About this file

This Broad Agency Announcement and related federal contract notice seek proposals for the demonstration and validation of non-fluorine based firefighting foams through the Environmental Security Technology Certification Program (ESTCP). Proposals are due no later than September 12, 2019, with multiple awards totaling approximately $5 million expected depending on available funds. Both small and large businesses are encouraged to respond. Proposals will be evaluated based on technical merit, cost/benefit of the technology, transition potential, and cost of the proposal. Awards will take the form of contracts, with proposals under $250,000 to be firm fixed price. Subcontracting plans are required for proposals over $700,000 from other than small businesses. The North American Industry Classification System codes applicable are 541715 and 541330 with a small business size standard of 1,000 employees and $15 million.

Supplemental Instructions

View the file

Other files for this federal contract opportunity

Other files attached to Environmental Security Technology Certification Program (ESTCP) - Environmental Technology Demonstrations, newest first.
File Type Posted
Subcontracting_Plans_Checklist_for_DoD_Mar_2018.pdf PDF
Subcontracting_Plan_Draft_Template_for_Offerors_8_Feb_19.docx DOCX document

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROGRAM ANNOUNCEMENT FOR ENVIRONMENTAL

SECURITY TECHNOLOGY CERTIFICATION PROGRAM (ESTCP)

FY 2020 SUPPLEMENTAL SOLICITATION

BAA Pre-Proposal Submittal Instructions

Reference: Broad Agency Announcement (BAA) August 1, 2019, U.S. Army Corps of Engineers, Humphreys Engineer Center Support Activity

INTRODUCTION

The Environmental Security Technology Certification Program (ESTCP) is the Department of Defense’s (DoD) demonstration and validation (Dem/Val) program for environmental and installation energy technologies. Throughout this document, “technology” refers broadly to integrated systems based on any combination of hardware (equipment) and software (processing), materials engineering processes, and resource management devices, methods, tools, or models based on scientific principles. Technologies appropriate for demonstration and validation will be sufficiently mature that all required laboratory or other proof-of-concept work has been completed. Commercial technologies already in use are not considered appropriate for demonstration and validation.

ESTCP is seeking proposals for demonstration and validation of non-fluorine based firefighting foams as candidates for funding beginning in Fiscal Year (FY) 2020. Descriptions of the specific topic area and complete solicitation details are on the ESTCP website.

This Broad Agency Announcement (BAA) is for Private Sector organizations. DoD organizations (Services and Defense Agencies) wishing to submit proposals to ESTCP should refer to the FY20 DoD Call for Proposals. Federal agencies outside DoD should refer to the FY20 Call for Proposals for Federal Organizations Outside DoD. Instructions for the DoD and Other Federal Calls for Proposals may be found on the ESTCP website.

Background The purpose of ESTCP is to demonstrate and validate promising innovative technologies that target DoD’s most urgent environmental and installation energy needs and are projected to pay back the investment through cost savings, improved efficiencies, or improved outcomes. ESTCP responds to high priority DoD environmental and installation energy technology requirements and the need to improve defense readiness by reducing the drain on the Department’s operation and maintenance dollars caused by real world commitments such as environmental restoration, waste and facility management, range sustainability, energy security, and water conservation. The goal is to enable promising technologies to receive regulatory and end-user acceptance and be fielded and commercialized more rapidly. To achieve this goal, ESTCP projects create a partnership between technology developers, responsible DoD organizations, and the regulatory community. This program announcement is seeking pre-proposals from the technology development community.

ESTCP demonstrations are conducted under operational conditions at DoD facilities or locations for which DoD holds environmental responsibility. Candidate technologies are expected to have successfully completed laboratory testing and, when applicable, initial small-scale field testing. The demonstrations are intended to generate supporting cost and performance data for acceptance or validation of the technology. ESTCP demonstration projects also are required to support the future implementation of the tested technology through the development of appropriate guidance, design, and/or protocol documents. ESTCP will not support full-scale demonstrations that are primarily intended to solve an individual installation’s problem. Full-scale cleanup is not performed under ESTCP. ESTCP gives priority to those projects that address multi-Service or DoD environmental requirements.

