 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)
1.6 (SCR-S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR
PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011)
1.7 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Section Table of Contents --
DOCUMENT 00 73 00.01 45 Page 1
TO ACCOMPANY AMENDMENT NO. 0004 TO SOLICITATION W912HY21B0019
DOCUMENT 00 73 00.01 45 Page 2
DOCUMENT 00 73 00.01 45
SPECIAL CONTRACT REQUIREMENTS, STANDARD
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984) (FAR
52.211-10)
The Contractor shall be required to:
(a) Commence work under this contract within 10 calendar days after the date the Contractor receives the Notice to Proceed.
(b) Prosecute the work diligently, and
(c) Complete the entire work ready for use not later than 215 calendar days after the date the Contractor receives the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
1.2 LIQUIDATED DAMAGES - CONSTRUCTION (SEPT 2000) (FAR 52.211-12)
(a) If the Contractor fails to complete the work within the time specified in the contract, the Contractor shall pay liquidated damages to the Government in the amount of $3,548.00 for each calendar day of delay until the work is completed or accepted.
(b) If the Government terminates the Contractor's right to proceed, liquidated damages will continue to accrue until the work is completed. These liquidated damages are in addition to excess costs of repurchase under the Termination clause.
1.3 PHYSICAL DATA (APR 1984) (FAR 52.236-4) AM#4
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) The indications of physical conditions on the drawings and in the specifications are the result of site investigations by surveys.
(b) Weather Conditions. Under ordinary conditions, the mean tidal range is about 1.5 feet. The height of tide is largely dependent on the force, direction, and duration of the wind. Strong northerly winds may depress the water surface as much as, and in some instances more than 2 feet below Mean Lower Low Water (MLLW), while southerly winds may raise the water surface as much as, and in some instances more than 4 feet above MLLW.
( c) Cont r act or shoul d expect t o encount er shoal r at es i n excess of 20, 000 cubi c yar ds per mont h i n t he Bol i var Fl ar e, Sect i ons 19 and 20.
(d) Transportation Facilities. The immediate vicinity is served by
DOCUMENT 00 73 00.01 45 Page 3 railroad, highway, and deep and shallow draft channels. The work site is accessible by water via the Gulf Intracoastal Waterway.
(e) Other Information. Channel traffic consists of (deep draft ships, small boats of various sizes, fishing vessels, ferries, tugs, tows consisting of a tug and one or more barges). Traffic will interfere with dredging operations to some extent.
The general shape of the existing section of channel to be dredged is shown by cross sections on the Contract drawings.
Contractor should expect to encounter strong currents in all the dredging sections.
1.4 QUANTITY SURVEYS (APR 1984) (FAR 52.236-16)
(a) Quantity surveys shall be conducted, and the data derived from these surveys shall be used in computing the quantities of work performed and the actual construction completed and in place.
(b) The Government shall conduct the original and final surveys and make the computations based on them. The Contractor shall conduct the surveys for any periods for which progress payments are requested and make the computations based on these surveys. All surveys conducted by the Contractor shall be conducted under the direction of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance.
(c) Promptly upon completing a survey, the Contractor shall furnish the originals of all field notes and all other records relating to the survey or to the layout of the work to the Contracting Officer, who shall use them as necessary to determine the amount of progress payments. The Contractor shall retain copies of all such material furnished to the Contracting Officer.
1.5 EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE(MAR 1995)
(a) This special contract requirement does not apply to terminations.
See 52.249-5000, Basis for Settlement of Proposals, and FAR Part 49.
(b) Allowable cost for construction and marine plant and equipment in sound workable condition owned or controlled and furnished by a contractor or subcontractor at any tier shall be based on actual cost data for each piece of equipment or groups of similar serial and series for which the Government can determine both ownership and operating costs from the con-tractor's accounting records. When both ownership and operating costs cannot be determined for any piece of equipment or groups of similar serial or series equipment from the contractor's accounting records, costs for that equipment shall be based upon the applicable provisions of EP 1110-1-8, Construction Equipment Ownership and Operating Expense Schedule, Region VI. Working conditions shall be considered to be average for determining equipment rates using the schedule unless specified otherwise by the contracting officer. For equipment not included in the schedule, rates for comparable pieces of equipment may be used or a rate may be developed using the formula provided in the schedule. For forward pricing, the schedule in effect at the time of negotiations shall apply. For retroactive pricing, the schedule in effect at the time the work was
DOCUMENT 00 73 00.01 45 Page 4 performed shall apply.
