A21_RFP_Amentment_1.pdf
PDF 669 KB Posted
- Solicitation number
- W912HQ18R0010
About this file
RFP Amendment 1
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 2018_Visit_Auth_DLL_blank(002)_(002).xlsx | XLSX spreadsheet | |
| A21_RFP_Q&A_18R0010_revised_23_Aug_18.pdf | ||
| A21_RFP_Q&A_18R0010.pdf | ||
| A21_Attachment__5_Subcontracting_Plan_Template_for_Offerors.docx | DOCX document | |
| A21_Attachment__2_Live_Task_Order_PWS.docx | DOCX document | |
| A21_Attachment__3_NAVFAC_USACE_Past_Performance_Questionnaire.docx | DOCX document | |
| A21_RFP_SF33_W912HQ18R0010.pdf | ||
| A21_Attachment__4_Small_Business_Participation_Plan.docx | DOCX document | |
| A21_Attachment__6__Level_of_Effort_for_Live_Task_Order_Response.xlsx | XLSX spreadsheet | |
| A21_Attachment__1_Labor_Rates_&_Total_Evaluated_Price_for_the_Live_Task_Order.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83)
Prescribed by GSA
FAR (48 CFR) 53.243
See Summary of Changes in the continuation page below .
1. CONTRACT ID CODE PAGE OF PAGES
J 1 28
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 20-Aug-2018
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W912HQ18R0010
X 9B. DATED (SEE ITEM 11)
30-Jul-2018
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE
RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
20-Aug-2018
CODE
USACE HUMPHREYS ENGR CTR SPT ACTIVITY
ATTN: CECT-HC,
7701 TELEGRAPH ROAD
ALEXANDRIA VA 22315-3860
W912HQ 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W912HQ18R0010
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE
The following have been added by full text:
AMENDMENT 1 TEXT
The purpose of this amendment is to address questions received in response to this Request for Proposals (RFP). The following changes were made to this RFP:
1. The contract level Performance Work Statement (PWS), the Proposal Submission Instructions (Section L), and the Basis for Award (Section M) include additional and revised language. Text that has been added or revised has been highlighted in yellow.
2. The small business subcontracting plan and small business participation plan (Factor 3) are now required to be submitted with Volume II.
3. The following text was deleted from the RFP:
Section M, A. Basis for Award: “Options. The Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. The Government may determine that an offer is unacceptable if the option prices are significantly unbalanced. Evaluation of options shall not obligate the Government to exercise the option(s).”
Section M, B. Factors and Sub-factors to be evaluated: “For evaluation purposes only, the estimated quantity of labor hours will be used to determine the total evaluated price for the Labor CLINs. The Government will evaluate price proposals based upon a Total Evaluated Price (TEP) for the base year and all option years combined.”
4. The attached Questions & Answers response is incorporated by reference.
SECTION C - DESCRIPTIONS AND SPECIFICATIONS
The following have been modified:
PERFORMANCE WORK STATEMENT
Performance Work Statement (PWS)
SERDP & ESTCP Support
1 OBJECTIVE
The Strategic Environmental Research and Development Program (SERDP) and the Environmental Security Technology Certification Program (ESTCP) require program support to execute their missions of developing and demonstrating technologies that meet the Department of
Defense (DoD) environmental requirements. SERDP and ESTCP are separate programs that are managed through a joint program office. Support is needed at the program level and in each of the technical areas in which SERDP and ESTCP invest.
2 BACKGROUND
SERDP is a multi-agency research and development program that was established by Congress in 1991. As described in Title 10, U.S.C. Sections 2901-2904, the major focus of SERDP is to “address environmental matters of concern to the Department of Defense and the Department of
Energy through support for basic and applied research and development of technologies that can enhance the capabilities of the departments to meet their environmental obligations.” SERDP supports environmental research and development activities in government, industry, and academic laboratories in the areas of Environmental Restoration, Munitions Response, Weapons
Systems and Platforms, and Resource Conservation and Resiliency.
ESTCP is a DoD demonstration and validation program for environmental and energy technologies. The DoD established ESTCP in fiscal year 1995. ESTCP demonstrates and validates innovative technologies that target DoD’s most urgent environmental needs and are projected to pay back the investment through cost savings, increased efficiency, and improved environmental outcomes. The program provides funding to government, industry, and academic institutions to conduct demonstrations in the areas of Environmental Restoration, Munitions Response, Weapons
Systems and Platforms, Resource Conservation and Resiliency, and Installation Energy and Water.
Details about the program structure, current SERDP and ESTCP projects, examples of solicitation documents, project requirements, and examples of program outreach can be found on the joint
SERDP and ESTCP web site, www.serdp-estcp.org.