ESTCP projects must:

1. Execute the technology demonstration to validate the technology’s performance and expected operational costs:

· Each project develops one or more Demonstration Plans, as appropriate to the project, to govern the technical execution and management of the demonstration. Guidance describing the requirements of the ESTCP Demonstration Plan can be found on the ESTCP website. The Demonstration Plan is reviewed and must be approved by the ESTCP Office prior to beginning any fieldwork.

· Each project is expected to generate sufficient pertinent and high quality data to scientifically validate all claims made for the technology.

· Cost and performance data will be collected during the demonstration(s) to allow realistic estimates to be derived for full-scale implementation of the technology at the demonstration site and other DoD sites.

2. Transfer the technology:

· Identify and work with the intended DoD user community to achieve their acceptance and feedback on the usefulness of the technology.

· Publish appropriate user guidance, design, and/or protocol documents to assist the future implementation of the technology.

· Publish a Final Report based on the ESTCP Final Report guidance.

· Publish the results of the demonstration in the scientific peer reviewed literature and present results at technical conferences, as appropriate.

· Identify pathways to implementation of the technology.

3. Provide data and support to achieve regulatory and end-user acceptance:

· Technologies needing regulatory approval for use will be required to engage the regulatory community at the outset of project execution. Feedback from regulators must be solicited and incorporated into the project’s Demonstration Plan.

· No single approach for working with the regulatory community is prescribed by the program. Interaction with individual state regulatory organizations, interstate groups, and the U.S. Environmental Protection Agency (EPA) is encouraged. The approach taken should be appropriate for the technology being demonstrated and the regulatory issues associated with implementing the technology.

Proposers selected for funding will be teamed with a DoD liaison who will be responsible for assisting in selecting the demonstration site, validating the technology’s cost and performance, interfacing with the regulatory and user community, and supporting the transfer of the technology across DoD.

General information for PRIVATE SECTOR Proposers The solicitation will be managed by the ESTCP Office along with the U.S. Army Corps of Engineers, Humphreys Engineer Center Support Activity (HECSA) in Alexandria, Virginia. For contracting or small business information regarding this BAA solicitation, contact Doug Pohlman at 703-428-6420 or by email at Douglas.E.Pohlman@usace.army.mil or the HECSA Small Business Representative at 703-428-7385 or HECSASmallBusinessProgram@usace.army.mil, respectively. General procedural questions may be referred to the ESTCP Office at 571-372-6565. For technical questions regarding this announcement, contact the individual listed within the topic area description.

Awardees under this BAA will be selected through a multi-stage review process. The technical review includes a proposal and an oral presentation. Proposals that pass an internal relevancy check will be presented in person to the ESTCP Technical Committee. The costs associated with this initial, pre-award presentation shall not be included in the proposal cost estimate. This cost is borne by the proposer.

Based on evaluation of the written proposal and oral presentation, each proposer will be notified as to whether the Government wishes to enter into negotiations for the award of a contract. Proposers are advised that only the Contracting Officer is legally authorized to commit the Government. ESTCP reserves the right to recommend for award any, all, or none of the proposals received. ESTCP also reserves the right to recommend a portion of the work proposed in any single proposal for award. There is no commitment by ESTCP or the HECSA Contracting Officer to make any contract awards, nor shall the Government be responsible for any money expended by the proposer before contract award is made. Due to the volume of proposals anticipated to be received, the Government will not provide debriefs on those that are selected for funding.

Cost realism and reasonableness may also be considered during the selection of acceptable proposals in accordance with FAR 35.016(e).

Evaluation Schedule Proposals will be evaluated based on the following schedule.