(c) Equipment rental costs are allowable, subject to the provisions of FAR 31.105(d)(ii) and FAR 31.205-36, Rental Costs. Rates for equipment rented from an organization under common control, lease-purchase arrangements, and sale-leaseback arrangements, will be determined using the schedule, except that actual rates will be used for equipment leased from an organization under common control that has an established practice of leasing the same or similar equipment to unaffiliated lessees.
(d) When actual equipment costs are proposed and the total amount of the pricing action exceeds the SAT, the contracting officer shall request the contractor to submit either certified cost or pricing data, or partial/limited data, as appropriate. The data shall be submitted on Standard Form 1411, Contract Pricing Proposal Cover Sheet.
NOTE: A copy of EP 1110-1-8, "CONSTRUCTION EQUIPMENT OWNERSHIP AND OPERATING EXPENSE SCHEDULE," is available at the following website:
http://www.publications.usace.army.mil/USACEPublications/EngineerPamphlets.aspx.
1.6 (SCR-S-102) CONTRACTOR SUPPLY AND USE OF ELECTRONIC SOFTWARE FOR
PROCESSING DAVIS-BACON ACT CERTIFIED LABOR PAYROLLS (April 2011)
The contractor is encouraged to use a commercially-available electronic system to process and submit certified payrolls electronically to the Government. The requirements for preparing, processing and providing certified labor payrolls are established by the Davis-Bacon Act as stated in FAR 52.222-8, PAYROLLS AND BASIC RECORDS and FAR 52.222-13, COMPLIANCE
WITH DAVIS-BACON AND RELATED ACT REGULATIONS.
If the contractor elects to use an electronic Davis-Bacon payroll processing system, then the Contractor shall be responsible for obtaining and providing for all access, licenses, and other services required to provide for receipt, processing, certifying, electronically transmitting to the Government, and storing weekly payrolls and other data required for the contractor to comply with Davis-Bacon and related Act regulations.
When the contractor uses an electronic Davis-Bacon payroll system, the electronic payroll service shall be used by the contractor to prepare, process, and maintain the relevant payrolls and basic records during all work under this construction contract and the electronic payroll service shall be capable of preserving these payrolls and related basic records for the required 3 years after contract completion. If the contractor chooses to use an electronic Davis-Bacon payroll system, then the Contractor shall obtain and provide electronic system access to the Government, as required to comply with the Davis-Bacon and related Act regulations over the duration of this construction contract. The access shall include electronic review access by the Government contract administration office to the electronic payroll processing system used by the contractor.
The contractor's provision and use of an electronic payroll processing system shall meet the following basic functional criteria: commercially available; compliant with appropriate Davis Bacon Act payroll provisions in the FAR; able to accommodate the required numbers of employees and subcontractors planned to be employed under the contract; capable of producing an Excel spreadsheet-compatible electronic output of weekly payroll records (format at http://rms.usace.army.mil/ ) for export in an Excel spreadsheet to be imported into the contractor's Quality Control System (QCS) version of Resident Management System (RMS), that in turn
DOCUMENT 00 73 00.01 45 Page 5 shall export payroll data to the Government's Resident Management System (RMS); demonstrated security of data and data entry rights; ability to produce contractor-certified electronic versions of weekly payroll data;
ability to identify erroneous entries and track the data/time of all versions of the certified Davis Bacon payrolls submitted to the government over the life of the contract; capable of generating a durable record copy, that is, a CD or DVD and PDF file record of data from the system database at end of the contract closeout. This durable record copy of data from the electronic Davis-Bacon payroll processing system shall be provided to the Government during contract closeout.
All contractor-incurred costs related to the contractor's provision and use of an electronic payroll processing service shall be included in the contractor's price for the overall work under the contract. The costs for Davis-Bacon Act compliance using electronic payroll processing services shall not be a separately bid/proposed or reimbursed item under this contract.
1.7 PERFORMANCE OF WORK BY THE CONTRACTOR (APR 1984) (52.236-1)
The Contractor shall perform on the site, and with its own organization, work equivalent to at least 65 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.
