AB STRACT OF OFFERS /CONT'D) Paae2 of2

Solicitation No. : W912HY19 B0029 Date Issued: 26 Jul 18 Date Ooened: 26 Aul! 19

Project Title: Unrestricted Procurement for Houston Ship Channe� Texas, Peggy Lake Placement Area Dewatering and Dike Raise in Harris County, Texas.

Offeror: #1 - Affolter Contracting Comoanv. Inc.

ITEM SCHEDULE NO. 1 UNIT

NO. DESCRIPTION OUAN1TIY PRICE TOTAL

0001 Mobilization and Demobilization 1 JB SUM $915 000.00

0002 Clesring and Stripping

1 JB SUM $200 000.00

0003 Collector Sump Excavation 1 JB SUM $70 000.00

0004 Perimeter Trench

11 560 LF $30.00 $346 800.00

0005 Interior Lateral Trenches 11 770 LF $30.00 $353 100.00

0006 Final Construction Survey 1 JB SUM $40 000.00

0007 Semi-Compacted B erm Construction using Onsite Soils 100 200 CY $8.00 $801 600.00

Semi-Compacted Dike Construction using Imported Clay

0008 Soils 174 100 CY $29.00 $5 048 900.00

0009 Uncornpacted Dike Construciton Using Onsite Soils

25 000 CY $8.00 $200 000.00

0010 Demolition of Existing Drop-Outlet Structure 1 JB SUM $100 000.00

0011 New Drop-Outlet Structure 1 JB SUM $850 000.00

Turfing

1 JB SUM $164 000.00

TOTAL SCHEDULE NO. 1

$9 089 400.00

Business Size: SB

, PO Box 1436, , La Marque, TX 77568