DATE

ACTIVITY

August 1, 2019
BAA Released

September 12, 2019; 2:00 p.m. Eastern Time

Proposals Due to ESTCP

October 2019

Briefings Before ESTCP Technical Committee

November 2019

Project Selection

June 2020

Anticipated Awards*

* Proposal packages will be sent to contracting in the first quarter of FY2020. Contract award is expected in the third quarter of 2020, but not guaranteed.

PROPOSAL INSTRUCTIONS

Proposals shall contain four sections, Abstract, Technical Section, Cost Section, and Appendices, submitted as one document. Each section is described in detail below. Proposals shall be prepared in accordance with the following:

· Type size should not be less than 11 point, any font.

· All margins (top, bottom, left, and right) should not be less than 1 inch.

· Pages should be numbered.

· Proposals should use the section headers provided in section 2.2. These section headers correspond to evaluation criteria that will be used to review, evaluate, and select proposals.

· Table of contents, introduction, executive summary, or any other elements not prescribed by this guidance are neither required nor desired.

2.1 ABSTRACT

In one page or less, provide a brief summary of the proposed effort following the structure outlined below. The abstract is not included in the page limitation. If your proposal is selected for funding, the abstract will serve as the basis for a project overview to be posted on the ESTCP website. Therefore, please ensure it is well written. Items 1-4 must be located at the top of the first page:

1. Proposal Number: The proposal number is generated by the SERDP and ESTCP Management System (SEMS) when the proposal details are entered. The proposal number for the full proposal is the same as the pre-proposal.

2. Proposal Title

3. Lead Principal Investigator

4. Lead Organization

5. Objective: Provide a succinct statement of the project’s overall objective in the context of the environmental problem that the proposed technology will address. Indicate the relevance and importance of this problem to the DoD. Include specific technical objectives if relevant.

6. Technology Description: Describe the proposed technology, in particular the innovative aspects of the technology that will be demonstrated in the project. Summarize what the project will attempt to demonstrate and what will constitute success.

7. Expected Benefits: Briefly describe the anticipated cost and performance benefits of the use of the technology to the DoD as compared to current practice or state-of-the-art technology, if one exists.

2.2 TECHNICAL SECTION

The technical section must contain all of the content elements outlined here and must not exceed 10 pages. It is expected that each section will be expanded to provide sufficient information that responds directly to the evaluation criteria. The emphasis should be on the technical approach. Throughout this document, “technology” refers broadly to integrated systems based on any combination of hardware (equipment) and software (processing), materials engineering processes, and resource management devices, methods, tools, or models based on scientific principles.

1. Short Descriptive Title

2. ESTCP Topic Area: Indicate the ESTCP topic area the proposal addresses.

3. Lead Organization: Project lead, organization, address, telephone number, and e-mail address.

4. Problem Statement: Clearly state the environmental problem the technology demonstration is addressing and its relevance and importance to DoD. Identify the current approach (if one exists) to this problem and its shortcomings.

5. Technology Demonstration: The technology description should include the following information:

a. Technical Objective: Discuss the objective(s) of the proposed effort.

b. Technology Description: Describe the technology in sufficient detail to provide an accurate and factual understanding of its theory, functionality, and operation. If appropriate, provide an overall schematic of the technology. Discuss how the technology is innovative. Identify the specific performance issues that require validation.

c. Technology Maturity: Provide evidence that the technology is mature enough for demonstration. Include references and past funding history. Discuss any development or design work that is required prior to demonstration.

d. Technical Approach: Provide a detailed overview of how the project will be conducted to address the technical objectives. For clarity, proposers should present this section in terms of specific tasks. Within this construct, the proposer should ensure that the following issues are addressed:

· Include a brief description of a proposed demonstration site(s), if known. If the site has not yet been selected, discuss required site characteristics for an optimal demonstration.

· Provide the performance objectives for the technology. These are the primary criteria established by the investigator for evaluating the performance and costs of the technology. Performance objectives may be related to qualitative or quantitative parameters. Discuss data required to evaluate the performance objectives and the criteria to determine whether objectives are successfully met. Refer to the ESTCP demonstration plan guidance on the ESTCP website for more detailed information and examples.