PART 2 PRODUCTS (Not Used)
PART 3 EXECUTION (Not Used)
-- End of Document --
DOCUMENT 00 73 00.01 45 Page 6
DIVISION 35 - WATERWAY AND MARINE CONSTRUCTION
SECTION 35 20 23.16 45
PIPELINE DREDGING
PART 1 GENERAL
1.1 SUMMARY
1.2 MEASUREMENT AND PAYMENT
1.3 WORK COVERED BY CONTRACT PRICE
1.3.1 Existing Conditions
1.4 REFERENCES
1.5 SUBMITTALS
1.6 MATERIAL TO BE REMOVED
1.6.1 Debris Within the Dredging Limits
1.7 EASEMENTS AND PERMITS
1.8 UTILITIES ACROSS THE LIMITS OF DREDGING
1.8.1 Known Pipeline/Utility Crossings
1.9 ORDER OF WORK
1.9.1 Dredging Options
1.10 OBSTRUCTION OF CHANNEL
1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
1.13 SIGNAL LIGHTS
1.14 PLANT
1.14.1 General Requirements
1.14.2 Capacity AM#4
1.14.3 Inspectors (Government Agents) Transportation
1.15 INSPECTION
1.15.1 Equipment
1.15.2 Transportation
1.16 QUANTITY SURVEYS
1.16.1 General
1.16.2 Dredging Sections
1.16.3 Submittals
1.17 FINAL EXAMINATION AND ACCEPTANCE
1.17.1 Acceptance
1.18 SHOALS
1.19 UNANTICIPATED SHOALING
1.20 VARIATION IN ESTIMATED QUANTITIES - DREDGING
1.21 CONTINUITY OF WORK
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
2.3 GOVERNMENT FURNISHED PROPERTY
PART 3 EXECUTION
3.1 ESTIMATED QUANTITY OF MATERIAL
SECTION 35 20 23.16 45 Page 1
3.1.1 Quantity Summary
3.1.2 Required Dredging Prism
3.1.3 Allowable Overdepth
3.1.4 Side And End Slopes
3.1.5 Excessive Dredging
3.2 AREAS TO BE DREDGED
3.3 CONDUCT OF DREDGING WORK
3.3.1 Pre-Operations Safety Coordination Meeting
3.3.2 Protection of Existing Waterways
3.3.3 Adjacent Property and Structures
3.4 PLACEMENT OF EXCAVATED MATERIAL
3.4.1 General
3.4.1.1 Misplaced Material
3.4.1.2 Placement Operations Inspection
3.4.1.3 Placement Area Drainage
3.4.1.4 Maintenance of Existing Dike and Drop-outlet Structures
3.4.2 Spillway Operations
3.4.3 Placement Area
3.4.3.1 Confined Placement Area No. 33
3.4.3.2 Confined Placement Area No. 34
3.4.3.3 Confined Placement Area No. 35
3.4.3.4 Confined Placement Area No. 36
3.4.3.5 Partially Confined Placement Area No. 38
3.4.3.6 Confined Placement Area No. 39
3.4.3.7 Confined Placement Area No. 40
3.4.3.8 Partially Confined Placement Area No. 41
3.4.3.9 Partially Confined Placement Area No. 43
3.4.3.10 Pierce Marsh Beneficial Use Site (BUS)
3.4.3.10.1 General
3.4.3.10.2 Containment Cell Earthen Berms
3.4.3.10.3 Flashboard Riser Structures
3.4.3.10.4 Order of Work
3.4.3.10.5 Placement Requirements
3.4.3.10.6 Monitoring and Surveying
3.5 PRESERVATION OF PUBLIC AND PRIVATE PROPERTY
3.5.1 Damages
3.5.2 Accountability and Restoration
3.6 ALTERNATE PLACEMENT AREA(S) PROPOSED BY CONTRACTOR WITH BID AFTER
AWARD OF CONTRACT
3.6.1 Data Submittal
3.7 METHOD OF PLACEMENT
3.7.1 Pipeline Route
3.8 DISPOSAL IN PLACEMENT AREA
3.8.1 Access to Placement Areas
3.8.2 Utilities within the Placement Area
3.8.3 Unauthorized Placement of Material
3.8.4 Debris Disposal
3.9 DREDGE PIPELINES
3.9.1 Submerged Pipeline
3.9.2 Submerged Pipeline Lighting Requirements
3.9.3 Floating Pipeline
3.9.4 Pipeline Leaks
3.9.5 Magnetometer Survey Report
3.10 HOUSTON-GALVESTON VESSEL TRAFFIC SERVICE AREA
3.10.1 General
3.10.2 Report Changes
3.10.3 Vessel Traffic Service Location
3.10.4 Communications
3.10.5 Operations
SECTION 35 20 23.16 45 Page 2
3.11 WORK IN THE VICINITY OF OTHER GOVERNMENT CONTRACTORS
3.12 DREDGING AND DREDGE RELATED MARINE WORK (CESWG)
3.13 AUTOMATIC IDENTIFICATION SYSTEM
3.14 DREDGE PLANT INSTRUMENTATION
ATTACHMENTS:
Appendix 1 - QUANTITY SUMMARY TABLE
-- End of Section Table of Contents --
SECTION 35 20 23.16 45 Page 3
SECTION 35 20 23.16 45 Page 4
SECTION 35 20 23.16 45
PIPELINE DREDGING
AMENDMENT NO. 0004
PART 1 GENERAL
1.1 SUMMARY
The work in this Section consists of furnishing plant, labor, materials, and equipment and performing the operations necessary for the removal of materials to the required dimensions shown, satisfactory disposal thereof, and other operations incidental thereto.