3 TYPE OF SUPPORT
The required services are expected to break out as roughly:
1. Technical Review of Proposals and Documents: 35%
2. Direct Support to Program Areas: 30%
3. Administrative and Financial: 15%
4. Meeting Planning, Logistics and Support: 10%
5. Outreach: 10%
All personnel shall be qualified by education and experience appropriate to perform their assigned tasks. The following key personnel are essential to management and oversight, and shall meet the minimum specific qualifications outlined.
Project Manager: The project manager shall have a minimum of 7 years’ experience in project management, including 3 years’ experience managing a team of the size and diversity of skills needed to perform the work described. The project manager shall have experience with government management of research and development, as well as familiarity with the structure and management of the DoD. The project manager must have http://www.serdp-estcp.org/ sufficient technical training so as to be capable of managing and assuring the technical quality of the support provided, including technical reviews.
Information Technology Specialist: Three essential elements of the work described below are the online project management system, the online proposal management and evaluation system, and the SERDP and ESTCP joint web site. To manage these elements, the contractor must demonstrate that the individual in the role of providing oversight for the information technology enterprise has expertise in state of the art hardware and software, including experience in web site management, database management, on-line reporting and management systems, acceptance and management of electronic proposals or similar documents, and the appropriate security protections.
Technical Reviewers: The contractor shall provide technical review of documents and proposals as required by SERDP and ESTCP. Effective technical review will require personnel with expertise in a wide variety of technical topics including environmental engineering, ecology, materials science, chemistry, energetic materials, electromagnetics, underwater acoustics, contaminated groundwater and sediments, munitions constituents, energy efficiency technologies, cybersecurity, renewable energy, and microgrids. As the SERDP and ESTCP portfolios evolve, additional expertise beyond this list may be required. The technical reviewers shall have advances degrees (generally a Ph.D. or a MS with 5+ years of experience) in their specified technical areas. Reviewers shall have sufficient familiarity with the environmental requirements of the DoD to make recommendations as to the technical merit of proposed and ongoing work, and its value to the DoD.
4 GENERAL REQUIREMENTS
This section describes the general requirements for this effort. The following sub-sections provide details of various considerations on this effort.
4.1 Non-Personal Services
The Government shall neither supervise contractor employees nor control the method by which the contractor performs the required tasks. Under no circumstances shall the Government assign tasks to, or prepare work schedules for, individual contractor employees. It shall be the responsibility of the contractor to manage its employees and to guard against any actions that are of the nature of personal services, or give the perception of personal services. If the contractor believes that any actions constitute, or are perceived to constitute personal services, it shall be the contractor's responsibility to notify the Procuring Contracting Officer (PCO) immediately.
4.2 Business Relations
The contractor shall successfully integrate and coordinate all activity needed to execute the requirement. The contractor shall manage the timeliness, completeness, and quality of problem identification. The contractor shall provide corrective action plans, proposal submittals, timely identification of issues, and effective management of subcontractors. The contractor shall seek to ensure customer satisfaction and professional and ethical behavior of all contractor personnel.
4.3 Contract Administration and Management
The following subsections specify requirements for contract, management, and personnel administration.
4.3.1 Contract Management: The contractor shall establish clear organizational lines of authority and responsibility to ensure effective management of the resources assigned to the requirement.
4.3.2 Contract Administration: The contractor shall establish processes and assign appropriate resources to effectively administer the requirement. The contractor shall respond to Government requests for contractual actions in a timely fashion. The contractor shall have a single point of contact between the Government and Contractor personnel assigned to support contracts or task orders.
4.3.3 Personnel Administration: The contractor shall provide the following management and support as required. The contractor shall provide for employees during designated Government non-work days or other periods where Government offices are closed due to weather or security conditions. The contractor shall maintain the currency of their employees by providing initial and refresher training as required to meet the PWS requirements. The contractor shall make necessary travel arrangements for employees. The contractor shall provide necessary infrastructure to support contract tasks. The contractor shall provide administrative support to employees in a timely fashion (time keeping, leave processing, pay, emergency needs).
4.4 Subcontract Management
The contractor shall be responsible for any subcontract management necessary to integrate work performed on this requirement and shall be responsible and accountable for subcontractor performance on this requirement. The prime contractor will manage work distribution to ensure there are no Organizational Conflict of Interest considerations. Cross teaming may or may not be permitted.
4.5 Contractor Personnel, Disciplines, and Specialties
The contractor shall accomplish the assigned work by employing and utilizing qualified personnel with appropriate combinations of education, training, and experience. The contractor shall match personnel skills to the work or task with a minimum of under/over employment of resources. The contractor shall ensure the labor categories as defined in the Labor Categories document (see Appendix A), labor rates, and man-hours utilized in the performance of each task order issued hereunder will be the minimum necessary to accomplish the task.
4.6 Location of Work
Accomplishment of the results contained in this PWS requires work primarily at the contractor’s and subcontractor’s location, with occasional domestic travel to be determined at the task order level. The administrative tasks described in Section 5.1.10 will be performed on-site at the SERDP and ESTCP Office. The Program Area Support tasks described in Section 5.2 will require approximately bi-weekly visits to the SERDP and ESTCP Office.