· Provide a broad overview of the experimental design. Discuss the scope of the proposed demonstration and relate the planned data collection to the performance objectives. Include a discussion of controls, various operational phases, and/or other means to evaluate the technology performance. Include any assumptions that have been made for costing purposes.

· Include a description of the data analyses that will be conducted to determine whether the success criteria for the performance objectives have been met. Include a description of statistical analyses to be conducted.

e. Technical Risks: Identify potential issues of concern and technical risks in taking the technology from the research phase to the proposed scale of the demonstration. Identify any assumptions that have been made that, if not realized, could impact the successful implementation of the project. Discuss how risks will be managed. If the demonstration is not at full scale, discuss any scale-up issues that will remain at the conclusion of a successful demonstration.

f. Related Efforts: Provide information on any relationship to other similar projects. Identify funding sources for these efforts.

6. Expected DoD Benefit: Describe the expected benefit in terms of environmental impact and/or reduced cost. Assess the environmental benefit per site or implementation and the expected aggregate benefit for DoD. Provide realistic projections of the number of DoD sites or facilities where the technology can be deployed. Discuss how the information obtained from the demonstration will enable adoption of the technology throughout DoD. Estimate the expected return on investment and the time for payback. Discuss the life cycle cost advantages over current approaches.

7. Schedule of Milestones: Provide a project schedule with expected milestones and deliverables for the duration of the project in the form of a Gantt chart. Ensure that all required ESTCP deliverables are included in the Gantt chart. Reporting requirements are found on the ESTCP website.

· Explicitly identify any development, design, baseline characterization, or treatability work that is required prior to demonstration.

· Estimate the time required for the demonstration. Include the planned initiation and completion dates for critical events, including but not limited to equipment installation, monitoring, fieldwork, data analysis, and other key activities as appropriate.

· Include expected submission dates to the ESTCP Office for the first draft and completed final document for Demonstration Plans and Final Reports. Separate first draft and final submission dates by a two-month period to allow time for ESTCP review.

8. Technology Transition: All proposals are expected to include a description of a specific technology transition tool that will aid in the transition of the technology to the end user. Reliance on presentations at conferences, scientific publications, or final project deliverables (i.e., Final Report) is not acceptable. A strong transition tool should focus on highlighting key lessons learned from the technology demonstration as well as an overview of the technology. Consider innovative methods to convey such information including user guides and web-based or electronic tools.

Specify how technology transfer methods will differ to reach appropriate audiences (e.g., regulators, consultants, etc.). Describe any proposed guidance documents that will assist in future implementation (e.g., guidance, design, and/or protocol documents). Explicitly identify potential first DoD users and follow-on implementation. If there are known institutional or regulatory barriers that affect the transition, they should be described in this section along with recommendations for addressing these barriers.

9. Disposition of Equipment: Identify any major equipment to be purchased for the demonstration. Indicate plans for disposition of major equipment to be purchased by the government.

10. Performers: List the name and organization of the lead person(s) for each organization involved in the proposed demonstration and summarize their expected contributions.

11. Acronym List: Include a list defining all acronyms used in the proposal. Not included in the page limitation.

0. COST SECTION

The cost section of the proposal is an estimate of the total project cost. The cost spreadsheet template is found on the ESTCP website. Cost sections in formats other than this template will not be accepted. The cost spreadsheet for the lead organization should reflect the entire project costs. Separate cost spreadsheets are required for each co-performer or sub-contractor whose costs exceed $50,000. Cost information must be rounded to the nearest dollar. If selected for funding, proposers will be required to provide a certificate of current cost or pricing data prior to award in accordance with Federal Acquisition Regulation (FAR) 15.403-4(a)(1) if the total contract value is expected to exceed $2,000,000.00 to the cognizant contracting office.

All ESTCP projects are funded incrementally, with funds provided in the year in which they are expected to be expended. The cost section should be structured to indicate annual, incremental funding required. For planning purposes, proposers should assume a project initiation date of May 1, 2020. The first year’s planned funding should run through January 31, 2021, and each subsequent year should span February 1-January 31, until anticipated project completion.

