Section 00 10 00 Page 1
SECTION 00 10 00_revA
BIDDING SCHEDULE
ITEM
NO.
DESCRIPTION ESTIMATED
QUANTITY
U/I UNIT PRICE AMOUNT
BASE
0001 MOBILIZATION AND DEMOBILIZATION
– MAINTENANCE DREDGING IN
CHARLESTON UPPER HARBOR
1 JA JOB $_________
0002 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 2
- DANIEL ISLAND REACH
270,000 CY $_________ $_________
0003 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 3
- DANIEL ISLAND BEND
91,000 CY $_________ $_________
0004 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 4
- NAVY YARD REACH (RIGHT)
49,000 CY $_________ $_________
0005 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 6
- PORT TERMINAL REACH
33,000 CY $_________ $_________
0006 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 7
- ORDNANCE REACH
224,000 CY $_________ $_________
0007 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 8
- ORDNANCE REACH TURNING BASIN
560,000 CY $_________ $_________
TOTAL (COMBINATION OF BASE BID
ITEMS 0001-0007)
OPTIONS
0008 DREDGING OF UNCLASSIFIED
MAINTENANCE MATERIAL IN SHOAL 1
- SHIPYARD RIVER
298,000 CY $_________ $_________
DREDGING OF UNCLASSIFIED
MATERIAL TC DOCK
0009AA
MOBILIZATION AND DEMOBILIZATION
MAINTENANCE DREDGING IN JOINT
BASE CHARLESTON CHANNEL TC Dock
1 JA JOB $_________
Section 00 10 00 Page 2
0009AB DESC (Sta. 1703+90 to 1704+90) 1 JA JOB $_________
0009AC MSDDC (Sta. 1704+90 to 1720+83) 55,000 CY $_________ $_________
TOTAL (COMBINATION OF OPTIONAL
BID ITEMS 0008-0009)
TOTAL
TOTAL (COMBINATION OF ALL BID
ITEMS 0001-0009)
STATEMENT
Enter prices where space is provided for ALL items. Failure to follow this instruction may render the bid non-responsive and the bid will not be considered for award.
All bidders are advised materially unbalanced bids may be rejected as non-responsive. See FAR 52.214-19 Contract Award – Sealed Bidding – Construction.
Quantities indicated are ESTIMATED and are comprised of material within the required channel prism including the maximum optional pay slope material and allowable overdepth, as depicted on the Contract Drawings.
SECTION 00 73 00 PAGE 1