4.7 Travel / Temporary Duty (TDY)
Travel to government facilities or other locations may be required and will be specified in the individual task order PWS. All travel requirements (including plans, agenda, itinerary, or dates) shall be pre-approved by the government (subject to local policy procedures), and is on a strictly cost reimbursable basis. Costs for travel shall be billed in accordance with the regulatory implementation of Public Law 99-234 and FAR 31.205-46 Travel Costs.
5 PERFORMANCE REQUIREMENTS
The contractor shall provide comprehensive technical, programmatic and administrative support services for the SERDP and ESTCP Office in the Washington, D.C. area. The contractor shall provide services to the Executive Director and his staff to meet all program planning, technical and financial oversight and management needs to the two programs. This includes support for the
Program Office located in Alexandria, VA.
5.1 Program Level Support
5.1.1 Web-Based Reporting System: The contractor shall support and maintain a web-based project tracking system for approximately 350 active SERDP and ESTCP projects. The incumbent contractor currently maintains the SERDP and ESTCP Management System
(SEMS), which is used to track technical and financial status of projects, contract actions, document status, financial planning and distribution. The contractor shall adhere to security plans for SEMS according to industry best practices. Specific details concerning operating platforms and content management systems will be provided at contract award. All relevant software code will be provided to the contractor at that time as required.
5.1.2 Solicitation: The contractor shall administratively manage one annual solicitation each for SERDP and ESTCP, as well as additional special solicitations as needed. Tasks include (a) assisting with updating and preparation of proposal submittal instructions and announcements; (b) administratively supporting the integration of technical input to the annual Statements of Need (SONs) and topic areas; and (c) disseminating outreach materials describing the solicitations, including but not limited to the SERDP and ESTCP joint web site, ListServe, and support of a webinar. The contractor shall support special studies and workshops as needed for solicitation development.
5.1.3 Proposal Management and Selection: The contractor shall provide technical and programmatic support to execute the SERDP and ESTCP solicitations. Both programs request a brief pre-proposal that is the basis for requesting or not requesting a full proposal.
Tasks include maintaining an electronic proposal submittal and tracking system;
administrative assistance with drafting selection plans and procedures, and associated documentation; administrative assistance with technical evaluations of proposals; and drafting and disseminating notification to proposers.
5.1.4 Information Requests and Programming Actions: The contractor will assist the director in responding to requests from the Office of the Secretary of Defense, the Congress, the
General Accountability Office, and other similar requests. The contractor shall assist in drafting and maintaining budget exhibits (R-2/R-3/R-4).
5.1.5 Financial: The contractor shall provide assistance to the director and financial officer.
Tasks include assisting with the preparation of funding documents; tracking execution of ~200 projects; and tracking the status of approximately 200 invoices per month.
5.1.6 SERDP Scientific Advisory Board (SAB): The contractor shall provide technical and program support to the director in managing the SAB. The SAB is a Federal Advisory Committee governed by the Federal Advisory Committee Act (FACA) that meets four times per year. Tasks include development and distribution of agendas and read-ahead materials for SAB meetings; meeting site selection and logistics; on-site support; recording and tracking action items from meetings; recording official minutes; maintaining correspondence and schedule for membership appointments; assistance with preparing the annual FACA report; and meeting all other FACA requirements.
5.1.7 SERDP Annual Report: The contractor shall assist with drafting the SERDP Annual Report, as required by Statute. Tasks include assembling all current year and planned future year investments and activities and drafting a summary of SAB activities for the year of the report.
5.1.8 Document Management: The contractor will track the status of all documents associated with SERDP and ESTCP projects, including receipt, review, revision, submission for clearance, and posting to the joint web site and DTIC. Document status shall be tracked electronically in a web-accessible format that is easily accessed by federal program staff.
The contractor shall prepare DoD forms to clear documents for public release and interact with the reviewing office in DoD.
5.1.9 Special Studies and Analyses: The contractor shall provide technical and administrative support to meet the needs of SERDP and ESTCP in response to information requests, program development, technology transfer, and collaboration.
5.1.10 Administrative Support: The contractor shall provide the administrative support needed to execute the requirements set forth in this PWS. Tasks will include assistance with correspondence, preparation and tracking of packages for OSD, assistance with travel planning, preparation and transmittal of contracting packages, maintenance of office files, interaction with DoD security and building management, interaction with DoD IT staff, and maintenance of an annual master program schedule.
5.2 Program Area Direct Support
The contractor shall provide direct support to each Program Area under SERDP and ESTCP. The direct support will involve assisting the Program Manager throughout the life-cycle of investments, including solicitation planning, proposal review and selection, tracking project execution, and ending with technology transfer. Each Program Area requires a designated support staff possessing excellent executive management skills in order to assist with the management of a multitude of deliverables, meetings, and information requests. Specific support activities that are required are described in the following sections.