1. Labor Costs: Show the projected labor rates in units of hourly rate or annual salary to be charged by the PI(s), associates, and assistants. Indicate in the footnote to the cost table the units you are using. In the units column, indicate the number of hours or the fraction of annual salary to be charged. The total column is the amount per year to be paid to each performer on the project. Labor costs should be unburdened.

2. Indirect Charge #1: Indicate burden or fringe rate applied to salaries and the total cost per year. Provide an explanation in the table footnote of what is included in this indirect charge.

3. Indirect Charge #2: Indicate other relevant indirect charges such as G&A. Provide an explanation in the table footnote of what is included in this indirect charge and to which cost elements it will be applied.

4. Contractor Acquired Property: Provide an itemized list of contractor acquired property (CAP), if any, to be acquired in support of the project, showing the cost for each item. Use the second tab in the cost spreadsheet located on the ESTCP website as a template. CAP is any article of non-expendable, tangible property having a useful life of more than two years and an acquisition cost of $5,000 or more per unit.

5. Materials, Supplies and Consumables: Provide a general description and total estimated cost of expendable equipment and supplies. Include a separate itemized list using the third tab of the cost spreadsheet template located on the ESTCP website.

6. Subcontracts and Government Partners: For any co-performer or subcontract totaling $50,000 or more, provide a breakout of the tasks and associated costs in a separate cost estimate using the cost spreadsheet template on the ESTCP website. Government partners will be provided a separate allocation of funds directly based upon this separate estimate. Funds provided directly from ESTCP to government partners are not to be subject to contractor indirect charges or fees. The lead organization should plan to manage all subcontracts to non-government partners.

7. Travel Costs: Estimate total travel costs. List the number of trips, the destinations, purposes, and costs per trip using reasonable and allowable rates in accordance with FAR 31.205-46 for all proposed travel. Use the fourth tab in the cost spreadsheet located on the ESTCP website as a template for the travel budget breakdown. For trips where the specific destination has not yet been determined, budget for a representative location. For planning purposes, ESTCP conducts an annual in-progress review of management and technical status of each project in the Arlington, VA area. New start projects funded to begin in 2020 will be reviewed first in February 2021, with additional annual reviews in either April/May or October/November thereafter for multi-year projects. ESTCP will support attendance at one domestic technical meeting each year. ESTCP intends to sponsor an annual technical Symposium in the Washington, D.C. area. Investigators are encouraged to budget for students working on the project to attend the Symposium in the total travel costs. In years when the Symposium takes place, investigators are expected to attend. In the event the Symposium is not held, investigators may attend an appropriate meeting of their choice at comparable cost.

8. Publication and Report Costs: Estimate the costs of publishing and reporting results, including the direct charges for clerical preparation, page or illustration charges, and distribution. The ESTCP reporting requirements are found on the ESTCP website. Include a separate itemized list using the fifth tab of the cost spreadsheet template located on the ESTCP website.

9. Contractor Manpower Reporting Application (CMRA): Estimate the costs to comply with CMRA. The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for ESTCP via a secure data collection site. The contractor is required to completely fill in all required data fields on the ECMRA website. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the fiscal year, all data shall be reported no later than October 31 of each calendar year. Contractors may direct questions to the ECMRA help desk.

10. Fixed Fee: Eligible organizations shall list the fixed fee, if any, applied to the demonstration project. Indicate in the footnote to the table the cost elements included in the basis for the fixed fee.

11. Cost by Task Summary Table: Provide a breakout of cost per task. The sixth tab in the cost spreadsheet located on the ESTCP website provides a template. These numbers must match those on the main cost spreadsheet.

APPENDICES

Appendices are not included in the page count for the full proposal.

1. Required, if literature is cited, Literature Citations: Provide literature citations for any material cited in the technical section or the supporting technical data.