1.2 MEASUREMENT AND PAYMENT
Measurement and payment for pipeline dredging will be paid for in accordance with provisions of the SECTION 01 22 00.10 MEASUREMENT AND
PAYMENT.
1.3 WORK COVERED BY CONTRACT PRICE
Base bids on the quantity of dredging indicated. If the total quantity of dredging varies from that specified as the basis for bidding, the Contract price will be adjusted in accordance with the CONTRACT CLAUSE 52.211.18 VARIATION IN ESTIMATED QUANTITY. The dredging conditions specified and indicated describe conditions which are known. However, the Contractor is responsible for other conditions encountered which are not unusual when compared to the conditions recognized in the dredging business as usual in dredging activities such as those required under this Contract. The Contract price for dredging will include the cost of removal and placement of the material as specified in the Paragraphs: MATERIAL TO BE REMOVED and PLACEMENT OF EXCAVATED MATERIAL. The Contract price for dredging will include the costs for maintenance of dikes and ditches necessary to confine the material within the areas shown.
1.3.1 Existing Conditions
The drawings already prepared as specified in the CONTRACT CLAUSE 252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS represent conditions existing as of the date of their preparation using average existing conditions. However, to reflect anticipated shoaling or scour occurring between the dates of preparation of the drawings and the dates of the "before-dredging" sections, the estimated dredging quantities stated in the Bid Schedule have been adjusted accordingly. The depths and elevations shown will be verified and corrected by fathometer soundings taken by the Government before dredging. The Government will normally use a frequency of 200 kHz to conduct hydrographic surveys. If the surveys indicate the presence of fluff in the channel, a frequency of 40 kHz will be used. Determination of quantities removed and the deductions made from them to determine quantities by in-place measurement to be paid for in the area specified, after having once been made will not be reopened, except on evidence of collusion, fraud, or obvious error.
SECTION 35 20 23.16 45 Page 5
1.4 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-5025 (2015) Dredging and Dredged Material Management
EM 385-1-1 (2014) Safety and Health Requirements Manual
1.5 SUBMITTALS
Government approval is required for submittals with a "G" designation;
submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Notification Prior To Commencement of Dredging Operations ; G
Indicate commencement of dredging operations, and location of dredge(s).
Temporary Removal of Aids To Navigation ; G
Pierce Marsh BUS Land Access Right of Entry
If access to Pierce Marsh is desired via land, the Contractor must obtain an ROE from the landowners. Documentation of this ROE must be submitted.
SD-02 Shop Drawings
Submerged Pipeline ; G
Indicate pipeline location and installation details as outlined in the Subparagraph: Submerged Dredge Pipeline.
Pipeline Route ; G
A detailed pipeline diagram for each Placement Area detailing the pipeline route and anchor locations are to be submitted prior to commencing work on this project.
SD-06 Test Reports
Magnetometer Survey Report ; G
Report to be be submitted as specified.
1.6 MATERIAL TO BE REMOVED
The material to be removed is shoals which have accumulated over a period
SECTION 35 20 23.16 45 Page 6 of time. However, some virgin material may be encountered in allowable overdepth, or side slope dredging. Bidders are expected to examine the worksite and the records of previous dredging, which are available in the Galveston Resident Office and after investigation decide for themselves the character of materials.
1.6.1 Debris Within the Dredging Limits
Debris including but not limited to, metal bands, pallets, pieces of broken cable, rope, stumps, and broken piles may be encountered. The Government has no knowledge of existing wrecks, wreckage, or other material of that size or character as to require the use of explosives or special or additional plant for its economical removal. Debris removed from the dredged area is to be removed from the water. Disposal is to be the responsibility of the Contractor and disposal is to be outside the limits of Government property. If the actual conditions differ from those stated or shown, an adjustment in Contract price or time of completion, or both, will be made in accordance with the CONTRACT CLAUSE 52.236-2
DIFFERING SITE CONDITIONS.
1.7 EASEMENTS AND PERMITS
Easements and Permits authorizing the laying of shore pipe, and for placement of dredge material in the Placement Area(s), are on file and available for examination in the Galveston District Office of the U.S.