5.2.1 Manage Project Selection Process: An annual solicitation is released each year under both SERDP and ESTCP. Historically, approximately 800-1000 pre-proposals and 250 full proposals are received for the combined solicitations. Within each Program Area, the contractor shall administratively manage the project selection process, to include the following:
Assist the Program Manager with the development of the Program Area’s solicitation topic.
Coordinate the technical review of submitted proposals, as described in Section
5.1.3, including assisting with the selection and notification of peer reviewers, and interfacing with Technical Review Committees.
Assist with the development of response letters to Principle Investigators (PIs).
Assist with the organization of selection meetings, including developing agendas, interfacing with PIs, collecting presentations in advance, and conducting the meeting.
5.2.2 Project Technical and Financial Tracking: The PI for each project is required to submit specific technical and financial information to the SERDP and ESTCP Office. Technical and financial information is summarized in a number of different reports and includes the following:
Monthly financial reports (MFRs) (required of all projects)
Quarterly progress reports (QPRs) (required of all projects)
Demonstration Plan (required for all ESTCP projects)
Interim Report (at least one required for all core SERDP projects)
Final Report (required for all projects)
Miscellaneous project-specific reports
Historically, excluding the MFRs and QPRs, a total of approximately 700 documents are received in a year. The contractor shall track technical and financial information through every step of the review process as described in Section 5.1.8, including the following:
Review the database for delinquent reports and contact lead investigators regarding delinquent reports as necessary.
Enter tracking information into a database for all documents excluding MFRs and QPRs.
Coordinate the technical review of documents as needed.
Incorporate technical reviewer comments into response letters to the PI for Program Office review as needed.
5.2.3 Manage Technical Progress Meetings: All SERDP and ESTCP PIs are required to attend an in-person meeting on an annual basis to provide an overview of project results to the
Program Office. The contractor shall manage these technical progress meetings, to include the following:
Track projects to ensure they attend progress meetings on the appropriate schedule.
Assist the Program Manager in the development and distribution of meeting agendas.
Interface with PIs and the Technical Review Committee to communicate logistical details.
Collect final presentations from PIs.
Assist with the development of response letters to PIs after the meeting.
Assist with conducting the meeting.
5.2.4 Represent Program Office at Technical Conferences: The Program Office attends approximately 10 national conferences per year and displays a booth at these meetings to highlight the Programs and encourage future participation in the solicitation process. The contractor shall attend these conferences, maintain and display the booth, and answer questions from conference attendees about SERDP and ESTCP.
5.2.5 Other Duties: The contractor shall provide additional direct support to the program areas in responding to data requests, maintaining orderly and up to date project information in SEMS and tracking deviances, planning and attending program area-related meetings, tracking project contracting actions and funding distributions, and attending and documenting other project-related calls and meetings including kick off calls and final project summary briefings.
5.3 Technical Review
The contractor shall provide technical review of documents and proposals as required by SERDP and ESTCP. Effective technical review will require personnel with expertise in a wide variety of technical topics including environmental engineering, ecology, materials science, chemistry, energetic materials, electromagnetics, underwater acoustics, contaminated groundwater and sediments, munitions constituents, energy efficiency technologies, cybersecurity, renewable energy, and microgrids. As the SERDP and ESTCP portfolios evolve, additional expertise beyond this list may be required.
The technical reviewers shall have advanced degrees (generally a Ph.D. or a MS with 5+ years of experience) in their specified technical areas. Reviewers shall have sufficient familiarity with the environmental requirements of the DoD to make recommendations as to the technical merit of proposed and ongoing work, and its value to the DoD.
Specific support activities required are described in the following sections.
5.3.1 Demonstration Plans and Reports: Each SERDP and ESTCP project is required to submit a number of technical reports over the life of the project. These include:
Demonstration Plans (required for all ESTCP projects), Interim Reports (at least one required for all core SERDP projects), Cost & Performance Reports (required for all ESTCP projects), Final Reports (required for all projects), and
Miscellaneous project-specific reports.
Historically, a total of 700 of these documents are received in a year. The contractor shall engage subject matter experts for an independent, critical review of each submitted document. The normal turn-around time expected for these reviews is three weeks, although the vagaries of field site availability or weather windows may require a shorter turn-around in a limited number of cases.
5.3.2 Pre-proposals and Proposals: Both SERDP and ESTCP release an annual solicitation of proposals. Historically, approximately 800-1000 pre-proposals and 250 full proposals are received in response to these solicitations.
For each pre-proposal, the contractor shall provide a review to evaluate relevance and feasibility, and will offer technical advice to support SERDP and ESTCP in deciding whether to request a full proposal.
For each full proposal requested, the contractor shall arrange for peer review by three to five outside experts identified by the contractor and approved by the
Director.
For each proposal recommended by the peer reviewers, the contractor shall summarize the review comments and provide technical advice to the Program
Manager to support a decision on whether to fund the proposal.