2. Required, Abbreviated Curricula Vitae (CV) (3 pages or less per CV): CVs are required for all key technical personnel at the lead organization and the lead individual for all key co-performers or subcontractors.

3. Optional, Letters of Support: If you have received letters of support or commitment from installations or site managers, provide them in this section.

4. Optional, Supporting Technical Data (limited to 5 pages): Include data sheets, charts, and excerpts from referenced research.

1.

SUBMITTAL INSTRUCTIONS

Proposals are submitted via the SERDP and ESTCP Management System (SEMS). No electronic mail, faxed, or hard copy proposals will be accepted. Proposals must be submitted prior to 2:00 p.m. Eastern Time on September 12, 2019.

Complete all steps below in order to submit a proposal.

· Create a single PDF file that contains all required sections outlined in the proposal guidance.

· Log in to SEMS.

· Enter all required proposal details into SEMS. Proposal details may be saved and edited prior to final submission.

· Download or print the “Proposal Details” page. This must be signed by an individual with the authority to commit the lead organization to execute the proposed work. The document may be electronically or hand-signed. Ensure all information on the signed summary matches the proposal file.

· Upload the signed “Proposal Details” page.

· Add the system-generated proposal number, project title, lead PI name and organization to first page of proposal as instructed in Section 1.1 above.

· Upload the final proposal file.

· Submit the proposal. Only proposals that have been submitted will be considered. Proposals with a “Saved” status will not be reviewed.

Once the proposal has been submitted, SEMS will display an on-line confirmation message and will send an email notification to the proposer. It is the sole responsibility of the proposer to make certain the proposal is properly received by ESTCP.

The proposer may continue to modify proposal details and upload revised proposal files until the due date. Prior versions of the proposal will be over-written and only the last version uploaded will remain in the system. Ensure the proposal details entered into the system match the contents of the PDF proposal file. It is recommended that proposals are uploaded as early as possible prior to the deadline, to ensure a successful and timely submission.

For proposal upload questions, contact the ESTCP Office at 571-372-6565.

EVALUATION FACTORS FOR PROPOSALS

The following evaluation factors will be the sole basis for reviewing proposals submitted in response to this BAA. ESTCP Relevance and Technology Maturity are pass/fail criteria; proposals not passing these gates will not be further evaluated. Among the other evaluation factors for proposals, Technical Merit is more important than Cost/Benefit of Technology, Transition Potential, and Cost of Proposal.

ESTCP RELEVANCE

An assessment will be made whether the proposal submission responds to the DoD environmental requirement as described in the topic area. ESTCP Relevance is a threshold review and if the proposal is determined not to be relevant, no further evaluation of the proposal will be made.

TECHNOLOGY MATURITY

An assessment will be made of the appropriateness of the proposed technology for demonstration and validation. Proposed technologies should have completed required proof-of-concept work and have evidence of the technology’s capabilities. Technologies should be mature enough that within one year of project initiation any required laboratory treatability work will be completed and a field ready application can be deployed for testing. Standard commercially available instruments or approaches currently deployed at DoD sites will be considered too mature. ESTCP will not consider project submissions that fall in the categories of basic research (scientific foundation) or exploratory development (bench-scale applied research). Technology Maturity is a threshold review and if the proposed technology is determined to be inappropriate for demonstration and validation, no further evaluation of the proposal will be made.

TECHNICAL MERIT

An assessment of the technical merit of the proposal will be made. Factors to be considered include: (a) the methodology is scientifically sound; (b) the technology is innovative and is the current state-of-the-art; (c) the technical risks are well characterized; and (d) the technical team is qualified to execute the proposed project.

COST/BENEFIT OF TECHNOLOGY

An assessment of the cost/benefit of the proposed technology, if it were deployed, will be made. Factors to be considered include: (a) the projected cost savings and/or risk reduction are significant; (b) the projected benefits are reasonable and consistent with the proposed technology; and (c) the payoffs from the proposed technology are commensurate with the projected costs and risks.