Army Corps of Engineers, Jadwin Building, 2000 Fort Point Road, Galveston, Texas. The instruments authorizing the laying of shore pipelines may contain certain restrictions relative to specific route, location, and general use of the land. These instruments form a part of these specifications and the Contractor is to strictly comply with the terms thereof.
1.8 UTILITIES ACROSS THE LIMITS OF DREDGING
It is the Contractor's responsibility to investigate the location of utility crossings. The Contractor is to take precautions against damages which can result from dredging operations in the vicinity of the utility crossings. If damage occurs as a result of dredging operations, the Contractor will be required to suspend dredging until the damage is repaired and approved. Costs of these repairs and downtime of the dredge and attendant plant is to be at the Contractor's expense.
1.8.1 Known Pipeline/Utility Crossings
There are pipelines and or utilities which are within the work limits.
The following pipeline/utilities cross the area(s) to be dredged:
Approximate Station
Permit No. Description Owner
161+693 7810 OVERHEAD CABLE
CLEARANCE
+91.4 FT.
M.L.L.W.
S.W. BELL
SECTION 35 20 23.16 45 Page 7
Approximate Station
Permit No. Description Owner
162+371 OVERHEAD POWER
LINE VERT
CLEARANCE +109.3
FT. M.L.L.W.
GULF STATES UTILITIES CO.
162+629 7490 1-12" PIPE
TOP PIPE EL.
-24.3 M.L.L.W.
BOLIVAR PENNINSULA WATER
SUPPLY CORP
176+181 1501 4-2" PIPES
TOP PIPE EL.
-24.3 M.L.L.W.
JOHN W. MECOM
177+194 859 5-3" PIPES
TOP PIPE EL.
-24.3 M.L.L.W.
PLACID OIL CO.
178+169 6186; 5990;
6187; AND
1-6" PIPE
1-4" PIPE
1-10" PIPE
TOP PIPE EL.
-29.3 M.L.L.W.
AMOCO PIPELINE CO.
UNION TEXAS PETROLEUM CO.
235+461 16516 EARTHEN PLUG SUN OIL CO.
235+811 2835 6" PIPE UNION TEXAS PETROLEUM
302+316 14091 2-10" PIPES
TOP PIPE EL.
-27.3 M.L.L.W.
CHAMBERS CO. GAS GATHERING
SYSTEM
302+417 6950 16" PIPE
TOP PIPE EL.
-27.3 M.L.L.W.
BLACK MARLIN PIPELINE CO.
311+035 9923 2-CONC PIPES
TOP PIPE EL.
-25.0 M.L.L.W.
SEAGULL PIPELINE CORP
315+225 9336 SLIP & DOCK HOUSTON OIL & MINERAL CO.
316+000 to 317+000
GAS LINE FENCED
OFF IN PA 43
HOUSTON OIL & MINERAL CO.
FACILITY
362+500 GALVESTON
CAUSEWAY VEHICLE
AND RAILROAD
BRIDGE
EVERY EFFORT HAS BEEN MADE TO GI VE ALL PERTI NENT DETAI LS ON THE LOCATI ON
OF PI PELI NES/ UTI LI TI ES. THE DATA FURNI SHED ON THE PLANS ARE BELI EVED TO
BE SUBSTANTI ALLY CORRECT. HOWEVER, THE EXACT LOCATI ONS MAY VARY FROM THAT
SHOWN: THEREFORE, THE CONTRACTOR I S TO COOPERATE WI TH THE RESPECTI VE
OWNERS TO ESTABLI SH THE ACTUAL POSI TI ON OF THE PI PELI NES/ UTI LI TI ES. .
THE FOLLOWING IS FURNISHED FOR INFORMATION ON VERIFYING PIPELINE
SECTION 35 20 23.16 45 Page 8
OWNERSHIPS:
Texas One Call at 811, 1-800-545-6005 or online at https://www.texas811.org/
1.9 ORDER OF WORK
The Contractor shall commence and complete Schedule No. 1 dredging in Section Nos. 19 and 20 as the first order of work. The remainder of Schedule No. 1, Section Nos. 1-7 and 10-11, and Option Nos. 1-4 may be completed in the order the Contractor desires. If Option Nos. 3 and/or 4 are awarded, Section Nos. 22 and 23 shall be completed between September 1st and February 28th of the following year due to nesting colonial water birds. The Government reserves the right to change the order of work at any time.
1.9.1 Dredging Options
The Government will award Dredging Options as specified.