The technical experts who review the proposals may be required to support the Program Manager at a Technical Committee selection meeting and subsequent In- Progress Reviews.
5.3.3 New Technical Challenges and Modifications to Existing Program Areas: As the environmental challenges confronting the DoD evolve, SERDP and ESTCP evolve to meet these challenges. This may take the form of modifications to the emphasis of existing
Program Areas or the establishment of new Program Areas. Often these changes are accomplished by convening a workshop of technical experts to assist SERDP and ESTCP in defining requirements and drafting a research strategy in response to these requirements.
As needed, the contractor shall identify technical experts in any new area identified by the
Director of SERDP and ESTCP, vet these experts, and make them available to support workshops and planning sessions. Subsequent to any modifications to SERDP and ESTCP, these technical experts, or others similarly qualified, shall be available for proposal and document review as described above.
5.4 Meeting Planning, Support and Logistics
5.4.1 The contractor shall provide support for program meetings as listed below. Tasks will include assistance with developing and distributing agendas and read-ahead materials, receipt and organization of presentations, identifying and procuring space, on-site meeting support, note taking, and summarizing and documenting action items. The contractor shall be capable of supporting on-line meetings and webinars for up to 500 people. For meetings where required (In Progress Reviews [IPRs], SAB and Selection Meetings at a minimum) , the contractor shall provide computer access for up to 20 attendees to provide real-time comments through web-based meeting software.
In-Progress Reviews (IPR): IPR meetings are held three times per year. Every core project that SERDP and ESTCP fund is required to provide an IPR presentation at least once per year. Typically, there are a total of 40-45 days of IPR meetings per year.
SAB: The SERDP SAB is required by statute to meet 4 times per year. Meetings are typically 1-2 days. Three meetings per year are held in the Washington, D.C.
area. One meeting is often held at a DoD installation and includes a tour of DoD activities relevant to SERDP.
SERDP Selection Meetings: Each of the four SERDP Program Areas holds a one-to two-day meeting to select proposals for funding annually.
ESTCP Selection Meetings: Each of the five ESTCP Program Areas holds one meeting annually to review pre-proposals. These meetings are 0.5-2 days’ duration.
The five areas also each hold one meeting to review full proposals. These meetings involve in-person presentations by proposers and are typically 2-4 days’ duration.
5.4.2 Workshops and Special Technical Meetings: The contractor shall provide technical, program, and administrative support for occasional meetings hosted by SERDP and ESTCP. Such meetings may include project reviews, technology transfer meetings, workshops, and other focused technical meetings. These meetings may vary in size from 10 to 100 participants. Tasks will include developing agendas, organizing speakers, organizing and disseminating read-ahead material, planning and acquiring space, making arrangements for hotel room blocks, providing on-site support, taking meeting notes, and drafting summary reports.
5.5 Outreach
5.5.1 Web Site: The contractor shall maintain and host the SERDP and ESTCP joint web site, keep content current, draft news stories and blogs, update and draft content for web pages, and produce pages for new start and complete projects. The contractor shall update the web site as needed, to include transfer to a new operating platform and an update of the content structure. The SERDP and ESTCP web site can be accessed at www.serdp-estcp.org.
5.5.2 Webinar Series: The contractor shall provide support for a series of regular bi-weekly webinars with a capacity of up to 500 attendees. The contractor shall be responsible for maintaining a schedule in consultation with SERDP and ESTCP staff, contacting presenters, coordinating presentations, providing all needed technical support, and recording and editing webinars for archiving on the SERDP and ESTCP web site.
5.5.3 ListServe: The contractor shall maintain the SERDP and ESTCP ListServe, which currently has approximately 15,000 subscribers, and periodically disseminate information at the direction of SERDP and ESTCP.
http://www.serdp-estcp.org/
5.5.4 Social Media: The contractor will maintain SERDP and ESTCP social media presence on
Twitter, Linked-In, Facebook, and Google+, as well as other emerging social media as appropriate. The contractor shall regularly post notices, including but not limited to new start projects, recently completed reports, awards to investigators, and significant events in the DoD related to energy and environment.
5.5.5 Newsletters: The contractor will assemble and disseminate the SERDP and ESTCP Headlines newsletter three times per year as well as Program Area specific newsletters up to once per month per Program Area. Most content is derived from materials already produced for the web site. Additional content will be required in the areas of program updates, news, and announcements.
5.5.6 Conference Support: The contractor shall represent and promote SERDP and ESTCP technical conferences relevant to the programs. Tasks include maintenance and support of an exhibit booth, preparing technical presentations, and supporting training sessions on technology implementation.
5.5.7 Technology Transfer Products: The contractor shall prepare as needed draft and final briefing slides, web pages, and written summaries of technologies, project status, demonstration results, and program accomplishments suitable for a variety of audiences, including DoD decision makers, end users, and regulators.