TRANSITION POTENTIAL

An assessment of the potential for a successful transfer of the technology to the DoD user will be made. Factors to be considered include: (a) there is a well-defined DoD user for the technology; (b) there are clearly identified activities that will support and enhance the transfer of the technology; and (c) the technology can be implemented within DoD.

COST OF PROPOSAL

Cost realism and reasonableness may also be considered during the selection of acceptable proposals in accordance with FAR 35.016(e). Costs should be appropriate and traceable to the level of effort required to execute the project.

Requirements for proposals Selected for Funding Please be aware of the following requirements for proposals that are selected for funding. These requirements are considered part of the proposal process and the associated costs are to be borne by the proposer.

REVISED PROPOSAL

Proposals selected for funding may require revision following the selection process and prior to contract award. Common revisions include adjustments to schedule, task structure, funding profile, or specification of required deliverables.

SUBCONTRACTING PLAN

The Subcontracting Plan is not required at the proposal stage. If your proposal is selected for funding, you may be required to submit a Subcontracting Plan if the criteria below apply to your proposal. In accordance with the Federal Acquisition Regulation (FAR) Subpart 19.7, all businesses, other than small business concerns are required to submit a subcontracting plan for contract proposals that exceed $700,000. The subcontracting plan should reflect realistic, challenging, achievable positive percentage and dollars goals for subcontracting with Small Business concerns. The subcontracting plan must address a goal for each of the statutory required elements: Small Business, Small Disadvantaged Business, Woman-Owned Small Business, Service-Disabled Veteran-Owned Small Business, Veteran-Owned Small Business, and Historically Underutilized Business Zones. The Subcontracting plan must be reviewed, negotiated and accepted by the Contracting Officer and Deputy of Small Business/Small Business Administration prior to contract award. The Small Business Subcontracting Plan shall be prepared in accordance with FAR 52.219-9 Small Business Subcontracting Plan. (DEVIATION 2018-O0018) and elements as described in the checklist in DFARS PGI 219.705-4. Additional information can be found on the Department of Defense Office of Small Business Programs website. The U.S. Army Corps of Engineers, Humphreys Engineer Center Support Activity (HECSA) Small Business Office website provides information on how to prepare a subcontracting plan, along with links to find small businesses to participate. For guidance on creating an acceptable subcontracting plan or for information on locating small business concerns, contact the HECSA Small Business Representative at HECSASmallBusinessProgram@usace.army.mil or 703-428-7385.

ACCOUNTING AND AUDITING REQUIREMENTS

ESTCP projects are generally awarded as cost-type contracts. To be eligible for such an award, a contractor must have an approved accounting system and an accepted up-to-date government audit. Details on these requirements can be found at the web sites for Defense Contract Audit Agency and Defense Contract Management Agency. Contractors selected for award who do not meet these requirements should inform their program manager immediately, as the process for approval can be time consuming. In some cases, if the work is appropriate to a firm fixed price contract and requirements for a cost-type contract cannot be fulfilled, successful proposers will be given the opportunity to enter into a firm fixed price contract.

SAFEGUARDING COVERED DEFENSE INFORMATION AND CYBER INCIDENT REPORTING

DFARS Clause 252.204-7012 Safeguarding Covered Defense Information and Cyber Incident Reporting (OCT 2016) as prescribed in DFARS 204.7304(c) is a mandatory clause that will be included in all ESTCP contracts. DFARS 204.7304(c) reads:

“(c) Use the clause at 252.204-7012, Safeguarding Covered Defense Information and Cyber Incident Reporting, in all solicitations and contracts, including solicitations and contracts using FAR part 12 procedures for the acquisition of commercial items, except for solicitations and contracts solely for the acquisition of commercially available off-the-shelf (COTS) items.”

Most ESTCP projects do not result in defense covered information. A written determination will be made by the ESTCP office at final project acceptance for those that do. However, any resultant contract will not include addendums or local text regarding this mandatory clause.

4BAA Supplemental Solicitation