1.10 OBSTRUCTION OF CHANNEL
The Government will not undertake to keep the Channel free from vessels or other obstructions, except to the extent of applicable regulations, if any, as may be prescribed by the Secretary of the Army, in accordance with the provisions of Section 7 of the River and Harbor Act approved 8 August 1917. The Contractor will be required to conduct the work using a method that will obstruct navigation as little as possible, and if the Contractor's plant does obstruct the Channel and makes passage of vessels difficult or endangers them, the plant is to be promptly moved on the approach of a vessel as far as may be necessary to afford a practicable passage.Upon completion of the work, promptly remove plant, including ranges, buoys, piles, and other marks placed under this Contract.
1.11 TEMPORARY REMOVAL OF AIDS TO NAVIGATION
The temporary removal or changes in locations of channel markers may be required to facilitate dredging operations. Notify the Contracting Officer at least 21days prior to the date that the removal or change in location of channel markers will be required so the U.S. Coast Guard can perform the work and so navigation interests may be informed sufficiently in advance of the proposed removal or change in location.
The Contractor is not to remove, change the location of, obstruct, willfully damage, make fast to, or interfere with aids to navigation.
Indicate temporary removal or changes in locations of channel markers required to facilitate dredging operations.
1.12 NOTIFICATION PRIOR TO COMMENCEMENT OF DREDGING OPERATIONS
Notify the Resident Engineer, Galveston Resident Office, in writing, at least 10days prior to commencement of dredging operations, the location or locations at which a dredge or dredges will be placed on the work. This information is required in addition to the progress charts and schedule provided for in the CONTRACT CLAUSE 52.236-15 SCHEDULE FOR CONSTRUCTION
CONTRACTS.
SECTION 35 20 23.16 45 Page 9
1.13 SIGNAL LIGHTS
Display signal lights and conduct operations in accordance with the General Regulations of the Department of the Army and of the U.S. Coast Guard governing the:
i) lights and day signals to be displayed by towing vessels with tows on which no signals can be displayed, vessels working on wrecks, dredges, and vessels engaged in laying cables or pipe or in submarine or bank protection operations;
ii) lights to be displayed on dredge pipe lines;
iii) day signals to be displayed by vessels of more than 65 feet in length moored or anchored in a fairway or channel;
iv) and the passing by other vessels of floating plant working in navigable channels as set forth in United States Coast Guard publication entitled Navigation Rules and Regulations Handbook. Web site location:
http://www.navcen.uscg.gov/?pageName=navRuleChanges
1.14 PLANT
1.14.1 General Requirements
Keep the necessary dredge equipment and attendant plant on the job to meet the requirements of the work. The dredge equipment and attendant plant is to be in satisfactory operating condition and capable of safely and efficiently performing the work as set forth in specifications and be subject to inspection by the Contracting Officer's representative at all times.
1.14.2 Capacity AM#4
No reduction in the capacity of the dredge equipment and attendant plant employed to execute the work is to be made except by written direction of the Contracting Officer. The measure of the "Capacity of the Dredge and Attendant Plant" is to be its actual performance on the work to which these specifications apply The ef f ect i ve pr oduct i on r at e of t he dr edge pl ant shal l not be l ess t han an aver age of 12, 000 cubi c yar ds per day i n t he Bol i var Fl ar e and Channel t o Por t Bol i var ( Sect i on Nos. 19- 21) and 400 l i near f eet per day i n t he r emai ni ng dr edgi ng sect i ons. No r educt i on i n t he capaci t y of t he dr edge equi pment and at t endant pl ant empl oyed t o execut e t he wor k i s t o be made except by wr i t t en di r ect i on of t he Cont r act i ng Of f i cer . The measur e of t he " Capaci t y of t he Dr edge and At t endant Pl ant " i s t o be i t s act ual per f or mance on t he wor k i n whi ch t hese speci f i cat i ons appl y .
1.14.3 Inspectors (Government Agents) Transportation
Furnish throughout the Contract period, for the exclusive use of the Government: a motorboat, minimum 18 feet in length, with enclosed cabin, a minimum of a 50 horsepower motor and equipped with safety equipment as required by EM 385-1-1 . Furnish fuel, oil, and maintenance for the motorboat throughout the Contract period. Assume full responsibility for the storage and security of the motorboat when not in use by the Government employees. There will be no separate payment for these items
SECTION 35 20 23.16 45 Page 10 and the cost will be distributed throughout the existing bid items.
Equipment which fails to perform because of insufficient power or other mechanical deficiencies are to be replaced and inexperienced operators unable to operate the equipment is to be replaced within 12 hours after the Contractor is directed to do. No smoking is to be allowed inside the cabin and operator's space while occupied by Government personnel. No Smoking signs are to be posted.
1.15 INSPECTION
The Government will direct the maintenance of the gages, ranges, location marks, and limit marks in proper order and position; but the presence of the inspector shall not relieve the Contractor of responsibility for the proper execution of the work in accordance with the specifications. The Contractor shall be required to furnish the following items.