5.5.8 Symposium: The contractor shall provide technical and administrative support for a joint
SERDP and ESTCP Symposium to be held in the Washington, D.C. area in a major conference center. The contractor shall cover all requirements to plan, publicize and execute a national technical conference that has recently attracted 1000 to 1200 attendees.
It is expected that future symposia will be similar in format to prior symposia, including a plenary session, multiple concurrent technical sessions, poster sessions, and short courses.
Information regarding prior symposia is on the SERDP and ESTCP web site at https://www.serdp-estcp.org/News-and-Events/Conferences-Workshops.
6 PROGRAM MANAGEMENT
6.1 Contract Meetings
The contractor shall participate in meetings for program management as deemed necessary by either party. Meetings may be held virtually, at the Humphreys Engineer Center in Alexandria, VA or at the SERDP and ESTCP Office in Alexandria, VA.
6.2 Monthly Report
The contractor shall provide a monthly progress report summarizing required activities for each active task order. The report shall identify each sub-task as assigned and display performance and schedule against the work plan originally submitted in the proposal responding to each task order.
https://www.serdp-estcp.org/News-and-Events/Conferences-Workshops
7 TIMELINESS OF SERVICES
In order to maintain orderly execution at the program and project level, it is essential that SERDP and ESTCP adhere to a tight annual schedule, including but not limited to solicitation development, proposal review, project selection, project review, document review, and funding execution. The contractor shall be required to provide timely services at critical steps throughout the annual cycle. Typical requirements are:
Information Requests and Programming Actions
1-7 days
Solicitation Documents Establish schedule to deliver draft documents beginning two months prior to release
Selection Meeting Summary and Comments
One week following conclusion of the meeting
Scientific Advisory Board Action Items and Minutes
Two weeks following conclusion of the meeting
In-Progress Review Comments One week following conclusion of the meeting
Demonstration Plan Reviews Three weeks from receipt of document
Final Report Reviews Four weeks from receipt of document
8 SPECIAL REQUIREMENTS
This section describes the special requirements for this effort. The following sub-sections provide details of various considerations on this effort.
8.1 Contractor Manpower Reporting
The contractor shall report ALL contractor labor hours (including subcontractor labor hours) required for performance of services provided under this contract for SERDP and ESTCP via a secure data collection site. The contractor is required to completely fill in all required data fields using the following web address: https://dodcmra.hqda.pentagon.mil/. Reporting inputs will be for the labor executed during the period of performance during each Government fiscal year (FY), which runs October 1 through September 30. While inputs may be reported any time during the
FY, all data shall be reported no later than October 31 of each calendar year of contract/task order performance. Contractors may direct questions to the help desk at help desk at:
http://www.ecmra.mil to review user manuals and gain an understanding about the data fields that will be included in the reporting structure that is hosted at http://www.ecmra.mil/
8.2 Quality
This section describes the Quality Control components for this effort. The following sub-sections provide details of various considerations on this effort.
https://dodcmra.hqda.pentagon.mil/ http://www.ecmra.mil/ http://www.ecmra.mil/
8.2.1 Quality Control: The Contractor shall develop a quality control plan (QCP) and maintain an effective quality control program to ensure services are performed in accordance with IDIQ contract and this PWS. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s QCP is the means by which he assures himself that his work complies with the requirement of the contract.
The finalized QCP will be accepted by the Government 30 days after date of the contract award.
The Contracting Officer may notify the Contractor of required modifications to the plan during the period of performance. The Contractor then shall coordinate suggested modifications and obtain acceptance of the plan by the Contracting Officer. Any modifications to the program during the period of performance shall be provided to the Contracting Officer for review no later than 10 working days prior to effective date of the change. The QCP shall be subject to the Government’s review and approval. The Government may find the QCP "unacceptable" whenever the Contractors procedures do not accomplish quality control objective(s). The Contractor shall revise the QCP within 10 working days from receipt of notice that QCP is found "unacceptable."
8.2.2 Quality Assurance Surveillance Plan (QASP): The Government shall monitor the Contractors performance under this contract and each task order in accordance with the Government’s QASP.
9 DELIVERABLES
The contractor shall provide deliverables as described in this PWS and subsequent task orders.
Deliverables shall be specified by the government. Format and delivery schedule for deliverables are outlined as stated in the applicable section of the PWS. The table below identifies a set of deliverables that will be required under this contract. A separate deliverables section will be included in each Task Order, tailored to that particular requirement.
Number Name Frequency Quantity
A1 Monthly Report Monthly 1 Summarizes required activities for each active task order; identifies each sub-task as assigned and display performance and schedule against the work plan originally submitted in the proposal responding to each task order.
A2 Quality Control Plan
The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services.
Once 1, updated as required
Performance Requirement Summary (PRS)
Performance standards define services. The Government performs surveillance to determine if the contractor meets or does not meet these standards.
