Question and Answer- Full Start Up Commissioning.pdf

PDF 209 KB Posted

Attached to
Full Start-Up Commissioning of Data Center Cooling Infrastructure and UPS Battery Replacement
Solicitation number
W912HQ26S0066
Issued by

About this file

This document is a Performance Work Statement (PWS) section outlining requirements for an Eaton UPS battery replacement project. The contractor must perform a complete battery swap for two (2) Eaton PW9390-160 UPS systems, involving the decommissioning and safe removal of eighty (80) existing batteries, EPA-compliant disposal and transportation of spent batteries with required Certificate of Recycling/Disposal documentation, supply and installation of eighty (80) new C&D Technologies UPS12-400MR batteries, and testing and calibration activities including connection cleaning and torquing to manufacturer specifications.

Testing requirements include IEEE 1188 compliant impedance/conductance testing and internal battery testing to verify string integrity, with UPS firmware and parameter updates as necessary to recognize new battery string characteristics. An accompanying Q&A clarification specifies that external load bank discharge testing will be omitted from the SOW, with internal battery testing deemed sufficient to satisfy testing requirements.

View the file

Other files

File Type Posted
CSS_Full Start-Up Commissioning of Data Center Cooling.pdf PDF
SOW.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

3.1 Eaton UPS Battery Replacement

The Contractor shall perform a complete battery swap for one (2) Eaton PW9390-160 UPS system:

• Decommissioning & Removal: Safely disconnect and remove eighty (80) existing batteries.

• EPA-Compliant Disposal: Transport and dispose of the eighty (80) spent batteries in strict accordance with Environmental Protection Agency (EPA), state, and local hazardous waste regulations. The Contractor must provide a Certificate of Recycling/Disposal.

• Installation: Supply and install eighty (80) new C&D Technologies UPS12-400MR batteries.

• Testing & Calibration: Clean and torque all connections to manufacturer specifications. Perform IEEE 1188 compliant impedance/conductance testing and discharge testing to verify string integrity.

Update UPS firmware/parameters if necessary to recognize the new battery string characteristics.

Will the discharge testing part of this section be required utilizing an external load bank?

A: Discharge testing will be omitted from the SOW, the internal battery test will suƯice.