1.15.1 Equipment
At the request of the Government, the Contractor shall furnish the use of boats, boatmen, laborers, and material forming a part of the ordinary and usual equipment and crew of the dredging plant as may be reasonably necessary in inspecting and supervising the work. However, the Contractor will not be required to furnish facilities for the surveys, specified in the Paragraph: FINAL EXAMINATION AND ACCEPTANCE.
1.15.2 Transportation
At the request of the Government, the Contractor shall furnish suitable transportation from all points on shore designated by the Contracting Officer to and from the various pieces of plant, and to and from the Placement Areas. If the Contractor refuses, neglects, or delays compliance with these requirements, the specific facilities may be furnished and maintained by the Contracting Officer, and the cost thereof will be deducted from the amounts due or to become due the Contractor.
1.16 QUANTITY SURVEYS
1.16.1 General
Quantity surveys are to be conducted, and the data derived from these surveys are to be used in computing the quantities of work performed and the actual dredging completed.
1.16.2 Dredging Sections
The Government will conduct the original and final surveys and surveys make the computations based on them. The Contractor will conduct the surveys for the periods when progress payments are requested and will make the computations based on these surveys. Surveys conducted by the Contractor must be conducted under the direction of the Contracting Officer, unless the Contracting Officer waives this requirement in a specific instance.
1.16.3 Submittals
Promptly upon completing a survey, the Contractor will submit the originals of field notes and other records relating to the survey or to the layout of the work to the Contracting Officer. The Contracting Officer will use them as necessary to determine the amount of progress
SECTION 35 20 23.16 45 Page 11 payments. The Contractor must retain copies of submitted material.
1.17 FINAL EXAMINATION AND ACCEPTANCE
As soon as practicable after the completion of the entire work or any section thereof, if the work is divided into sections and in the opinion of the Contracting Officer will not be subject to damage by further operations under this Contract, this work will be thoroughly examined at the expense of the Government by sounding or by sweeping, or both, as directed. If shoals, lumps, or other lack of Contract depth are disclosed by this examination, the Contractor will be required to remove same by dragging the bottom or by dredging at the Contract rate for dredging but, if the bottom is soft and the shoal areas are small and form no material obstruction to navigation, the removal of the shoal may be waived at the discretion of the Contracting Officer. The Contractor or its authorized representative will be notified when soundings or sweepings are to be made and will be permitted to accompany the survey party. When the area is found to be in a satisfactory condition it will be accepted finally. If more than two sounding or sweeping operations by the Government over an area are necessary, by reason of work for the removal of shoals disclosed at a prior sounding or sweeping, the cost of the third and any subsequent sounding or sweeping operations will be charged against the Contractor at the rate of $10,628.00 per day for each day in which the Government plant is engaged in sounding or sweeping or is enroute to or from the site or held at or near the site for these operations.
1.17.1 Acceptance
Final acceptance of the whole or a part of the work and the deductions or corrections of deductions made thereon will not be reopened after having once been made, except on evidence of collusion, fraud, or obvious error, and the acceptance of a completed section will not change the time of payment of the retained percentages of the whole or any part of the work.
1.18 SHOALS
If, before this Contract is completed, shoals occur in a section previously accepted, redredging at the Contract price, within the limit of available funds, may be done if agreeable to both the Contractor and the Contracting Officer.
1.19 UNANTICIPATED SHOALING
During the course of this Contract, unanticipated dredging requirements may develop that require the use of the Contractor and Contractor's plant. The dredging required would be similar in scope to that required under the current Contract. Dredging would consist of limited portions of a section of channel, intended to remove critical shoals hindering commercial navigation. If such a need arises, the Contracting Officer may issue a Request for Proposal for the work under the CONTRACT CLAUSE 52.243-4 CHANGES, and the work performed upon the execution of a bilateral contract modification.
1.20 VARIATION IN ESTIMATED QUANTITIES - DREDGING
Where the quantity of a pay item in this Contract is an estimated quantity and where the actual quantity of material within the required dredging prism varies, an equitable adjustment will be processed in accordance with CONTRACT CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY (April 1984).
SECTION 35 20 23.16 45 Page 12
The equitable adjustment applies only to the quantity within the required dredging prism, which does not include the allowable overdepth.
If the total quantity of material to be paid for and actually removed under this Contract exceeds the limit established by CONTRACT CLAUSE 52.211-18, VARIATION IN ESTIMATED QUANTITY (April 1984), an additional time will be allowed at the rate of 1 calendar day for each 10,000 cubic yards in excess of the established limit. The Contractor is not to exceed the estimated quantities in the Contract Line Items without prior authorization and only with a signed modification issued by the Contracting Officer.