The Contractor shall submit a time and cost estimate for each proposed task order and shall submit their plan for performance of the work. At a minimum, the Contractor’s plan will include: (1) a statement of understanding the task; (2) a description of the approach to the task; (3) a list of participants by expertise; (4) level of effort estimated by labor category, e.g., program manager, project manager, technical specialist. The Government shall use these standards to determine contractor performance and shall compare contractor performance to an Acceptable Quality Level (AQL). The Acceptable Quality Level is the percentage of tasks that meet the standards listed in the table below.
ID PRODUCT STANDARD ACCEPTIBLE
QUALITY
LEVEL
METHOD OF
SURVEILLANCE
INCENTIVE
1 Prepare and submit proposals per Government provided PWSs.
Product delivered on time.
95% over all task orders
100% Review
Exercise of Option Period
2 Prepare and submit monthly invoices in accordance with the Contract.
Delivered in a timely manner and in accordance with contract clause with no more than 10% variance.
tasks
100% Review
3 Prepare and submit completed products, i.e., reports, studies, etc. As described in the Government’s
SOW.
Product delivered on time with no more than 10% variance.
Product deemed acceptable by
COR.
tasks
Direct Observation, 100% Review or Status Meeting.
ID PRODUCT STANDARD ACCEPTIBLE
QUALITY
LEVEL
METHOD OF
SURVEILLANCE
INCENTIVE
4 SERDP and
ESTCP
Proposal Solicitations;
Acceptance of
Peer Review Technical Rankings.
Product delivered on time with no more than 10% variance.
Product deemed acceptable by
COR.
95% over task
100% Review of Status Meeting
5 Program Execution Tracking/SEM
S: Completenes s and Accuracy of Data in
SEMS;
Product delivered on time with no more than 10% variance.
System Down Time less than
0.5 days/month
Direct Observation
6 Document
Reviews (Demon-stration Plans, Technical
Reports, Cost/Performan ce Reports):
On-time completion of reviews;
Acceptance of Review
Comments by
SERDP/ESTCP
Program Manager
95% of document reviews
7 Multi-media Outreach
Product delivered on time with no more than 10% variance.
Product deemed acceptable by
COR.
95% of overall tasks
Direct Observation, APPENDIX A – LABOR CATEGORIES
The following labor categories are the only approved labor categories to be used on task orders:
Project Manager (PM) - Serves as single individual responsible for formulating and enforcing work standards, assigning contract staff and schedules, maintaining regular contact with Government's Contracting Officer’s Representative (COR). Supervises all project personnel and communicates policies, procedures, and goals of the firm to these employees. The PM is responsible for the overall project plan, project performance, and client satisfaction on multiple project tasks.
Information Technology Specialist (ITS) – The ITS provides oversight for the information technology enterprise and has expertise in state of the art hardware and software, including experience in web site management, database management, on-line reporting and management systems, acceptance and management of electronic proposals, and the appropriate security protections.
Technical Reviewer (TR) – The TR is a highly qualified, nationally recognized expert in his or her field. The TR’s role review and provide written comments on pre-proposals, full proposals, demonstration plans, and final reports, as well as other occasional technical project reports. The TR will also attend In-Progress Reviews and assist in technical workshops.
Deputy Project Manager (DPM) – Oversees key tasks and directly supervises junior personnel.
The DPM is responsible for coordination, schedule, and staffing of day-to-day activities to meet program requirements.
Program Assistant 1 - Responsible for advising, assisting, performing technical work, project tracking, financial tracking, interacting with investigators, and guiding lower level employees in a broad set of tasks within a technology area.
Program Assistant 2 – Responsible for assisting in the performance of technical work, project tracking, financial tracking, and interacting with investigators to maintain project files.
Administrative/Clerical (A/C) - Assists PM and DPM by producing, administrative, fiscal, and management reports for resource planning, meetings, and client briefings. Assists with correspondence, file maintenance, FACA requirements, and day-to-day office operations. A/C staff must be knowledgeable in Microsoft Office products such as Scheduler, Word, and Excel.
Technical Specialist (TS) – Responsible for such tasks as document management, data base management, technical editing, web site maintenance, and production of outreach materials.
Financial Specialist (FS) – Assists the financial officer with the preparation of funding documents and travel. Provides regular updates on the execution status of funds.
SECTION L - INSTRUCTIONS, CONDITIONS AND NOTICES TO BIDDERS
PROPOSAL SUBMISSION
1. General Instructions:
(a) This section provides a general guidance for preparing proposals as well as specific instructions on the format and content of the proposal. The Offeror’s proposal must include all data and information requested in this section and must be submitted in accordance with these instructions. Any Offeror who submits an incomplete package may be considered ineligible for award. The proposal must be compliant with the requirements as stated in the PWS and Appendices thereto. Non-conformance with the instructions provided in this section may result in unfavorable proposal evaluation.
(b) Proposal Submission. Offerors shall submit proposals to the following address:
U.S. Army Corps of Engineers Humphreys Engineer Center Support Activity ATTN: CECT-HC (Ms. Amanda Eaton)
7701 Telegraph Road Kingman Building, Room 1B04 Alexandria, VA 22315
The package exterior should contain the solicitation number W912HQ18R0010.
Electronic submissions will NOT be accepted. Failure to submit proposals by the closing time and date designated in Block 9 of the Standard Form 33 (SF33) may result in the proposal being deemed “late” and not considered for evaluation. See FAR
52.215-1 for rules concerning submission of offers and late proposals. Proposals will not be returned (except for timely withdrawals), but will be retained by the Government for official record purposes. NOTE: When hand-carrying proposals, Offerors are advised that they must process through gate security and should account time for possible delays.
(c) Inquiries. Offerors may submit inquires, questions or comments relating to this solicitation via email to Amanda.E.Eaton@usace.army.mil within 10 calendar days from the solicitation issue date. Email subject line shall read: “Solicitation No.
W912HQ18R0010 Questions”. The Government will consider all correspondence, but will not issue individual responses; instead, if appropriate, a solicitation amendment will be issued. No questions will be accepted via phone. Individual meetings with firms will not be scheduled. Voicemails with questions and/or requests for meetings will not receive a response. Questions received after 10 calendar days from the solicitation issue date may or may not be answered.
2. PROPOSAL SUBMISSION REQUIREMENTS
mailto:Amanda.E.Eaton@usace.army.mil
The Offeror’s proposal shall consist of two volumes and each Factor will be contained in a separate tab, submitted in hard copy, with accompanying digital copies, as set forth below:
Volume No. & Title Printed Copy Maximum Pages Digital Copy
Volume I – Factors 1-
Original + 4 250* 1 CD/DVD
Volume II – Factor 3-
Original + 4 N/A 1 CD/DVD
NOTE 1: Pages that exceed the required page limitations will not be evaluated.
Additional pages over the maximum allowed will be removed or not read and will not be evaluated by the Government. The page limit is inclusive of all documentation required in Volume I, including resumes, completed past performance questionnaires, and manpower charts.
NOTE 2: No pricing information should be included with Volume I. Only include pricing information is Volume II.
a. Files shall not contain classified data. The use of hyperlinks in proposals is prohibited. Offerors are cautioned that “parroting” of the Technical requirements of the PWS with a statement of intent to perform does not reflect an understanding of the requirement or capability to perform. Offerors are responsible for including sufficient details to permit a complete and accurate evaluation of each proposal. Proprietary information shall be clearly marked.
b. Each volume shall be submitted in a separate three-ring binder. Any pages that are changed (as a result of negotiations or proposal revisions) should be of a different color and have changed information clearly marked by a vertical line in the right margin of the page. The revised pages shall be dated. Each binder shall be clearly labeled with its Title and a copy number (e.g., copy 1 of 5).
c. Printing should be single spaced. Each paragraph shall be separated by at least one blank line. A standard, 12-point minimum font size applies. Arial or New Times Roman fonts are suggested. Tables and illustrations may use a reduced font size no less than 8-point and may be landscape.
3. PROPOSAL FILES
a. Format. The submission shall be clearly indexed and logically assembled.
Each volume shall be clearly identified and shall begin at the top of a page. All pages of each volume shall be appropriately numbered and identified by the complete company name, date and RFP number in the header and/or footer. A Table of Contents should be created using the Table of Content feature in MS Word. MS Word (doc) files shall use the following page setup parameters:
Margins – Top, Bottom, Left, Right – 1” Gutter – 0” From Edge – Header, Footer 0.5” Page Size, Width – 8.5”
Page Size, Height – 11”
NOTE: 11X17 folded pages are acceptable for tables/graphic representations;
however, each 11X17 page counts as two pages.
The following additional restrictions apply:
b. File Packaging. All of the proposal files shall be compressed (zipped) into one file entitled proposal zip using WinZip version 6.2 or later, or as separate uploads in their native format, i.e. doc, xls, ppt, etc., and provided on CDs or DVDs. Zip disks are not permitted. All price breakdown information to aide in the cost/price evaluation shall be submitted in Microsoft Office Excel Read/Write format and viewable in Microsoft
Excel 2010 or higher. Each disc shall be externally labeled with the volume number, date, and the Offeror’s name. **Please note – Self extracting exe files are not acceptable. ** If the hard-copy proposal differs from the electronic version, the hard copy will govern.
c. Content Requirement. The proposal shall be prepared clearly and concisely to demonstrate that the Offeror has a complete understanding of the requirements.
Offerors shall prepare proposals on the presumption that the Government has no previous knowledge of the Offeror’s capabilities. Proposals will be evaluated only on the information specifically presented in respective submittals, with the exception of the Past Performance evaluations. When applicable, the Offeror shall cross reference to the solicitation by annotating the solicitation reference in parenthesis, (e.g., Sec C, para
4…