1.21 CONTINUITY OF WORK
No payment will be made for work done in an area designated by the Contracting Officer until the full depth required under this Contract is secured in the whole of this area, unless prevented by ledge rock, nor will payment be made for excavation in an area not adjacent to and in prolongation of areas where full depth has been secured except by decision of the Contracting Officer. If a non-adjacent area is excavated to full depth during the operations carried on under this Contract, payment for the work therein may be deferred until the required depth has been reached in the area intervening. The Contractor may be required to suspend dredging when the gages or ranges cannot be seen or properly followed.
PART 2 PRODUCTS
2.1 BRIDGE-TO-BRIDGE RADIOTELEPHONE EQUIPMENT
Dredge and self-propelled attendant floating plant is to be radiotelephone equipped to comply with the provisions of the Vessel Bridge-to-Bridge Radiotelephone Act (Public Law 92-63). This will require, as a minimum, the radiotelephone equipment capable of transmitting and receiving on
156.65 MHz (Channel 13). Multi-channel equipment will also require 156.8 MHz (Channel 16). Dredge tugs and tenders will be considered towing vessels within the meaning of the Act.
2.2 LOOKOUTS AND RADIO COMMUNICATIONS
When working in the Gulf Intracoastal Waterway, have a lookout person posted in the dredge control room at all times to visually monitor the movement of vessels around the dredge plant; to perform radio communications with company work boats; and to deliver passing arrangements with other commercial, fishing and recreational vessels. The lookout is to be competent in U.S. Coast Guard and Federal Communications Commission radio communications procedures and requirements and is to be trained in the Vessel Bridge to Bridge Radiotelephone Act. The lookout is to maintain up to the minute information on the status of each company work boat and approaching vessels, and will communicate this information as required to prevent collisions. Each company work boat is to check in with the lookout when arriving at the dredge and receive radio clearance from the lookout before departing the dredge.
Failure to comply with this requirement will be considered a violation of the safety protocol established herein. Pursuant to the direction of the Contracting Officer, the Contractor may be required to cease operations until this provision is complied with. A suspension, delay or interruption of work arising from non-compliance of this provision will not constitute a breach of this Contract and will not entitle the
SECTION 35 20 23.16 45 Page 13
Contractor to a price adjustment in accordance with the CONTRACT CLAUSE 52.242-14 SUSPENSION OF WORK or any other provision under this Contract.
2.3 GOVERNMENT FURNISHED PROPERTY
If Option Nos. 3 and/or 4 are awarded, the Contractor must coordinate with the Galveston Bay Foundation transportation of six (6) pre-fabricated flashboard riser structures for installation onsite.
PART 3 EXECUTION
3.1 ESTIMATED QUANTITY OF MATERIAL
Within the limits of available funds, the Contractor will be required to excavate the entire quantity of material necessary to complete the work specified whether the quantities involved are greater or less than those estimated. The work is to be done in accordance with this Contract and at the Contract price or prices, subject to the provisions of the Paragraph entitled 52.211.18 VARIATIONS IN ESTIMATED QUANTITIES - DREDGING.
3.1.1 Quantity Summary
The quantities listed in Appendix 1 - QUANTITY SUMMARY TABLE include the volumes present at the time of the surveys indicated on the Contract drawings, plus anticipated shoaling before dredging begins. For the purpose of acceptance, the pipeline dredging work in the Bid Item(s) of the Bid Schedule are divided into Sections.
3.1.2 Required Dredging Prism
The total estimated amount of material to be removed from within the specified limits, including side and end slopes and including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys but excluding overdepths, in cubic yards is listed in Appendix 1 - QUANTITY
SUMMARY TABLE.
3.1.3 Allowable Overdepth
To cover unavoidable inaccuracies of the dredging process, material actually removed from the designated areas to be dredged, will be measured and paid for at full Contract price. The maximum amount of allowable overdepth dredging is estimated, including anticipated shoaling occurring prior to the dates of the "before-dredging" surveys in cubic yards is listed in Appendix 1 - QUANTITY SUMMARY TABLE.
3.1.4 Side And End Slopes
Dredging of the side and end slopes are to follow, as closely as practicable, the lines indicated or specified. Material actually removed from within the limits as approved, to provide for final side and end slopes as specified, but not in excess of the amounts originally above the limiting side and end slopes will be estimated and paid for, whether dredged in original position or by dredging the space below the pay slope plane at the bottom of the slope for upslope material capable of falling into the cut.